Exercises and Advanced Exercises FRCC 2008 PRESENTED BY Bob Burkard, P.E. Rocky Sease, P.E. Systems Operations Success,

Slides:



Advertisements
Similar presentations
NERC Policies Introduction
Advertisements

NAESB Coordinate Interchange
NERC TPL Standard Issues TSS Meeting #146 Seattle, WA August 15-17, 2007 Chifong Thomas.
Spinning Reserve from Load Consideration of a Trial at Xcel Energys Cabin Creek Station Presentation to CMOPS January 7, 2005 John Kueck ORNL Brendan Kirby.
Operating Reserves --- Again A Discussion Primer
Dynamic Transfers Bob WECC MIC Meeting “The Last Hurrah!”
Governor Droop Criteria
Interchange Authority Recommendations Board of Directors Meeting December 7, 2007.
FRCC Fall Compliance Workshop October , 2013
1 April 27, 2011 Southeast Tornado Event System Operator Conference September and September 25-27, 2012 Memphis, TN Rocky Williamson, SOS Chair Operations.
Unit 1: Introductions and Course Overview Administrative Information  Daily schedule  Restroom locations  Breaks and lunch  Emergency exit routes 
August 14, 2003 Blackout Final Report
Bulk Electric System Power Outages and Restoration Considerations Peter Heiman Western Area Power Administration (Desert Southwest Region) 1.
1. 11/26/2012: NERC Board of Trustees adopted CIP v5 CIP thru CIP CIP and CIP Version 5 Filing FERC requested filing by 3/31/2013.
System Operator Conference NERC Standards Review for: Simulator Drill Orientation 2014 System Operator Conferences Charlotte NC & Franklin TN SERC/SOS.
Generator Governor Frequency Response Alert
A R EVIEW OF L ARGE -S CALE R ENEWABLE E LECTRICITY I NTEGRATION S TUDIES Paulina Jaramillo, Carnegie Mellon University And Paul Hines, University of Vermont.
DRAFT – FOR DISCUSSION PURPOSES ONLY © 2014 New York Independent System Operator, Inc. All Rights Reserved. Emergency Transfer Criteria NYSRC Reliability.
Team BUSS Backup Storage Source. Team BUSS Idaho Power Company Backup Storage Source Project Title Extra High Voltage (EHV) Station Second DC Storage.
System Operator Conference Simulator Drill Orientation 2014 System Operator Conferences Charlotte NC & Franklin TN SERC/SOS Facilitator Team.
ERCOT’S COMPLIANCE ASSESSMENT PROGRAM Mark Henry Compliance Manager March 23, 2005.
1 The Effects of Integrating Wind Power on Transmission System Planning, Reliability, and Operations Phase 1 Preliminary Overall Reliability Assessment.
1 Voltage Stability and Reactive Power Planning Entergy Transmission Planning Summit New Orleans, LA July 8, 2004 Entergy Transmission Planning Summit.
FRCC Seasonal Transmission Assessment & Operational Seasonal Study Winter 2012.
Joel Koepke, P.E. ERCOT Operations Support Engineer ERCOT Experiences During Summer 2011.
ERCOT SOL Methodology for the Planning and Operations Horizons Stephen Solis 2014 OTS 1.
Module on Computation of PoC Transmission Charges
Recommendations from 2011 Southwest Outage Heather Polzin, FERC Office of Enforcement Dave Nevius, Senior Vice President, NERC Member Representatives Committee.
Applying the Distribution System in Grid Restoration/NERC CIP-014 Risk Assessment Srijib Mukherjee, Ph.D., P.E. UC Synergetic.
IEGC PROVOSIONS FOR RENEWABLE GENERATION SCHEDULING & UI SETTLEMENT 1.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N WIAB WECC Interchange Authority Backup BY LOU MIRANDA BONNEVILLE POWER ADMINISTRATION TRANSMISSION.
NERC Congestion Management Congestion Management Option 3 Vendor Meeting Julie Pierce – NERC IDCWG Chair.
Welcome New York Independent System Operator. (Pre-NYISO) Regulated Market Physical contracts Regulated industry Cost Based System Two Party Deals Bundled.
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
Cognitive Task Analysis and its Application to Restoring System Security by Robin Podmore, IncSys Frank Greitzer, PNNL.
December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.
Expert Operator Decision Making Introduction EMS User Conference Prepared By Robin Podmore, IncSys Robert Eubank, WECC Greg Lange, GCPUD Frank Greitzer,
Effect of generation loss and Frequency Response Characteristics (FRC) on tie-line flow to Southern Region under various scenarios and Target setting for.
1 Security assessment: decision support tools for power system operators James D. McCalley, Iowa State University, Ames, Iowa September.
1 Mid-Continent Area Power Pool Wind Integration Studies Edward P. Weber August 16, 2007.
ISO Outlook Summer 2005 and Beyond Senate Energy, Utilities and Communications Committee February 22, 2005 Jim Detmers Vice President of Grid Operations.
Generation assets important to the reliable operation of the Bulk Electric System What does this mean?
Bill Lewis, Compliance Team Lead NERC Reliability Working Group May 16, 2013 Texas RE Update Talk with Texas RE April 25, 2013.
Montana Energy Summit April 22, 2008 Ancillary Service – Regulating Reserves.
Project Cyber Security Order 706 Version 5 CIP Standards Potential to Adversely Impact ERCOT Black Start Capability.
Page 1 Slides for FR Technical Conference Office of Electric Reliability September 2010.
COMPLIANCE ROLLOUT Vann Weldon Compliance Training Administrator March 23, 2005 NERC FUNCTIONAL MODEL REVIEW.
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 1 Five Ways to Build a Microsoft Project Schedule Lynn Frock, PMP Phone
Dale Osborn Midwest ISO October 13, 2008 EE 590 Transmission Planning with Significant Energy Resources.
Loss of EMS Events 2015 System Operator Seminar. Training Objectives 2 System Operators will be able to identify the ERO Event Analysis Process Category.
-- Bhanu Bhushan -- < > (August, 2011)
BAL-001-TRE-01 ERCOT CPS2 R2 Waiver Regional Variance April 16, 2009 Sydney Niemeyer.
Operating Topics Part 2 Mike Oatts May 9, 2008 Transmission Customer Forum Destin, Florida Part 2 Mike Oatts May 9, 2008 Transmission Customer Forum Destin,
Impacts and Actions Resulting from the August 14, 2003 Blackout Minnesota Power Systems Conference November 2, 2003.
Restoration Concepts PEAK RC Training Classification: Confidential Version No.: 1.5 Date of Document: Document Owner/Author: B Pederson Classification:
THE POWER OF POSSIBILITY AESO current limits for Alberta-BC transfers Jeff Palermo – KEMA/AESO.
Current Nodal OS Design 1.The NMMS database will have an OWNER and an OPERATOR designation for each piece of equipment in the model. The OWNER and OPERATOR.
NERC BAL-005, BAL-006, FAC-001 Gary Nolan WECC ISAS April 20, 2016.
©2003 PJM 1 Presentation to: Maryland Public Service Commission May 16, 2003.
Reliability Standards Committee 2009 Scope and Plan Judith James Manager, Reliability Standards.
Blackstart Hugh Francis Southern Company Transmission Customer Forum September 22, 2006 Hugh Francis Southern Company Transmission Customer Forum September.
“FRCC RESTORATION PLAN (BLACKOUT & BLACK START)” - TRAINING -
NERC Published Lessons Learned
Overview of New Control Room Desk
Team Members: Kyle Jones Mark Magee Jason Rippee
ECEN 460 Power System Operation and Control
Impacts and Actions Resulting from the August 14, 2003 Blackout
Security assessment: decision support tools for power system operators
NERC Congestion Management
WIAB WECC Interchange Authority Backup
Presentation transcript:

Exercises and Advanced Exercises FRCC 2008 PRESENTED BY Bob Burkard, P.E. Rocky Sease, P.E. Systems Operations Success, International

2 Exercises

Exercise No. 1: ACE Chart variation after Generation Loss

4 Exercise No. 1: ACE Chart variation after Generation Loss Purpose The purpose of this exercise is to illustrate what happens to ACE in a simple system following the loss of generation. During this exercise you (PALCO Balancing Authority) will lose the Crawford 2 unit, a loss of ~335 MW of generation. This is a little under 7% of total online generation in the PALCO Balancing Area at the time.

5 Results: Record the following Values after the Unit Trip: Maximum Frequency Deviation: ___________ Initial Frequency Recovery due to Governor Droop: ________ Did BA meet DCS? YES/NO

6

7

8

9 Advanced Exercises

Advanced Exercise No. 1

11 Advanced Exercise No. 1 Objectives To be able to operate under emergency conditions.

12 Background Weather is normal, no storms forecast. It is 2 PM Your system Net Scheduled Interchange is 0 MW All units are on-line except the 70 MW Baker Unit and 80 MW Uxbrdg Unit The Amus unit is removed from service for emergency repairs for 48 hours. All NERC and FRCC Reliability Standards and Procedures are applicable.

13 Advanced Exercise No. 1A

EXTERNAL CHSANUXBRDGCOPMANOR COPLEY STNTONOAKDLE AMUS POOL BEAVER ASH LOCHER MOSES JENKINHOMER VEXLEY WYNHAM ELLS FARLIE GRANGE DAWSON TANTON RICTER KINCAID DOYLE 200 3* * BAKER CRWFRD AIRPRT NESTLE 230 KV 138 KV 69 KV 33 KV

15 Advanced Exercise No. 1B Transmission Supervisor reports conductor damage on Oakdale-Crawford 230 kV lines 1 and 2 – No. 1 will take 15 minutes to repair and No. 2 will take 8 hours to repair. WHAT DO YOU DO?

16

17

18 EXTERNAL CHSANUXBRDGCOPMANOR COPLEY STNTONOAKDLE AMUS POOL BEAVER ASH LOCHER MOSES JENKINHOMER VEXLEY WYNHAM ELLS FARLIE GRANGE DAWSON TANTON RICTER KINCAID DOYLE 200 3* * BAKER CRWFRD AIRPRT NESTLE 230 KV 138 KV 69 KV 33 KV

19 Cues/Patterns Lines are heavily overloaded Extreme low voltages at Ricter and Cheshan

20 Debrief What were the important cues? What patterns were recognized? What are the recommended actions? What were your greatest concerns? What other alternatives were considered?

21 Advanced Exercise No. 2

22 Advanced Exercise No. 2 Objectives To be able to plan for a system emergency.

23 Background All NERC and FRCC Reliability Standards and Procedures are applicable. The sales are non-firm contracts.

24 Advanced Exercise No. 1A You are assigned the responsibility of drafting a System Restoration Plan for your system. You have only one unit capable of blackstart – The Baker Unit. Determine the path you will use to bring start up power to the Crawford Units 1 & 2.

25 Describe Briefly the System Restoration Procedure _______________________________________________________ _______________________________________________________ _______________________________________________________ _______________________________________________________ _______________________________________________________ _______________________________________________________ _______________________________________________________ _______________________________________________________ _______________________________________________________ _______________________________________________________ _______________________________________________________ _______________________________________________________ _______________________________________________________

EXTERNAL CHSANUXBRDGCOPMANOR COPLEY STNTONOAKDLE AMUS POOL BEAVER ASH LOCHER MOSES JENKINHOMER VEXLEY WYNHAM ELLS FARLIE GRANGE DAWSON TANTON RICTER KINCAID DOYLE 200 3* * BAKER CRWFRD AIRPRT NESTLE 230 KV 138 KV 69 KV 33 KV

27 This exercise will bring Murphy’s Law into play. Here are the assumptions: A severe storm moved through the Crawford area and both Baker to Crawford 230 kV lines No. 1 and 2 are out of service for repairs. This storm precipitated a blackout. Baker is the only black start unit. Start-up Power is required for the Crawford Units 1 & 2. Write a switching order to bring startup power from Baker to the Crawford 1 and 2 Units.

28

29

30

31

32 Advanced Exercise No. 3

33 Advanced Exercise No. 3 Objectives To be able to make decisions and take appropriate action under emergency conditions.

34 Background It is 6 AM and External is purchasing 450 MW All External units are on line and all power flows and voltages are normal. All tie-lines are rated at 350 MW. The PALCO transmission system is normal and all units are on line except the 70 MW Baker Unit The weather report calls for Severe storms in the PALCO and External areas All NERC and FRCC Reliability Standards and Procedures are applicable.

35 Advanced Exercise No. 3A

EXTERNAL CHSANUXBRDGCOPMANOR COPLEY STNTONOAKDLE AMUS POOL BEAVER ASH LOCHER MOSES JENKINHOMER VEXLEY WYNHAM ELLS FARLIE GRANGE DAWSON TANTON RICTER KINCAID DOYLE 200 3* * BAKER CRWFRD AIRPRT NESTLE 230 KV 138 KV 69 KV 33 KV

37

38

39 Advanced Exercise No. 3B

EXTERNAL CHSANUXBRDGCOPMANOR COPLEY STNTONOAKDLE AMUS POOL BEAVER ASH LOCHER MOSES JENKINHOMER VEXLEY WYNHAM ELLS FARLIE GRANGE DAWSON TANTON RICTER KINCAID DOYLE 200 3* * BAKER CRWFRD AIRPRT NESTLE 230 KV 138 KV 69 KV 33 KV

41

42 Advanced Exercise No. 3C

EXTERNAL CHSANUXBRDGCOPMANOR COPLEY STNTONOAKDLE AMUS POOL BEAVER ASH LOCHER MOSES JENKINHOMER VEXLEY WYNHAM ELLS FARLIE GRANGE DAWSON TANTON RICTER KINCAID DOYLE 200 3* * BAKER CRWFRD AIRPRT NESTLE 230 KV 138 KV 69 KV 33 KV

44

45 Advanced Exercise No. 3D

EXTERNAL CHSANUXBRDGCOPMANOR COPLEY STNTONOAKDLE AMUS POOL BEAVER ASH LOCHER MOSES JENKINHOMER VEXLEY WYNHAM ELLS FARLIE GRANGE DAWSON TANTON RICTER KINCAID DOYLE 200 3* * BAKER CRWFRD AIRPRT NESTLE 230 KV 138 KV 69 KV 33 KV

47

48 Advanced Exercise No. 3E

49 Debrief What were the important cues? What patterns were recognized? What are the recommended actions? What were your greatest concerns? What other alternatives were considered?

50 Advanced Exercise No. 4

51 Advanced Exercise No. 4 Objectives You will be able to make decisions and take appropriate action under emergency conditions All NERC and FRCC Reliability Standards and Procedures are applicable.

52 Background It is 6 AM and PALCO is selling 450 MW to External All External units are on line and all power flows and voltages are normal. The PALCO transmission system is normal and all units are on line except the 70 MW Baker Unit and 80 MW Uxbrdg Unit. All tie-lines are rated at 350 MW. The weather report calls for Severe storms in the PALCO and External areas. All NERC and FRCC Reliability Standards and Procedures are applicable.

53 Advanced Exercise No. 4A

EXTERNAL CHSANUXBRDGCOPMANOR COPLEY STNTONOAKDLE AMUS POOL BEAVER ASH LOCHER MOSES JENKINHOMER VEXLEY WYNHAM ELLS FARLIE GRANGE DAWSON TANTON RICTER KINCAID DOYLE 200 3* * BAKER CRWFRD AIRPRT NESTLE 230 KV 138 KV 69 KV 33 KV

55

56

57

58

59 Advanced Exercise No. 4B

EXTERNAL CHSANUXBRDGCOPMANOR COPLEY STNTONOAKDLE AMUS POOL BEAVER ASH LOCHER MOSES JENKINHOMER VEXLEY WYNHAM ELLS FARLIE GRANGE DAWSON TANTON RICTER KINCAID DOYLE 200 3* * BAKER CRWFRD AIRPRT NESTLE 230 KV 138 KV 69 KV 33 KV

61

62

63

64

65 Advanced Exercise No. 4C

EXTERNAL CHSANUXBRDGCOPMANOR COPLEY STNTONOAKDLE AMUS POOL BEAVER ASH LOCHER MOSES JENKINHOMER VEXLEY WYNHAM ELLS FARLIE GRANGE DAWSON TANTON RICTER KINCAID DOYLE 200 3* * BAKER CRWFRD AIRPRT NESTLE 230 KV 138 KV 69 KV 33 KV

67

68

69

70 Advanced Exercise No. 4D

EXTERNAL CHSANUXBRDGCOPMANOR COPLEY STNTONOAKDLE AMUS POOL BEAVER ASH LOCHER MOSES JENKINHOMER VEXLEY WYNHAM ELLS FARLIE GRANGE DAWSON TANTON RICTER KINCAID DOYLE 200 3* * BAKER CRWFRD AIRPRT NESTLE 230 KV 138 KV 69 KV 33 KV

72

73

74

75

76

77 Advanced Exercise No. 4E

78

79

80 Advanced Exercise No. 4F

EXTERNAL CHSANUXBRDGCOPMANOR COPLEY STNTONOAKDLE AMUS POOL BEAVER ASH LOCHER MOSES JENKINHOMER VEXLEY WYNHAM ELLS FARLIE GRANGE DAWSON TANTON RICTER KINCAID DOYLE 200 3* * BAKER CRWFRD AIRPRT NESTLE 230 KV 138 KV 69 KV 33 KV OPEN

82

83

84 Debrief What were the important cues? What patterns were recognized? What are the recommended actions? What were your greatest concerns? What other alternatives were considered?

85 Advanced Exercise No. 5

86 Advanced Exercise No. 5A

87

88

89 Debrief What were the important cues? What patterns were recognized? What are the recommended actions? What were your greatest concerns? What other alternatives were considered?

90 Review of Advanced Exercises Team Decision Making

91 Bob Burkard, P.E. CONTACT INFORMATION Office: (270) Mobile: (270)