O. Napoly, ILC Industrial Forum, IPAC 201022 May 20101 Status of XFEL Module Assembly at Saclay O. Napoly, CEA-Saclay, IRFU/SACM.

Slides:



Advertisements
Similar presentations
O. Napoly, C. Madec CEA-Saclay, Irfu/SACM
Advertisements

SRF Cryomodule Assembly Facility Plans Tug Arkan AAC, May 10-12, 2005.
RF Unit Test Facility at NML & CM1 Test Plan Bob Kephart Fermilab IWLC-10 October 20, 2010.
APPLICATION OF EDMS TO XFEL CRYOMODULE ASSSEMBLY AT CEA Christelle CLOUE - Catherine MADEC.
Question 27: Outline the key steps for industrialization of machine components and the likely remaining vulnerabilities in achieving them. Achieving industrialization.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Superconducting Accelerating Cryo-Module Tests at DESY International Workshop on Linear Colliders 2010 (ECFA-CLIC-ILC Joint Meeting) Denis Kostin, MHF-SL,
Status report on “Industrialization studies” at LAL on power couplers for XFEL _____ TILC08 – Tohoku University 3-6 March 2008 Sendai - Japan G. Wormser.
Needs of a European SCRF Facility - the BIG plan Lutz Lilje DESY -MPY- DESY 11/2006 Planning Resource needs.
Summary of WG 2 - cavities W. Weingarten 15th SPL Collaboration Meeting CERN - 25/26 Nov Cavity WG.
TESLA MEETING May 2003 Frascati LINAC TECHNOLOGY WORKING GROUP Working Group Linac techology introduction Cryomodule design and Assy. Tuner issue.
Present status of TTF-cryomodules short overview Bernd Petersen DESY MKS March, 7, 2005 Main design features of TESLA-cryomodules Design changes for XFEL-cryomodule.
S. Prat SCRF meeting Fermilab April 21-25, 2008 Status report on “Industrialization studies” at LAL on power couplers for XFEL _____ SCRF Meeting Fermi.
FNAL Cavities for S1 Global Jim Kerby ALCPG 09. FNAL Deliverables Discussed in meetings 15/16 July and 10/11 Sept, and Webex and s 9/30/20092FNAL.
Type IV Cryomodule Proposal (T4CM) Don Mitchell, 16 JAN 2006.
XFEL SRF Accelerating Module Prototypes Tests at DESY Fermilab Seminar, July 21st Denis Kostin, MHF-SL, DESY.
Cryomodule Design and R&D during the EDR phase Robert Kephart With input from the T4 CM Collaboration.
1 The Design & Value Costs SRF Technology The XFEL as a Prototype Japan as a Host International Linear Collider Status Mike Harrison.
D.Proch, DESY; GDE meeting Vancouver 06 Technical systems: Cavity Report Overview on costing activities for ILC –European costing method Overview industrial.
Americas Region: T4CM Status and Plans H. Carter TD SRF Dev. Dept. July 14, 2006.
3.9 GHz Cryomodule Shipment to DESY E.Harms on behalf of the Third Harmonic Effort Team (AD & TD, with help from PPD, FESS, BS)
Harry Carter – LCFOA Meeting 5/1/06 1 LCFOA Technical Briefings: Cryomodules H. Carter Fermilab Technical Division.
Summary ( Cryomodule, Plug-compatible Interface) Norihito Ohuchi.
LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.
E. KAKO (KEK) 2009' Oct. 26 ILC KEK Global Design Effort 1 Cavity Preparation for S1-Global Eiji Kako (KEK, Japan)
Accelerator/ Medium Beta Cavities Paolo Michelato INFN Milano - LASA April 21, 2015.
Medium Beta Cavities Paolo Michelato, Paolo Pierini, and Carlo Pagani INFN Milano - LASA.
Medium beta cavities Paolo Michelato, Paolo Pierini, Carlo Pagani INFN Milano - LASA.
30 May 2007 DESY Cryomodule Discussion 1 Type 4 Cryomodule Technical Discussion Tom Peterson Compiled from various previous meeting notes and many sources.
Carlo Pagani University of Milano INFN Milano-LASA & GDE ILC and XFEL Cryomodules Preliminary thoughts for convergence ILC EDR Kick-off Meeting DESY,
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
Detail plan of S1-Global H. Hayano (KEK),
Cryomodule Assembly Facility (CAF) at Fermilab Tug Arkan (FNAL) FNAL-LBNL joint meeting on SRF Cavities and Cryomodules March 15, 2012.
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
CM2 Helium Circuit Vacuum Leak & Repair Tug Arkan, 6/18/
C.MADEC - TTC meeting E-XFEL cryomodule assembly : prototyping phase at Saclay.
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
Pierre Bosland 4 TH OF FEBRUARY 2016 COORDINATION COMMITTEE FR-SW AGREEMENT STATUS OF THE FRENCH ACTIVITIES UNDER THE RESPONSIBILITY OF CEA.
Accelerator/Technical Documentation and Breakdown Structure Dr. Felix Schlander Lead Engineer 20 April
Cryomodule Assembly Facility Fermilab Cleanroom: Assembly/Disassembly Tools Tug Arkan 1.
Vacuum experiences on XFEL Beam Position Quadrupole Units (BQU) preparation Marco Schalwat TTC Topical Workshop on SRF Cryomodule Clean Room Assembly CEA.
FNAL Cryomodule Assembly and Installation Plans Tug Arkan May 22, 2015.
Wish list from ESS Christine Darve H-ECCTD Kick-off meeting 16 March
S. Barbanotti - DESY Requirements Conformance for SRF Cryomodules Workshop 16/10/2014 – ESS, Lund XFEL cryostat main components: Quality Assurance and.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
JLAB Cryomodule Assembly Facilities Visit Report Tug Arkan, Yuriy Orlov March 26, 2012.
ILC-HiGrade annual meeting - 22 November 2010 ILC-HiGrade Meeting Cavity-Treatment at CEA Saclay (WP6) F. Eozénou.
Tests on production cryomodules Bob Kephart Sept 30, 2006.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
Third SPL Collaboration Meeting – CERN - 11 November 2009S. Chel 1 XFEL: cryomodule assembly at CEA/Saclay XFEL facility & Superconducting linac Main assembly.
J. Osborne LHeC Linac Design Issues Frank Zimmermann 10 December 2010.
WP High Beta Cavities Delivery
Status of E-XFEL Module Assembly at Saclay
Status of SCRF Accelerator Activities at CEA-Saclay
Cryomodule test stand at ESS site
WP-46 XFEL 3rd harmonic system XFEL Project Progress Report (1-2010)
Meeting for S1-Global module design Cryomodule and Cryogenics
Uppsala Commitment to ESS and FREIA Planning
Evolving an ILC focused SCRF Facility from the XFEL Infrastructure
MLC Schedule Plan Proven in-house expertise and infrastructure for fabrication, assembly, and testing cryomodules Confident in our technical expertise.
Definition of work flow for string DESY Example on critical operation
DESY experiences on education and training of cleanroom team
Accelerator Module Test Facility
UK RFD Pre-Series cryomodule
WP 3 coordination meeting Saclay May 2008
IHEP Cryomodule Status
Daresbury ESS In-Kind Contributions
XFEL cryomodule production and Reliability improvement
Presentation transcript:

O. Napoly, ILC Industrial Forum, IPAC May Status of XFEL Module Assembly at Saclay O. Napoly, CEA-Saclay, IRFU/SACM

O. Napoly, ILC Industrial Forum, IPAC May CEA contributes to the XFEL Cold Linac construction through Cavity String Assembly in Clean Room (WP9) and Module Assembly (WP3)  Accelerator Module Assembly assembly of 103 accelerator modules with 1 per week throughput ! operated by an industrial contractor on the Saclay site.

Project Timeline Our effort develops over the 3 phases: Phase 1: Preparation of Infrastructure and Tooling 2008  April 2010 Phase 2: Training and Commissioning at Saclay with XFEL Prototype Modules (PXFEL2 and PXFEL3) May 2010  mid-2011 leading to Restricted Call for Tender for Assembly Contract by end 2010 Phase 3: XFEL module assembly by ind ial. contractor mid-2011  mid-2014 O. Napoly, ILC Industrial Forum, IPAC May 20103

Industrialization Baseline Build the Assembly Tool adapted to the goal of 1 module/week – normal mode  7 workstations for 7 week assembly time – degraded mode  doubling of most workstations Review assembly procedures to avoid variations and other sources of man errors  long training phase with prototype modules  pre-industrialization phase with pre-series modules  optimize procurement of pre-fabricated parts Implement personnel safety regulations ahead of contract Implement reception and control operations in the fabrication timeline (just started) Optimize operator’s incentive vs. technical expertise: one team per module vs. one team per workstation (just started). O. Napoly, ILC Industrial Forum, IPAC May 20104

Optimisation Rationale Comply with XFEL project schedule and DESY procedures  limited room for unproven innovation Tailored to Saclay pre-existing hall layout  three buildings around a central courtyard Optimized for cost (manpower) effectiveness  7 (maybe 6) week total assembly time Optimized for assembly fluidity  alternating workstation occupation Adaptive facility towards future projects  maximum module length = 15 m O. Napoly, ILC Industrial Forum, IPAC May 20105

Phase 1: Preparation of Infrastructure and Tooling O. Napoly, ILC Industrial Forum, IPAC May 20106

O. Napoly, ILC Industrial Forum, IPAC May XFel Village Bldg 124 North 25x15 m² Bldg 126 North 40x11 m² 7 Bldg 126 South 30x17 m² 8 1 Court Yard 6b Overview of the Assembly Buildings ©GoogleMap Clean rooms Assembly halls Offices Warehouse

O. Napoly, ILC Industrial Forum, IPAC May Organisation of Work Stations 1. Clean Room Cold Coupler Area (IS04-CC-WS1) –Cold coupler assembly 2. Clean Room String Assembly Area (ISO4-SA-WS1, ISO4-SA-WS2) 3. Roll-out Area (RO-WS1, RO-WS2) –HOM adjustment, magnetic shielding, tuners,… –2Ph-tube welding, cold-mass/string connection 4. Alignment Area (AL-WS1, AL-WS2) –Cavity and quadrupole fine alignment –Coupler shields and braids, tuner electric tests 5. Cantilever Area (CA-WS1) –Welding of 4K and 70 K shields, super insulation –Insertion into vacuum vessel and string alignment 6. Coupler Area (CO-WS1, CO-WS2) –Warm couplers + coupler pumping line –Quad current leads 7. Shipment Area (SH-WS1, SH-WS2) –Instrumentation –Control operations (electrical, RF), “acceptance test” –End-caps closing, N-insulation, loading.

O. Napoly, ILC Industrial Forum, IPAC May ISO4-CC-WS1 Coupler cold part assembly (8 cavities / week) ISO4-SA-WS1 Cavity string assembly (1 string / week) Cavity washer Unpacking / packing and cleaning pieces Cavity storage ISO4-SA-WS2 2 nd week string assembly Clean Room : Work Stations

Assembly Hall : Workstations AL-WS1+2 CO-WS1CO-WS2 RO-WS1+2 CA-WS1 SH-WS1+2 Ware house 22 May O. Napoly, ILC Industrial Forum, IPAC 2010

22 May ISO 7 (class ) 28 m m x 4.72 m ISO 5 (class 100) 38 m m x 4.72 m ISO4 (Class 10) 112 m² 7.8 m x ( ) m 15.6 m Clean Room Layout

O. Napoly, ILC Industrial Forum, IPAC May Clean Room constructed (Sept’09)

O. Napoly, ILC Industrial Forum, IPAC May Clean room: Washer-Dryer (June ’09) Objective: avoid particle contamination of clean room from external envelopes All cavities with He tank, coupler cold parts and quadrupole-BPM units will be cleaned and dried externally before entering ISO4 area

O. Napoly, ILC Industrial Forum, IPAC May double rail systems, adapted from Fermilab clean room solution: total length ~45 m, 39 anchors every 1.2m, alignment < 67 µrd Objectives: ensure a good alignment of the cavities before connecting bellows ensure a good stability of cavity string during roll-out Clean Room : Railing System

O. Napoly, ILC Industrial Forum, IPAC May Assembly Halls Three Assembly Halls and Services (offices, dressing rooms, warehouse, central courtyard, etc…) are currently under rehabilitation : Hall n°1 is ready: 3. Roll-out Area (RO-WS1, RO-WS2) 4. Alignment Area (AL-WS1, AL-WS2) Hall n°2 is ready 5. Cantilever Area (CA-WS1) 6. Coupler Area (CO-WS1, CO-WS2) + offices and warehouse Hall n°3 is ready 7. Shipment Area (SH-WS1, SH-WS2) Assembly Hall and Services ready: April 2010 Central courtyard re-surfaced in June 2010.

Module Dimensions and Placeholder Module dimensions: 1.Red Girder : L = (+ 5877, ) mm 2.Cold Mass : L = (+6374, -5776) mm 3.Cavity string : L = ( , ) mm  place-holder set by the cold mass (with flanges) 22 May O. Napoly, ILC Industrial Forum, IPAC 2010

Roll-Out and Alignment Areas AL-WS2 RO-WS1 AL-WS1 RO-WS2 22 May O. Napoly, ILC Industrial Forum, IPAC 2010

Cantilever and Coupler Areas CO-WS2 CA-WS1 CO-WS1 22 May O. Napoly, ILC Industrial Forum, IPAC 2010

22 May Big Tools in Assembly Halls: Status FNAL Welding Bladders: 2 units ordered and received by DESY/MKS Girders for Vacuum vessel: 2 units ordered by DESY/MKS Traverse for cold mass: 3 units 4 Pillars: 2 sets over the rails + 2 sets for alignment Cold Mass Transfer Frame: 1 unit Cantilever system: 1 unit Electrical Transfer Vehicle: 1 unit New drawings, specific to Saclay Plant, generated by DESY/MKS (many thanks !)

Big Tools Fabrication Cantilever system with M8* (no string), 21/05/ May O. Napoly, ILC Industrial Forum, IPAC 2010

Big Tools Fabrication FNAL Transfer frame, 17/03/ May O. Napoly, ILC Industrial Forum, IPAC 2010 First Traverse (out of 3 units) + 4 sets of pillars + Frame delivered to Saclay on 1 st June (installation  1 month) Electric transfer vehicle delivered to Saclay in October 2010 Two « yellow » girders, 19/05/2010

Phase 2: Training and Commissioning at Saclay with XFEL module prototypes (PXFEL 2, PXFEL3) O. Napoly, ILC Industrial Forum, IPAC May

O. Napoly, ILC Industrial Forum, IPAC May Plans for Detailed Industrialisation Study Detailed Industrialisation Study at Saclay (EPPS) launched in March 2010, with the following deliverables: Review of Saclay hall equipments and assembly tools Participation to PXFEL3 assembly at DESY (spring 2010) Detailed study of the Clean Room tooling Detailed Industrial File (assembly routings, tooling,...) Optimization of working weeks per stations (6 weeks ?) Commissioning of Saclay infrastructure with 2 module prototypes (starting Q2-2010) Control Operations QA plans and Risk Analysis Specifications for ERP (Entreprise Resource Planning) Contract awarded to Ajilon Engineering (Adecco Group)

Phase 3: XFEL Module Assembly by an Industrial Contractor O. Napoly, ILC Industrial Forum, IPAC May

O. Napoly, ILC Industrial Forum, IPAC May Ramping up industrial assembly P1: assembly of 3 pre-series modules in sequence for training of the first ½ teams by CEA and DESY personnel, assuming 7 week assembly interleaved by 3 weeks for CMTB qualification. P2: assembly of 5 modules in parallel during a ramp-up period (P2) for training of the second ½ teams by the first ½ teams, assuming 2 week assembly per module. P3: assembly 95 modules in parallel at the rate of 1 module/week. Period 1: assembly of 3 pre-series modules, in sequence, interleaved with CMTB tests Period 2: parallel assembly of 5 modulesPeriod 3: // assembly of 95 modules 1/week

Preliminary Lessons for the ILC O. Napoly, ILC Industrial Forum, IPAC May

Rough Figures CEA will spend about 6 M€ M&S for the infrastructure, large tooling and preparation work, starting from existing buildings. Most of it is considered a long term investment (ESS, ILC, …) and only the amortization and running costs will be “billed” to E- XFEL. The ILC will need at least five such plants to reach throughput of1 module/day:  5 regional clean rooms with 1+1 rails, or a central clean room with rails with more space in between: economical vs. political optimum ? Industrial team for E-XFEL is estimated to about 30 operators and supervisors working on Saclay site. No learning curve in assembly operation is yet assumed (cf. for LHC magnet tests). O. Napoly, ILC Industrial Forum, IPAC May

Industrialization Readiness Two examples of “fuzzy” procedures to be worked out with DESY experts: 1°) Particle counting of string hardware: Particle counting is done by one operator shooting ionized Nitrogen “through” bolts, nuts, washer,… with one hand, and “counting” particles with the other hand: highly repetitive and tedious operation, shoot in the air solution !!  Investigate procuring of pre-cleaned hardware (vendors ?). 2°) Super-insulation (2K and 80K) Foil by foil super-insulation is a manpower pit : pre-cutting is done in parallel, 80 K mdoule insulation requires 7 operators for almost 1 day.  Investigate replacing by pre-fabricated blankets (like for LHC SC magnets). There are technical and economical issues. The case of the SC Quadrupole : For future projects (ESS, ILC, …) I have a VERY strong prejudice against SC quadrupole in the string. It is a (pita) huge complication to the industrialisation process (procurement, cleaning, transport through clean room, specialized supports, tools, and assembly procedures, string pumping, connection of cryogenic distribution, design and connection of current leads …). The alternatives would be 1° warm quadrupoles (cryogenics ?) or 2° a separate cryomodule with a smaller but very technical assembly plant with the BPM (politics ☺ ). O. Napoly, ILC Industrial Forum, IPAC May

Summary O. Napoly, ILC Industrial Forum, IPAC May

O. Napoly, ILC Industrial Forum, IPAC May Past and Current Activities Preparation of the Assembly Infrastructure Construction of the Clean Room Complex Civil Engineering for 3 halls and the central courtyard Procurement of the Big Tools (cantilever, girders, etc…) Procurement of Transfer Vehicle Layout of Alignment Workstations and Instruments Preparation to the Industrialization Preliminary Industrialization Study by Thales (Dec.08). “Detailed Industrialisation Study at Saclay” (Mar.-Sept.10). Assembly Training Operations: Observation of M8* string and module assembly Reception test of M8* at Saclay Participation to M3** and PXFEL1 module assembly Observation of M3**, PXFEL1, PXFEL2 string assembly Participation to PXFEL3 string and module assembly Considerable help received from DESY-MKS

O. Napoly, ILC Industrial Forum, IPAC May CEA-Saclay Milestones for WP3+9 August 2009: delivery of the Clean Room The 1 st user will be Spiral2 (12 QWR)  qualification of Clean Room. March 2010: delivery of the assembly halls and buildings April 2010: start of Detailed Industrialisation Study (EPPS, ~9 months) April-May 2010: participation to PXFEL3 string and module assembly at DESY Q2 2010: delivery and installation of the big tools at Saclay Q2 2010: disassembly and assembly of PXFEL2-3 modules (~12 months) Interleaved with transport and CMTB tests  qualification of Infrastructure End 2010: Call for Tender for String and Module Assembly Operation. Q3 2011: 3 pre-series module assembly (1 module / 2 weeks) interleaved with CMTB tests  qualification of Industrialized Production

O. Napoly, ILC Industrial Forum, IPAC May Acknowledgments Considerable help received from DESY, thanks to C. Engling, K. Jensch, A. Matheisen, M. Schmöckel, H. Weise, … and from FNAL, thanks to T. Arkan, … Thanks to my CEA colleagues: S. Berry, J.P. Charrier, P. Contrepois, S. Cozette, C. Madec, B. Visentin

O. Napoly, ILC Industrial Forum, IPAC May Acknowledgments