TPTF CIM Health Check Raj Chudgar Program Director for Market Redesign.

Slides:



Advertisements
Similar presentations
June 26, 2008 TAC Texas Nodal Market Implementation: Program Update Jerry Sullivan.
Advertisements

Program Management Office Update Janet Ply July 21, 2008.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation ERCOT Board of Directors Meeting Nodal Status Review February.
January 8, 2009 TAC Texas Nodal Program Implementation: P rogram Update Ron Hinsley.
November 1, 2007 TAC Meeting Texas Nodal Program Update Jerry Sullivan, Executive Director.
June 12, 2008 ROS SEM Go-Live procedure Linda Clarke.
Lead from the front Texas Nodal 1 Texas Nodal Market Management System Requirement Documents November 7, 2006 Sai Moorty MMS Project.
© Property of ERCOT /8/20061 TPTF ERCOT 30/60/90 day Plan Raj Chudgar, Nodal Program Manager February 20, 2006.
03/22/07 TPTF meeting ICCP Quality Codes Bill Blevins/Frank Kendall.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation Program Implementation Scenarios September 6, 2006.
1 Single Entry Model (SEM) Go-Live Update ROS Update July 16, 2009.
July 9, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan.
Market Implementation Board Presentation July – v1.1F 1 Texas Nodal Market Implementation ERCOT Board of Directors Meeting Program.
Machine to Machine Interface Update 1 Machine-to-Machine Interface Update January 10, 2007 Daryl Shing.
EDS 2 Early Delivery Systems Review and Request for Approval May 2007 John Webb.
March 20, 2008 TPTF CIM Update Raj Chudgar Program Director for Market Redesign.
Nodal COMS Update Commercial Operations Subcommittee January 13, 2009 Clay Katskee ERCOT - Market Operations Division Projects Organization.
Texas Nodal Timeline Options, TPTF Jul 11, Timeline Options Trip Doggett TPTF
Program Management Office Update Janet Ply July 21, 2008.
September 8, 2008 TPTF Nodal Core Projects Updates Nodal Project Managers.
Lead from the front Texas Nodal 1 ERCOT Nodal Program Facilities Draft Request January 22, 2007.
Lead from the front Texas Nodal 1 Texas Nodal Critical Path Update TPTF Date xxx.
March 11, 2008 Texas Nodal Market Redesign Program Commercial Operations Subcommittee.
February 5, 2009 Technical Advisory Committee Meeting Texas Nodal Program Implementation: Program Update Trip Doggett.
April 1, 2008 TPTF Quality Center Update Eileen Hall.
ROS Meeting – 05/15/081Texas Nodal Program - TPTF Update Texas Nodal Transition Plan Task Force ROS Meeting Stacy Bridges, ERCOT Thursday, 05/15/08.
January 15, 2008 Monthly Board of Directors Meeting Texas Nodal Market Implementation Program Update Jerry Sullivan.
EMS Users Conference 1 September 23rd – 26th CIM in the Network Model Management System Joel Koepke Network Model Engineer, ERCOT.
July 7, 2008 TPTF Texas Nodal Market Implementation: - Program Update - Market Readiness Update Jerry Sullivan.
Lead from the front Texas Nodal 1 Integrated ERCOT Readiness and Transition (IRT) TPTF - November 6 th, 2006.
September 25, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan.
August 25, 2008 TPTF Nodal Status Report: Projects Status Updates Adam Martinez.
Texas Nodal Market Implementation Metric Sub Group Readiness Advisor January 30, 2006.
July 10, 2008 ROS Early Delivery Systems Status – R6.3 2 Hour Test John Dumas and Jeff Gilbertson.
May 22, 2008 TPTF Texas Nodal Market Implementation Program Update Raj Chudgar.
1 Single Entry Model (SEM) Go-Live Update Special TAC Meeting (Updated) August 18, 2009.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation ERCOT Board Of Directors – August 15, 2006 TPTF Meeting August.
2009 Project Prioritization Troy Anderson ERCOT Program Management Office February 20, 2008.
Nodal Program Update Mike Cleary Sr. VP and Chief Technology Officer.
August 25, 2008 TPTF Nodal Status Report: Integrated Schedule Update Change Control Update Adam Martinez Troy Anderson.
Integrated Release Approach and Update TPTF 11/10/2008 Matt Mereness.
TPTF CIM Health Check Raj Chudgar Program Director for Market Redesign.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation Program Implementation Scenarios September 6, 2006.
17 February 2009 ERCOT Board of Directors Texas Nodal Market Implementation: Program Update Trip Doggett Sr. Vice President and Chief Operating Officer.
October 8, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan Program Director, Market Redesign.
November 29, 2007 TAC Meeting Texas Nodal Program Update Jerry Sullivan, Executive Director.
September 22, 2008 TPTF Nodal Status Report: Project Status Updates Nodal Project Managers.
PMO Update to PRS Troy Anderson ERCOT Program Management Office June 17, 2010.
August 11, 2008 Texas Nodal - Integrated Schedule Update Integrated Schedule Update for TPTF Janet Ply.
Market Redesign Update ERCOT Board of Directors Meeting April 18, 2006 Ron Hinsley Chief Information Officer
August 27, 2007 Executive Committee Meeting Texas Nodal Program Update Jerry Sullivan.
Lead from the front Texas Nodal 1 Reduction of MMS Vendor Effort for TPTF January 8, 2008 Murray Nixon Sai Moorty.
March 4, 2008 TPTF Texas Nodal Market Implementation EMS CIM Importer update David Hackett, EMS PM.
April 1, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan.
Lead from the front Texas Nodal 1 Early Delivery System Testing Environments & Planning – Involving Market Participants TPTF May.
October 2, 2008 TAC Texas Nodal Market Implementation: Program Update Ron Hinsley.
January 3, 2008 TAC Meeting Texas Nodal Program Update Jerry Sullivan.
June 5, 2008 TAC Texas Nodal Market Implementation Program Update Jerry Sullivan.
ROS Meeting – 06/12/081Texas Nodal Program - TPTF Update Texas Nodal Transition Plan Task Force ROS Meeting Stacy Bridges, ERCOT Thursday, 06/12/08.
6/21/2007 TPTF: Baselines 1&2 WP and CI Baselines 1 and 2 White Papers and Change Items Diran Obadina.
1 Single Entry Model (SEM) Go-Live TAC Update May 7, 2009.
Lead from the front Texas Nodal 1 Texas Nodal EDS4 - Approach 11/28/2007.
Lead from the front Texas Nodal 1 Texas Nodal Energy & Market Management System EMS/MMS Projects Requirement Documents November.
1 Single Entry Model (SEM) Go-Live Update TAC Update August 6, 2009.
October 13, 2008 TPTF Nodal Status Report: Program Update Ron Hinsley.
PMO Update to PRS Troy Anderson ERCOT Program Management Office May 20, 2010.
August 11, 2008 TPTF Early Delivery Systems Status Daryl Cote.
August 11, 2008 TPTF EDS Sequence and Durations Discussion Daryl Cote.
NMMS Nodal Network Mgmt and Monitoring System Update
Texas Nodal Program Current Schedule and Recent Changes
Presentation transcript:

TPTF CIM Health Check Raj Chudgar Program Director for Market Redesign

2 TPTF 3 Major challenge for Nodal is the successful integration of CIM data between NMMS, EMS, MMS and other Nodal systems CIM critical dependency is on successful model integration of EMS, MMS and NMMS

3 TPTF CIM Impacts on the Nodal Early Delivery Systems (EDS) EDS 2 Release 4NOMCR Checkout and Network Model Verification Current XXX EDS 3 Release 6.3LFC Testing ERCOT systemJune ‘08 XXX EDS 3 Release 7.5CRR Integration TestingJune ‘08 X EDS 4 Release 9.3Initial DAM/RUC Execution *(as discussed at last TPTF, ERCOT is implementing a workaround to start 9.3) April ’08 XXX EDS 4 Release 9.4DAM, RUC and Adjustment Period Execution May ’08 XXX EDS 4 Release 9.5Execute Full Nodal Integrated System July ’08 XXX EMS Zonal Exporter NMMS Exporter MMS Importer EMS Importer 1423

4 TPTF CIM Exporter/Importer still under development – making progress, final health check at next TPTF meeting, listed below is the current state Design/Build Exporter/Importer Design Documents Complete & Build Testing CIM Exporter or CIM Importer Test Plan Data Validation Data Model and Data Market TrialsMitigation NMMS Initial Design complete. Refactoring in progress. ERCOT NMMS testing exporter since April 2007 Data Model: updated per downstream system request. Will need to sync up data model versions in the future Data: ON GOING, waiting for EMS importer NOMCR Market Trials Model exchange with multiple vendors on- going Planning Interoperability Test with all vendors at ERCOT MMS Initial Design complete. Refactoring in progress MMS CIM importer testing since November Outstanding issues communicated to NMMS team Data Model: Few critical issues remain. MMS Application able to import NMMS Nodal Model. Will need to sync up data model versions in the future Data: ON GOING, Starting to use CIM for 9.3 Trials ABB maintaining detailed prioritized spreadsheet with all modeling and data issues. ERCOT helping define and execute CIM importer tests during MMS3 pre-FAT&FAT and MMS4 pre-FAT&FAT ERCOT performing internal due diligence of all CIM attributes necessary to execute all functions Regular conversations on the status of the CIM importer between ERCOT & ABB (technical leads, project engineers and project managers) EMS Initial Design in progress.Network Model testing in progress. Data model: Network model validation in progress. Will need to sync up data model versions in the future Data: ON GOING Not Using CIM ERCOT escalation to AREVA mgmt on delay of product ERCOT personnel planned to be at AREVA to push delivery ERCOT doing preliminary testing in parallel to reduce testing cycle ERCOT setting up hardware in advance of product delivery 123 CIM Component Measurement Items