RF strategy, limits and issues A. Butterworth L. Arnaudon, Ph. Baudrenghien, O. Brunner, E. Ciapala, W. Hofle, J. Molendijk, E. Shaposhnikova, J. Tuckmantel,

Slides:



Advertisements
Similar presentations
LONGITUDINAL (IN)STABILITY WITH BATCH INJECTION T. Argyropoulos, P. Baudrenghien, C. Bhat, J. E. Muller, T. Mastoridis, G. Papotti, E. Shaposhnikova,
Advertisements

Masahito TOMIZAWA and Satoshi MIHARA Accelerator and proton beam.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Friday, h10: Stable beams at 1.38 TeV. 09h03: Beam dump.  One bunch dropped too much in intensity and gave BPMS interlock (dump protection). 10h36:
Bunch Flattening with RF Phase Modulation T. Argyropoulos, C. Bhat, A. Burov, J. F. Esteban Müller, S. Jakobsen, G. Papotti, T. Pieloni, T. Mastoridis,
RF performance and operational issues The LHC RF team reported by A. Butterworth Special thanks: L. Arnaudon, E. Ciapala, Ph. Baudrenghien, O. Brunner,
STRIPLINE KICKER STATUS. PRESENTATION OUTLINE 1.Design of a stripline kicker for beam injection in DAFNE storage rings. 2.HV tests and RF measurements.
Sat 18/6 – Sun 19/6 07:48 Beam dump due to spurious interlock from BIS 08:30 access BIC repair. RF intervention in parallel. 13:00 Intervention on BIC.
First measurements of longitudinal impedance and single-bunch effects in LHC E. Shaposhnikova for BE/RF Thanks: P. Baudrenghien, A. Butterworth, T. Bohl,
Design and operation of existing ZS B.Balhan, J.Borburgh, B.Pinget B.BalhanDesign and operation of existing ZS SPS ZS Electrostatic Septum Upgrade Review.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
P. Baudrenghien, with contributions from L. Arnaudon, T. Bohl, O. Brunner, A Butterworth, M. Jaussi, P. Maesen, J.E. Muller, G. Ravida, E. Shaposhnikova,
G. Rumolo, G. Iadarola, H. Bartosik, G. Arduini for CMAC#6, 16 August 2012 Many thanks to: V. Baglin, G. Bregliozzi, S. Claudet, O. Dominguez, J. Esteban-
History and motivation for a high harmonic RF system in LHC E. Shaposhnikova With input from T. Argyropoulos, J.E. Muller and all participants.
AAC February 4-6, 2003 Protons on Target Ioanis Kourbanis MI/Beams.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
Elias Métral, LHC Beam Commissioning Working Group meeting, 08/06/2010 /191 SINGLE-BUNCH INSTABILITY STUDIES IN THE LHC AT 3.5 TeV/c Elias Métral, N. Mounet.
Production of bunch doublets for scrubbing of the LHC J. Esteban Muller (simulations), E. Shaposhnikova 3 December 2013 LBOC Thanks to H. Bartosik, T.
ADT re-commissioning after LS1 A. Butterworth, W. Höfle, F. Killing, G. Kotzian, T. Levens, D. Valuch with many thanks to BE/OP LBOC, ADT re-commissioning.
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
W. Hofle LIU-SPS Meeting SPS BA2 Damper LS1 Progress and plans reported by W. Hofle LIU-SPS Meeting G. Kotzian T. Levens D. Valuch.
ADT Tune Measurement F. Dubouchet, W. Hofle, D. Valuch Acknowledgement: R. Calaga, F. Roncarolo, E. Bravin, shift crews New developments and tests on August.
RF improvements over the weekend Giulia on behalf of Delphine, Philippe, Andy and many other people in the RF team LHC Beam Commissioning Working Group,
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
SPS proton beam for AWAKE E. Shaposhnikova 13 th AWAKE PEB Meeting With contributions from T. Argyropoulos, T. Bohl, H. Bartosik, S. Cettour.
1 Consequences of RF system failures during LHC beam commissioning T.Linnecar AB-RF.
Proposal to change bunch length during physics fills to assess beam induced heating after LS1 M. Barnes, P. Baudrenghien, A. Burov, S. Claudet, S. Jakobsen,
Beam loss and radiation in the SPS for higher intensities and injection energy G. Arduini 20 th November 2007 Acknowledgments: E. Shaposhnikova and all.
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
RF measurements during floating MD in Week 40 3 rd of October 2012 LIU-SPS BD WG 25/10/2012 Participants: T. Argyropoulos, H. Bartosik, T. Bohl, J. Esteban.
Stefan Wilke, DESY MHF-e 1 12th ESLS RF Meeting 1 st October, 2008 at DIAMOND Overview and Status of Assembling and Commissioning the RF-System at PETRA.
ADT kickers and amplifiers in tunnel point 4 of LHC, RB44 and RB46 1 W. Hofle LHC Transverse Damper LARP CM20 Napa April 8-10, 2013 LHC Transverse Damper.
Outcome of beam dynamics simulations - Scenarios, requirements and expected gains s LIU-SPS Coordination meeting 26/08/2015 A. Lasheen, E. Shaposhnikova,
Summary of ions measurements in 2015 and priorities for 2016 studies E. Shaposhnikova 3/02/2016 Based on input from H. Bartosik, T. Bohl, B. Goddard, V.
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
Juan F. Esteban Müller P. Baudrenghien, T. Mastoridis, E. Shaposhnikova, D. Valuch IPAC’14 – Acknowledgements: T. Bohl, G. Iadarola, G. Rumolo,
RF acceleration and transverse damper systems
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
RF interlocks for higher intensities (LMC 15 June)
Machine Coordinators: G. Arduini, J. Wenninger
Longitudinal beam parameters and stability
Friday 15th June 01:11 Injection.
Friday 18/03 07:15 Test ramp with pilot after the test of dynamic FIDEL correction. Ramp was OK, but fill was stopped due to the trip of several RQTFs.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Summary Friday h38: Ramp down and pre-cycle.
Wednesday 5th September - morning
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
The SPS 800 MHz RF system E. Shaposhnikova for BE/RF
Monday 18 October : Collimation system
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
LHC RF Status Reported by P. Baudrenghien CERN-BE-RF
Scrubbing progress - 10/12/2012
LHC Morning Meeting - G. Arduini
Summary Thursday h21: Stable beams fill #1303.
Sunday/Monday & :30 Stable beams. Fill #1851.
Beam dynamics requirements after LS2
Thursday Fill 1364 (24 bunch) dumped at 07h
Collective effects in the SPS and LHC (longitudinal plane)
Friday 28 October 2011.
LHC status - Week 35 G. Arduini, M. Lamont Main aims:
Tuesday 20 September 2011.
Mon 2/4 08:00-13:00: Access for: Experiments Power converters BBQ
Wednesday h18: 228b fill lost just before start of ramp.
Friday h55 Stable beams. Fill #1841. Lumi ~1.2e33.
Thu :00 Dumped beams, refill for Pb-Pb physics. No more protons in 2011… Some changes: Increase of flat top total voltage to 14 MV. Feed-forward.
Daniel, Gianluca and Belen (for the Collimator team)
Presentation transcript:

RF strategy, limits and issues A. Butterworth L. Arnaudon, Ph. Baudrenghien, O. Brunner, E. Ciapala, W. Hofle, J. Molendijk, E. Shaposhnikova, J. Tuckmantel, D. Valuch

Outline How to push the RF voltage at flat top – if larger longitudinal emittance is required for reduction of IBS Do we have enough available RF power – to handle increasing beam intensity? Protection of RF equipment at high beam intensity Bunch length at injection/ramp – reduce heating (kicker, collimators, cryogenics) Dipole oscillations at injection 25ns bunch spacing Conclusions

RF voltage & power on flat top Currently 12 MV (1.5 MV per cavity) – 120kW klystron power with 1.15e11 x 50ns and Q ext = 60k – increasing to around 130kW with 1.5e11 – With the present DC settings (50kV, 8A) we should not exceed ~150 kW RF to keep far enough from saturation to provide gain for the RF feedback. 150 kW 50kV, 8A J. Molendijk

Increasing the RF voltage Increasing 12MV  14MV would require Q ext =60k – already above our 150kW limit Increase Qext: – with Q ext =80k we could get 14 MV total (1.75 MV/cav) with 134 kW/klystron average. – on beam 2, cavity 3B2 is "sick" and stands 1.3 MV only – the other 7 cavities would have to provide MV, requiring 142 kW – gain in bucket area is only 8% – cf. bunch length increase from 1.2 to 1.3 ns increases emittance by 17% Change DC working point: – e.g. 58kV, 8A – saturation at 300kW – but reliability may suffer: probably more crowbar trips 58kV, 9A 200 kW

Klystron DC power issues Klystron DC working point is currently 50kV, 8A – to increase available power, need to increase HV, cathode current or both 58kV, 9A has been validated – simulation (power distribution on collector) – already run >500 hours in 2009/10 – collectors show signs of overheating – need to minimize time spent with full power on collector – reduce HV and/or cathode current when no beam (sequencer?) New collectors, improved cooling: – 4 out of 16 klystrons already modified – 4 more in Christmas stop 2011/12 – then will be able to increase voltage without risk in half of the cavities Please switch off klystrons if no beam for more than a few hours !!

RF equipment protection (1/3) Return power from high intensity beam in a tripped cavity can damage the RF equipment 200kW return power limit set as safe limit – now exceeded with 1380 bunches Must protect: – main power coupler window – circulator load – HOM couplers – klystron Wattcher LO (reflected power) Wattcher HI (fast) [SIS] (slow) Circulator load (330kW max) Circulator Klystron Cavity Main Power Coupler (ceramic window) Arc detecto r HOM coupler MC Vacuum Beam HOM Power [SIS] HOM Temperature [SIS] RF Switch Veto Generates RF Veto Generates Beam Interlock [SIS]: Software interlock Helium pressure (cavity quench) Helium level (Cryo OK) Since 17 June, all RF interlocks also generate a beam dump

RF equipment protection (2/3) This configuration leaves us open to spurious dumps… The main culprits were the Arc Detectors: – Main coupler: new electronics everywhere: shorter coincidence window new system in development with 4 redundant sensors & majority voting (end of year) investigating radiation-tolerant fibres – Waveguide: low-pass filters to reject radiation-induced pulses, seems to be successful So far we have not seen any dumps due to spurious RF trips

RF equipment protection (3/3) The current situation (all RF interlocks generate a beam dump) is conservative but safe – in case of excessive false dumps, a new firmware has been prepared for the interlock modules which would remove some of the interlocks from the beam dump chain including some useful ones (Wattcher LO, Cavity vacuum, Cryo OK) – decided not to install it unless absolutely necessary In the longer term, a rationalization of the interlock system is under study – separate RF from beam interlocks – for end of year or LS1

Bunch length in ramp Optimise blowup in LHC to reduce undershoot? – studies done in June – revisit parameters start excitation earlier? – improve update rate of BQM data Bunch length at injection – longer bunches from SPS? – blowup batch by batch on flat bottom possible in theory using (future) longitudinal feedback system not yet implemented, will take time to develop  not for this year! Bunch length on flat top – could increase target bunch length but impact on lifetime above ~1.3ns? Last 2 physics ramps before TS 1.15ns 1.1ns

Observed at injection: – amplitude grows for 5-10 minutes, then damping with a time constant ~ 30 min – quite insensitive to total intensity, number of bunches per batch and distance between batches – suggests not multi-bunch instability (but more analysis needed) – dependence on bunch length – not yet a problem for normal operation, but need to keep an eye on it Long-lasting dipole oscillations Top: Amplitude of dipole oscillation (min, max, mean over all bunches of a given batch). Bottom: Bunch length from BQM. Evolution for Fill 1, Beam1. (P. Baudrenghien et al.)

25ns bunch spacing: RF No hard limit for going to 25ns – first tests of capture gave good results – still need to analyze our data – if vacuum in IP4 is degraded, longer conditioning times

Transverse damper No issues with 50 ns bunch spacing No issues with high bunch intensity, but – automatic gain adjustment needed for efficient running at increased and different bunch intensity (settings management) Time needed for 25 ns bunch spacing commissioning: delay adjustment critical Expect less good noise performance with 25 ns (reflections on cable, addressed in future shutdowns), adaptation of signal processing if gain  20 MHz an issue Ahead: – blow-up with noise for efficient loss maps – use of damper data for MDs very useful, more work needed (efficient “data mining”)

Conclusions Ideally we change nothing… Some headroom to increase voltage, power, emittance, bunch length if necessary but need to be careful with operation of the klystrons Equipment protection at high total beam intensity: we play safe with interlocks Further improvements to controlled longitudinal blowup? 25ns bunch spacing: – No show stopper from RF – ADT needs time for setting up, expect less good noise performance

Why more tricky in 2011? Bunch Length Mean and Noise Amplitude during Ramp Situation 2011: Because the capture voltage is mismatched, the 1.5 ns long SPS bunch shrinks to ~1.20 ns after capture. With a 1.2 ns target value for bunch length, excitation must start immediately as soon as the ramp starts. We typically end-up a bit short of the demanded 1.2 ns and observe “jumps” in bunch length measurements when bunch profile changes (non-adiabatic) LBOC meeting Situation 2010: Thanks to the matched capture the bunch shape is not changed much at injection. It is ~1.5 ns at the start of the ramp. The first part of the ramp proceeds smoothly without blow- up, with adiabatic bunch length reduction till it reaches the demanded 1.2 ns.