D. Angal-KalininEUROTeV Annual Meeting, DESY30.01.2009 WP2 : Beam Delivery System D. Angal-Kalinin ASTeC, STFC, Daresbury Laboratory 4 th EUROTeV Annual.

Slides:



Advertisements
Similar presentations
ASTeC Linear Collider Activities Susan Smith. ASTeC Aims To contribute to LC accelerator R&D, positioning the UK to take a lead in delivery of significant.
Advertisements

Ongoing & Planned BDS work Deepa Angal-Kalinin ASTeC Daresbury Laboratory (CCLRC)
BDS GDE context LC-ABD2 : WP4 - Beam Line Design 12 th April 2007, LC-ABD Plenary, RHUL Deepa Angal-Kalinin ASTeC, The Cockcroft Institute.
ILC BDS Collimation Optimisation and PLACET simulations Adina Toader School of Physics and Astronomy, University of Manchester & Cockcroft Institute, Daresbury.
ILC BDS Collimation Optimisation and PLACET simulations Adina Toader School of Physics and Astronomy, University of Manchester & Cockcroft Institute, Daresbury.
European Design Study Towards a TeV Linear Collider WP 2 : Beam Delivery System Co-ordinator: Deepa Angal-Kalinin CCLRC, Daresbury Laboratory.
ATF2 Status and Plan K. Kubo ATF2, Final Focus Test for LC Achievement of 37 nm beam size (Goal 1) – Demonstration of a compact final focus.
1 ATF2 Tuning and its application to ILC and CLIC FFS/IR region ASTeC and MAN : working together on tuning methods for the ATF2 and ILC IR/extraction design.
Beam Delivery System Review of RDR(draft) 1.Overview 2.Beam parameters 3.System description 3.1 diagnostic, tune-up dump, machine protection MPS.
ILC Beam Delivery System Layout and Lattice Design Deepa Angal-Kalinin ASTeC, Cockcroft Institute Cockcroft Institute SAC th November 2006.
Global Design Effort Push-pull studies How to proceed LCWS07 June 1, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi.
ATF2 optics … 1 3 rd Mini-Workshop on Nano Project at ATF ATF2 optics, tuning method and tolerances of initial alignment, magnets, power supplies etc.
UK/EU Plans for ATF2 G.A. Blair ATF2-IN2P3-KEK kick-0ff meeting, Annecy, 8 th October 2006 Overview EUROTeV UK.
Global Design Effort Beam Delivery System => EDR LCWS07 June 2, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi Yamamoto.
Summary of WG1 K. Kubo, D. Schulte, P. Tenenbaum.
WP: Parameters and design. Plans from IFIC, Valencia Javier Resta López on behalf of the IFIC accelerator group ( IFIC (CSIC-UV),
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
Project Management Mark Palmer Cornell Laboratory for Accelerator-Based Sciences and Education.
1 Collimator Design Adriana Bungau The University of Manchester, UK Annual EuroTev meeting - Frascati, Italy, January 2008.
Feedback On Nanosecond Timescales (FONT): Robert Apsimon, Philip Burrows, Neven Blaskovic, Douglas Bett, Glenn Christian, Michael Davis, Davide Gamba,
2 nd EuroTeV Scientific Workshop, Orsay 16 th May 2006 WP2 : Beam Delivery System D. Angal-Kalinin ASTeC, CCLRC Daresbury Laboratory.
1 Collimator Design Adriana Bungau The University of Manchester, UK Annual EuroTev meeting - Frascati, Italy, January 2008.
EUROTeV WP4 Report Polarised Positron Source Jim Clarke, on behalf of the WP4 team DESY Zeuthen STFC (Daresbury and RAL) University of Durham University.
11th December 2007 LET workshop, SLAC 1 Beam dynamics issues in Beam Delivery System Deepa Angal-Kalinin ASTeC, Daresbury Laboratory.
CLIC main activities and goals for 2018 Design and Implementation studies: CDR status: not optimized except at 3 TeV and not adjusted for Higgs discovery,
ATF2 Kiyoshi KUBO Accelerator Test Facility (ATF) at KEK ATF – Designed as a prototype of damping ring and injector of LC – Achieved low vertical.
Beam Delivery System collimators for the International Linear Collider J. L. Fernandez-Hernando STFC/ASTeC Daresbury Lab.
BDS Andrei Seryi, Deepa Angal-Kalinin, Emmannual Tsesmelis, Rogelio Tomas, Andrea Latina, Daniel Schulte Detectors Civil engineering.
ATF2 Commissioning Toshiyuki Okugi 2008 / 7 /9 ATF2 beam commissioning meeting, KEK.
CTF3 Probe Beam G. A. Blair Royal Holloway Univ. London CTF3 Meeting, CERN 30 th November 2005 Introduction – UK Context Draft Proposal Future prospects.
Introduction: Tasks of “Information for simulations”, hardware specs K.Kubo
17 th November, 2008 LCWS08/ILC08 1 BDS optics and minimal machine study Deepa Angal-Kalinin ASTeC & The Cockcroft Institute Daresbury Laboratory.
2 nd EuroTeV Annual Meeting, Daresbury 9 th January 2007 WP2 : Beam Delivery System D. Angal-Kalinin ASTeC, CCLRC Daresbury Laboratory.
BDS: 1 October 13, 2007 BDS KOM EDR planning discussion Andrei Seryi October 13, 2007.
FNAL efforts on LHC Crab Cavity R&D (Proposals for R&D sub-tasks, resources and schedule) Nikolay Solyak.
Global Design Effort CLIC-ILC BDS & MDI work Materials for discussion Daniel Schulte, Rogelio Tomas and Emmanuel Tsesmelis for CLIC team Andrei Seryi for.
ILC-BDS Collimators - Simulation and Experiment Adriana Bungau The University of Manchester Group Annual Meeting December, 2007, Manchester Adriana Bungau.
13 September 2006 Global Design Effort 1 ML (x.7) Goals and Scope of Work to end FY09 Nikolay Solyak Fermilab Peter Tenenbaum SLAC.
WP10.3 Crab Cavities Overview EUCARD SRF Annual Review Peter McIntosh (STFC, ASTeC, Daresbury Laboratory) 4 – 5 May 2011, Orsay.
Low Emittance Generation and Preservation K. Yokoya, D. Schulte.
Global Design Effort: Controls & LLRF Americas Region Team WBS x.2 Global Systems Program Overview for FY08/09.
BDS Lattice Design : EDR plans GWP03 Meeting 04/12/2007.
LET in the ILC DRs with Minimal Tuning Knobs and other assorted information James Jones Deepa Angal-Kalinin and Frank Jackson.
Introdcution to Workpackage/Activity Reflection D. Schulte.
Introduction D. Schulte for K. Kubo and P. Tenenbaum.
Diagnostics Workpackage G A Blair EUROTeV Final Meeting, DESY, Hamburg 30 th January 2009 Tasks Summary.
CERN, 27-Mar EuCARD NCLinac Task /3/2009.
Main and Drive Beam Dynamics Working Group Caterina Biscari, Daniel Schulte Attending people ~ 20 ± 5 Presentations ~ 18 (7 from CERN) CL IC 07.
FP7: EuCARD after a year of preparation… A.Jeremie.
DRAFT: What have been done and what to do in ILC-LET beam dynamics Beam dynamics/Simulations Group Beijing.
IWLC10, 18 th -22 nd October10, CERN/CICG 1 Global Design Effort Updates to ILC RDR Beam Delivery System Deepa Angal-Kalinin & James Jones ASTeC, STFC.
BDS/MDI Deepa Angal-Kalinin Andrei Seryi AD&I Meeting, DESY, May 29, 2009.
IoP HEPP/APP annual meeting 2010 Feedback on Nanosecond Timescales: maintaining luminosity at future linear colliders Ben Constance John Adams Institute,
February 4, 2007 Global Design Effort 1. February 4, 07 Global Design Effort IR&MDI: 2 Tuesday’s discussion EDR organization Work Package distribution.
1 Comments concerning DESY and TESLA Albrecht Wagner Comments for the 5th meeting of the ITRP at Caltech 28 June 2004 DESY and the LC What could DESY contribute.
25 October 2004O. Napoly, EU-GDE meeting in Oxford 1 French Funding Agencies CNRS/IN2P3 : National research Institute on Nuclear Physics and Particle Physics.
ILC R&D Activities at KEK Superconducting Linac Development Beam-handling Technology Development.
Status of ATF2 linear collider focus prototype emphasizing France-China joint contributions Philip Bambade Laboratoire de l’Accélérateur Linéaire Université.
ESGARD OMIA Sept EUROdrive and LED Motivation Work Packages Partners & resources.
Task 9.4 Beam Delivery System CERN, 27-Mar /3/2009
Thomas Schoerner-Sadenius DESY Hamburg, Germany
UK X FEL Kick-off Meeting
In collaboration with P. N. Burrows, A. Latina and D. Schulte
Oversea collaborators
Developments on Proposed
CLIC Study Aim Conceptual design report in 2010
WP10.3 LHC Crab Cavities Overview EUCARD SRF Annual Review
CLIC-ILC BDS & MDI work.
Muon Acceleration in a Neutrino Factory
CLIC damping rings working plan towards the CDR
Presentation transcript:

D. Angal-KalininEUROTeV Annual Meeting, DESY WP2 : Beam Delivery System D. Angal-Kalinin ASTeC, STFC, Daresbury Laboratory 4 th EUROTeV Annual Meeting, DESY 30 th January 2009

D. Angal-KalininEUROTeV Annual Meeting, DESY WP2 : Beam Delivery System  Beam delivery System Lattice Design (BDSLD) (CEA, CERN, Manchester, JAI, LAL, STFC) Task leader : Deepa Angal-Kalinin  Crab Cavity RF System Design (CRABRF) (Lancaster, Manchester, STFC) Task leader : Amos Dexter  Fast Beam Based Feedback (FFBK) (Oxford, STFC) Task leader : Phil Burrows  Spoiler Wake Field and Mechanical Design (SWMD) (Birmingham, Lancaster, Manchester, CERN,TEMF, STFC) Task leader : Nigel Watson  Super Conducting Final Doublet technology R & D (SCFD) (CEA) Task leader : Olivier Napoly

D. Angal-KalininEUROTeV Annual Meeting, DESY Beam Delivery System Lattice Design (CEA, CERN, Manchester, JAI, LAL, STFC) ILC  2mrad minimal extraction line and final focus design with designed extraction magnet parameters.  Collimation performance optimisation for the RDR lattice.  Performance and tuning of 14 mrad IR region. CLIC  Optimised BDS design for 500 GeV CM and 3 TeV CM with shorter final focus systems.  Review of collimation design for new CLIC parameters.  Performance simulations on the Beam diagnostics section.  Tuning studies based on minimisation algorithms instead of knobs. ATF/ATF2  Emittance growth investigation, emittance measurements.  Development of tuning procedures.  Pushed beta optics (ILC pushed and CLIC regime). Task Summary : EUROTeV-Report

D. Angal-KalininEUROTeV Annual Meeting, DESY Crab RF ( Lancaster, STFC, Manchester)  Testing of a LLRF system which could synchronise the phases of two cavities to the required tolerance for ILC crab cavities.  A vertical cryostat facility has been established at STFC Daresbury.  These tests have now been completed and the required synchronisation has been achieved. 2 x 3.9 GHz SRF crab cavities in vertical cryostat to verify LLRF control and synchronisation. Final Deliverable : EUROTeV-Report EUROTeV-Report

D. Angal-KalininEUROTeV Annual Meeting, DESY Fast Beam Based Feedback (Oxford, STFC)  Development and testing of prototype hardware for the ILC intra- train beam-based feedback system.  Basic functionality demonstrated for ILC.  The linearity and resolution of BPM processors were tested under a variety of beam conditions in January, March and May’08. Alternate processing scheme was tested and looks very promising.  Feedback system operation at ATF, with particular attention to quality of the feedback. Task Summary : EUROTeV-Report

D. Angal-KalininEUROTeV Annual Meeting, DESY Spoiler Wake Fields and Mechanical Design (Birmingham, Lancaster, Manchester, CERN,TEMF, STFC)  Wake field tests (T480) at ESA, MAFIA/GdfidL simulations and data analysis.  Beam damage simulations (FLUKA/Geant4, ANSYS). Beam damage test beam at ATF (phase 1) (Feb./Mar. 2008), Proposed phase 2 (using stress waves) in ATF2 extraction line.  First draft engineering design of ILC spoiler was presented at EPAC08. Final Deliverable: EUROTeV-Report EPAC08 paper

D. Angal-KalininEUROTeV Annual Meeting, DESY Super conducting Final Doublet Technology (CEA)  The construction of the 1m long superconducting quadrupole prototype with Nb 3 Sn conductors is completed (not part of the EUROTeV contract).  This task did not deliver the cold test of the Nb3Sn superconducting quadrupole embedded in the 2-4 T solenoid field.  The 3D magnetic and mechanical modelling efforts initiated by this task, both for the quadrupole and for the solenoid magnets, lead the way to a successful investigation of the ILC interaction region properties. Task Summary : EUROTeV-Report

D. Angal-KalininEUROTeV Annual Meeting, DESY Milestone NamePlanned (in months) Achieved (in months) Comments Detailed scope and planning report to First Workshop 66 Presentation of results and detailed implementation at second workshop 1825 Presentation of phase 2 results to Third workshop; plans for GDI-TDR input and further R&D (phase 3 & beyond) 30 Optimised BDS lattice design with component specification available. 30 EUROTeV- Report Demonstration of high-field super conducting quadrupole in strong solenoid complete 48Not achievedEUROTeV- Report CRAB RF low-power systems test (including phase stability studies) available. 4846EUROTeV- Report Report Mechanical spoiler design complete4842EUROTeV- Report EPAC’08 Demonstration of prototype intra-train feedback and scanning systems available. 4836EUROTeV- Report Milestones

D. Angal-KalininEUROTeV Annual Meeting, DESY Deliverable NamePlanned (in months) Achieved (in months) Fully documented optimised BDS lattice, including component (magnet) specification 30 Engineering design for ILC mechanical spoiler, including prototype evaluations of wakefield and beam-damage performance 4842 Prototpye intra-train feedback stabilisation and scanning system 4840 Report on CRAB RF low-power prototype tests, including phase-stability system Report on demonstration of superconducting quadrupole in strong solenoid field 48Not achieved. Comments EUROTeV- Report EUROTeV- Report EPAC’08 EUROTeV- Report EUROTeV- Report Report EUROTeV- Report Deliverables

D. Angal-KalininEUROTeV Annual Meeting, DESY Summary  BDS work package has delivered most of the milestones and deliverables.  There was a change in programme for SCFD task due to resources issues and technical problems. The changed programme has lead to a successful investigation of the ILC interaction region properties.  There are task summaries for 3 tasks (BDSLD, FFBK,SCFD). The deliverables of other two tasks (SWMD, CRABRF) have been covered in one/more EUROTeV reports.  The work package has delivered 80 EUROTeV reports + 3 journal publications (+ few in preparation).  Thanks to all the Task Leaders and the contributors.