Massimo GiovannozziChamonix XV, January 23-27 20061 Electrical circuits required for the minimum workable LHC during commissioning and first two years.

Slides:



Advertisements
Similar presentations
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Advertisements

Critical beam losses during Commissioning & Initial Operation Guillaume Robert-Demolaize (CERN and Univ. Joseph Fourier, Grenoble) with R. Assmann, S.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Spectrometer compensation in IR2 and IR8 during the 450 GeV collision run September 11, 2006 LOC meeting Y. Papaphilippou Thanks to S. Fartoukh, W. Herr,
Highlights of the ATS MD part I (injection and ramp) … An 8h video game party carefully organized by Jorg et al. 1S. Fartoukh, LSWG 24/05/2011.
Magnetic Behavior of LHC Correctors: Issues for Machine Operation W. Venturini Delsolaro AT-MTM; Inputs from A. Lombardi, M. Giovannozzi, S. Fartoukh,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
MG - MTE Workshop 24/09/20101 Measurements’ analysis S. Gilardoni, M. Giovannozzi, M. Newman Introduction Techniques, tools Results (selected) Outlook.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Updates to WISE for LHC run II Per Hagen May 2015.
Bernhard Holzer * IP5 IP1 IP2 IP8 IR 7 ”Beam Dynamics for Nb3Sn dipoles... latest news"
E. Todesco FIELD MODEL AT 7 TEV N. Aquilina, E. Todesco CERN, Geneva, Switzerland On behalf of the FiDeL team CERN, 17 th June.
LHC Technical Committee, 23/05/20071 LHC Commissioning Phases Squeeze presented by Massimo Giovannozzi on behalf of the LHCCWG Particular thanks to S.
Update of beam dynamics target for the LHC correctors A.M. Lombardi FQWG
1 / 23 Workshop Chamonix XV January 2006, L'Esplanade du Lac, Divonne-les-Bains S. Sanfilippo Transfer Function of the.
The Large Hadron Collider Contents: 1. The machine II. The beam III. The interaction regions IV. First LHC beam [R. Alemany] [CERN AB/OP] [Engineer In.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Optimization of Field Error Tolerances for Triplet Quadrupoles of the HL-LHC Lattice V3.01 Option 4444 Yuri Nosochkov Y. Cai, M-H. Wang (SLAC) S. Fartoukh,
Ramping & Snapback Andy Butterworth AB/RF Chamonix XIV 17 January 2005.
The Large Hadron Collider First LHC beam measurements [R. Alemany] [CERN BE/OP] [Engineer In Charge of LHC] Lectures JUAS ( )
AT-MEL, CERN, 1211 Geneva 23 R.Wolf-LHCCWG Magnet Setup Cycling for LHC R. Wolf for the FQWG et al. Contents -Overview -Details of individual cycles.
Proton Source 1/12/07 E Prebys 1 Proton Delivery Because MiniBooNE is off.
LHC Workshop, Jan '05P. Collier AB-OP/LHC1 450 GeV P. Collier AB/OP  Prerequisites  First Turn  Getting Closure  RF Capture  Preliminary Commissioning.
1 EMMA Tracking Studies Shinji Machida ASTeC/CCLRC/RAL 4 January, ffag/machida_ ppt & pdf.
E. Todesco EXPERIENCE WITH FIELD MODELING IN THE LHC E. Todesco CERN, Geneva Switzerland Thanks to the FiDeL team CERN, Space charge th April 2013.
2/12/2013 Massimo Giovannozzi - CERN1 Sorting of the LHC magnets and lessons learnt S. Fartoukh, M. Giovannozzi Introduction The LHC in a nutshell The.
Faster ramp rates in main LHC magnets Attilio Milanese 7 Oct Thanks to M. Bajko, L. Bottura, P. Fessia, M. Modena, E. Todesco, D. Tommasini, A. Verweij,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
1 Task particle simulations studies: progress report M. Giovannozzi Objectives To study the field quality tolerances for new magnetic elements for.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
WP2: Beam dynamics and optics Workflow between Work Packages 1 O. Brüning – BE-ABP WP2 HL-LHC meeting 17. November 2011.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
R.Bailey, Chamonix XV, February 2006 Staged commissioning plan for protons Hardware commissioning Machine checkout Beam commissioning 43 bunch operation.
08/11/2007M. Giovannozzi – CARE-HHH-APD IR’071 Optics issues for Phase 1 and Phase 2 upgrades Massimo Giovannozzi, CERN Outline: –Option for Phase 1 and.
Linear optics - I Low beta* at injection –Reduction of injection could potentially reduce time to collisions and allow for a more relaxed ramp&squeeze,
Crossing Schemes Considerations and Beam-Beam Work plan T. Pieloni, J. Barranco, X. Buffat, W. Herr.
Collimation Aspects for Crab Cavities? R. Assmann, CERN Thanks to Daniel Wollmann for presenting this talk on my behalf (criticism and complaints please.
Expected field quality in LHC magnets E. Todesco AT-MAS With contributions of S. Fartoukh, M. Giovannozzi, A. Lombardi, F. Schmidt (beam dynamics) N. Catalan-Lasheras,
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
First evaluation of Dynamic Aperture at injection for FCC-hh
Review of the present non-conformities in view of HL-LHC
LHC Commissioning with Beam
FiDeL: the model to predict the magnetic state of the LHC
Parameters and tolerances
Multi-Turn Extraction studies and PTC
Field quality update and recent tracking results
Optimization of Triplet Field Quality in Collision
Powering the LHC Magnets
Large Booster and Collider Ring
Status and needs of dynamic aperture calculations
Status of Magnet Setup Cycling for LHC
Field quality to achieve the required lifetime goals (single beam)
LHC Commissioning Phases
UPDATE ON DYNAMIC APERTURE SIMULATIONS
Alice solenoid – orbit distortion
Nonlinear Field Quality Checks
Alternative design of the matching section for crab-cavity operation
LHC OPERATION AND SUPPORT
Field quality of LHC corrector magnets
HL-LHC operations with LHCb at high luminosity
450 GeV Preliminary Commissioning: Measurement Programme
Magnetic axis tolerances for the SSS magnets
Thanks to S. Fartoukh, W. Herr, B. Jeanneret, M. Giovannozzi
MD Planning Fri – Sat (1. – 2.7.)
Triplet corrector layout and strength specifications
Beam dynamics requirements on MQT
Sawtooth effect in CEPC PDR/APDR
Another Immortal Fill….
Large emittance scenario for the Phase II Upgrade of the LHC
Presentation transcript:

Massimo GiovannozziChamonix XV, January Electrical circuits required for the minimum workable LHC during commissioning and first two years of operation M. Giovannozzi Summary:  Introduction  Magnetic circuits: commissioning  Magnetic circuits: first two years of operation  RF circuits  Conclusions and outlook Acknowledgements: H. Burkardt, S. Fartoukh, E. Métral, F. Ruggiero, R. Saban, E. Shaposhnikova, E. Todesco, J. Tuckmantel

Massimo GiovannozziChamonix XV, January Aim: identify circuits (magnetic and RF) that are critical for the commissioning. In general it can be stated that low-order correctors are mandatory from day 1, while higher- order correctors can be delayed to a later stage. Of course, the relevance of a circuit is also a function of the beam conditions. Inspiring presentation made by O. Brüning at the 17 th LHCOP meeting. Introduction

Massimo GiovannozziChamonix XV, January From Roger’s talk

Massimo GiovannozziChamonix XV, January Trajectory- orbit From Roger’s talk Optics: tune, chromaticity RF on

Massimo GiovannozziChamonix XV, January Stage 1: initial commissioning - I Orbit correctors: Arc correctors (in SSS) Insertion correctors (in special SSS, used also for crossing scheme, and near warm quadrupoles) All orbit correctors are needed from day 1

Massimo GiovannozziChamonix XV, January Stage 1: initial commissioning - II Optics correctors: Tune correction Coupling correction Optics in the insertions MQT: trim quadrupoles in SSS (Q14-Q21 L/R) MQTL: long trim quadrupoles used in special SSS (Q11) to trim the insertion optics and in Q6 in IR3 and IR7 MQS: skew quadrupoles in SSS for coupling correction (Q23, Q27 L/R) All MQT and MQTL correctors are needed from day 1

Massimo GiovannozziChamonix XV, January Stage 1: initial commissioning - III Coupling correction Pre-requisite for tune setting Estimate of C - without correction (S. Fartoukh 31. LCC, O. Brüning – Chamonix 2003) -> using 9901 error table for MBs The estimate did not change drastically using data from MB production. Therefore, all MQS correctors are needed from day 1

Massimo GiovannozziChamonix XV, January Stage 1: initial commissioning - IV Sextupolar correctors Spool pieces: all MBs are equipped with sextupolar correctors (MCS) Contribution to chromaticity from b 3 error in MBs Correction of dynamic effects: decay and snap back Remark: 1 unit of b3 -> 45 units of Q’ Remark: specifications are (S. Fartoukh O. Brüning LHC PR 501) Q’=2±1, Q’ x =Q’ y New specs given by O. Brüning (see MAC presentation December 2004), but not substantially different Spool pieces are needed from day 1 Sector Average b 3 in MB at injection [10 -4 ] Average b 3 in MB at injection [10 -4 ] Rms b 3 in MB at injection [10 -4 ] Rms b 3 in MB at injection [10 -4 ]V1V2V1V Courtesy S. Fartoukh, MEB-107 presentation Courtesy L. Bottura

Massimo GiovannozziChamonix XV, January Stage 1: initial commissioning - V Sextupolar correctors All SSS are equipped with chromaticity sextupoles (MS) Natural chromaticity is Q’ x =-93, Q’ y =-87 Correction of natural chromaticity is essential for tune measurement (decoherence)! Chromaticity sextupoles are needed from day 1 Four skew sextupoles are installed in each arc (MSS) Specification (S. Fartoukh O. Brüning LHC PR 501) based on bound on Q’’ (a 3 has no impact on dynamic aperture) a 3 (sys)=0 a 3 (sys)=0 a 3 (ran)=0.7 a 3 (ran)=0.7 a 3 (unc)=1.5 a 3 (unc)=1.5 a3(sys)= – inj a3(ran)= inj a3(sys)= coll a3(ran)= coll Courtesy E. Todesco Skew sextupoles might not be needed from day 1

Massimo GiovannozziChamonix XV, January Stage 1: initial commissioning - VI Octupolar correctors Spool pieces: MBs type A are equipped with octupolar correctors (MCDO) Specification (S. Fartoukh O. Brüning LHC PR 501) based on bound on Q’’ and anharmonicity (b4 has an impact on dynamic aperture) b4(sys)=±0.2 b4(sys)=±0.2 b4(ran)=0.5 b4(ran)=0.5 b4(unc)=0.4 b4(unc)=0.4 MB-intrinsic b4 is fine. The main source of b4 comes from feed-down from MCD. Feed-down effects are nearly on specification. Remark tracking studies showed that without MCO the minimum dynamic aperture drops from 11.2  to 9.6  (see M. Hayes LHC PR 522). b4(sys)= – inj b4(ran)= inj b4(sys)= coll b4(ran)= coll Courtesy E. Todesco

Massimo GiovannozziChamonix XV, January Stage 1: initial commissioning - VII Octupolar correctors Lattice octupoles: all SSS not equipped with MQT or MQS are equipped with a Landau octupole (MO) -> 168 per ring Not used at injection Used to stabilise the beams at top energy (before starting beam collisions). Under the beam conditions of the initial commissioning they should not be used However, the beam brightness is the relevant parameter (e.g. TOTEM, see E. Métral and A. Vérdier LHC PN 345) MCO might not be needed from day 1. MO are not needed from day 1, but…

Massimo GiovannozziChamonix XV, January Stage 1: initial commissioning - VIII Decapolar correctors Spool pieces: MBs type A are equipped with decapolar correctors (MCDO) Specification (S. Fartoukh O. Brüning LHC PR 501) based on bound on Q’’’ and chromo-geometric detuning (b5 has an impact on dynamic aperture) Courtesy E. Todesco

Massimo GiovannozziChamonix XV, January Stage 1: initial commissioning - IX A possible solution for MCO and MCD correctors would be to suppress them only in few arcs (see M. Hayes LHC PR 522). To be checked with the latest version of the LHC layout

Massimo GiovannozziChamonix XV, January Stage 1: initial commissioning - X Spectrometer compensator magnets (IP2 and IP8) Since the first physics run, the spectrometers of ALICE and LHC-b will be on. Hence the three warm magnets/IP used to compensate the bump should be available from day 1

Massimo GiovannozziChamonix XV, January Stage 1: initial commissioning - XI Nonlinear corrector package in the triplet quadrupoles No impact on machine performance if beta* > 1 m Not needed from day 1, but maybe MQSX and MCSX in IP2

Massimo GiovannozziChamonix XV, January Stage 1: initial commissioning - XII Experimental solenoids They will not be ramped Effect negligible at top energy (see J.-P. Koutchouk et al. SL ) At injection C - ~ 5×10 -3 for the CMS solenoid (H. Burkhardt, LOC meeting) MQSX could be used to correct the coupling from solenoids -> work in progress (H. Burkhardt et al.) Vertical crossing angle in IP2 Change of polarity in spectrometer will change a2 generated from feed-down of b3. a2 correction with MQSX not possible for both beams and with MQS not effective MCSX could be used to correct the b3

Massimo GiovannozziChamonix XV, January Stage 1: initial commissioning - XIII RF system (see T. Linnecar Chamonix 2005 for RF failures) Independent for each ring Two modules of 4 cavities each. Each cavity delivers 2 MV Nominal conditions: 8 MV at injection and 16 MV at top energy

Massimo GiovannozziChamonix XV, January Stage 1: initial commissioning - XIV 8 MV at injection leaves margin for beam loading from nominal beam For reduced beam intensity one might think of using only 8 MV throughout the whole cycle -> only one module would be used However: it would be wise to capture with full voltage (16 MV) during stage 1 to have maximum longitudinal acceptance (e.g. energy errors between SPS/LHC) No spare would be available and commissioned in case of problems Hence, all modules should be available from day 1

Massimo GiovannozziChamonix XV, January Stages 2 and 3 Beam conditions will approach the nominal ones. All the corrector circuits will be needed to ensure the performance No staging seems possible

Massimo GiovannozziChamonix XV, January Conclusions - I Stage 1: Circuits mandatory for day 1: Orbit correctors MQTs, MQTLs, MQS MCS, MS Spectrometer compensators All RF modules Circuits required for day 2(!): MCD (decapoles) MCO (octupoles) MQSX MCSX in IP2 MO Circuits not required for day 1: MSS Nonlinear correctors in the triplet quadrupoles Stages 2 and 3: Put in operation all the circuits still missing

Massimo GiovannozziChamonix XV, January Conclusions - II Some additional details are needed for evaluating the (beneficial) impact of reducing the number of circuits required in the various stages of LHC commissioning, namely What is the time required for the hardware commissioning of the circuits not required for day 1? Is it possible to perform the hardware commissioning in case it is found that they are actually needed? In this case what would be the time required to commission the circuits?