Presentation is loading. Please wait.

Presentation is loading. Please wait.

HL-LHC operations with LHCb at high luminosity

Similar presentations


Presentation on theme: "HL-LHC operations with LHCb at high luminosity"โ€” Presentation transcript:

1 HL-LHC operations with LHCb at high luminosity
R. De Maria, N. Karastathis Thanks to G. Arduini, F. Cerutti, I. Efthymiopoulos, S. Fartoukh, M. Giovannozzi LHCb Meeting 21/3/2018

2 Peak luminosity Minimum ฮฒ* is constrained by optics flexibility.
๐ฟ= ๐‘ ๐‘ 2 ๐‘“ ๐‘Ÿ๐‘’๐‘ฃ ๐‘˜ ๐‘ 4๐œ‹๐œ– ๐›ฝ ร— โˆ— ๐›ฝ โˆฅ โˆ— โ‹… ฮฆ ๐‘ 2 Protons per bunch ๐‘ ๐‘ Number of Bunches ๐‘˜ ๐‘ 2572(2374) R.M.S. bunch length ๐œŽ ๐‘  7.61(9.0) cm +/- Polarity By<0 / By>0 ฮฆ ๐‘ = ๐œŽ ๐‘  ๐œŽ ร— โ‹… ๐œƒ ร— 2 = ๐œŽ ๐‘  ๐›ฝ ร— โˆ— โ‹… bb sep 2 ๐œƒ external , ๐›ฝ* at constant luminosity ๐œƒ ร— = ๐œƒ external ยฑ ๐œƒ spectrometer cos ๐›ผ plane cm-2s-1 baseline Minimum ฮฒ* is constrained by optics flexibility. Maximum crossing angle limited by orbit corrector strength For a given ฮฒ*: Aperture constrains maximum crossing angle. Beam-beam effects (i.e. beam lifetime) constrains minimum crossing angle. Beam-beam effects Orbit corrector limitations Aperture limitations cm-2s-1 Optics limitations

3 Beam-beam limitations at collision
DA margins at the end of Atlas/CMS levelling as a function of IR8 horizontal half external angle for a scenario with cm-2s-1. -250 ฮผrad, Neg. -200 ฮผrad, Neg. -180 ฮผrad, Neg. -150 ฮผrad, Neg. N. Karastathis

4 Beam-beam limitations at collision
DA margins at the end of Atlas/CMS levelling as a function of IR8 horizontal half external angle for a scenario with cm-2s-1. -200 ฮผrad โ€œBadโ€(Neg) Polarity -150 ฮผrad โ€œGoodโ€(Pos.) Polarity N. Karastathis Spectrometer polarity has an impact of minimum external crossing angle. Tentative IR8 external half crossing angle with horizontal crossing: -200 ฮผrad with Neg. polarity (-65 ฮผrad half crossing angle) -150 ฮผrad with Pos. polarity (-285 ฮผrad half crossing angle) Not fully validated, full cycle simulation needed. A vertical external half crossing angle of 160 ฮผrad is expected to behave in between the two horizontal options (210 ฮผrad half crossing angle)

5 Aperture limitations in collision
Maximum half external crossing angle as function of ฮฒ* ฮฒ* [m] H1 [ยตrad] H2 [ยตrad] V3 [ยตrad] V1,4 [ยตrad] 1 -165 -220 ยฑ115 ยฑ220 1.5 -225 -275 ยฑ165 ยฑ235 2 -265 -310 ยฑ205 ยฑ270 3 ยฑ250 ยฑ310 1 with present TCDDM 2 without present TCDDM 3 crossing plane can be rotated during the ramp (difficult to setup) 4 if beam screen is rotated, introducing strong limitations during the ramp Aperture in the triplet is not symmetric (H=57.8 mm, V=48 mm) and cannot be rotated easily. TCDDM needed for D1 protection Present aperture bottleneck for Beam 2 H and Beam 1 V. H crossing V crossing H crossing V crossing Compatible with previous scenarios and still aperture margin for ฮฒ*//. Beam screen rotation not needed so far in V crossing, and, if it would, the issues are at injectionโ€ฆ

6 Constraints at injection
Baseline Horizontal crossing. Pos. Spec., 450 GeV -170 ยตrad, +3.5 mm As the LHC, but with double the intensity in HL-LHC. This needs to be still validated, no margin expected.

7 Constraints at injection
Baseline Horizontal crossing. Neg. Spec., 450 GeV -170 ยตrad, +3.5 mm As the LHC, but with double the intensity in HL-LHC. This needs to be still validated, no margins expected.

8 Constraints at injection
Vertical crossing and rotated beam screen with critical issues Neg. Spec., 450 GeV -170 ยตrad, +3.5 mm 2ฯƒ Additional close encounters, in particular close to the IP. Not compatible with different ion species runs (e.g. p โ€“ lead). Not compatible with present orbit tolerance specifications for p-p.

9 Constraints at injection
Horizontal crossing and rotated beam screen with critical issues Neg. Spec., 450 GeV -170 ยตrad, +3.5 mm 2ฯƒ Not enough aperture for the crossing angle in the H plane. Reducing crossing angle and increasing parallel separation not trivial.

10 Tentative scenarios ฮฒ* [m] Ext. Crossing /Spec. Polarity
Peak Luminosity [1034] 1.5 H/ยฑ200 /- 2.16 H/ยฑ150/+ 1.59 (implies operation overhead) V/ยฑ160/+ or - 1.8 (not simulated with DA) ฮฒ* [m] X Int. Lumi [1034/year] 1.5 H 43 52 V 51 Assuming same โˆซL in both polarities, to be verified with more realistic luminosity models Not significant advantage of designing the detector for cm-2s-1. 43 fb-1 sufficient to reach a target of 300fb-1 (triplet lifetime) in RunV, RunVI (~6 years of operations). Beam screen rotation not needed for these configurations, small crossing angle also better for dose at constant luminosity.

11 Example of Luminosity evolution
Case with LHCb virtual luminosity of cm-2s-1 with three levelling scenarios. Simple model used for illustration only and not for quantitative estimates. Atlas/CMS Atlas/CMS LHCb LHCb Atlas/CMS Machine LHCb

12 Example of Luminosity evolution
Case with LHCb virtual luminosity of cm-2s-1 with three levelling scenarios. Simple model used for illustration only and not for quantitative estimates. Atlas/CMS Atlas/CMS LHCb LHCb Atlas/CMS Machine LHCb

13 Example of Luminosity evolution
Case with LHCb virtual luminosity of cm-2s-1 with three levelling scenarios. Simple model used for illustration only and not for quantitative estimates. Atlas/CMS Atlas/CMS LHCb LHCb Atlas/CMS Machine LHCb

14 Open points Validate the new tentative configurations for LHCb at high luminosity: Evaluate commissioning overhead of two external crossing angles depending on the polarity. Complete beam-beam simulations, in particular for the whole cycle and with vertical crossing (ongoing). Perform energy deposition studies for the cycle for different crossing scenarios. Assess feasibility and cost of protecting devices such as: TAS, TAN, TCDDM, TCL. A study group is going to be put in place to provide information concerning the impact on HW and costs. Asses realistic dose considering no TAS before RunIV and large crossing angle. If operational margins exist one can consider the options: Flat beams (e.g. ฮฒ*// < ฮฒ*X) which gives more luminosity at constant aperture but with additional beam-beam effects to be evaluated. In H crossing smaller ฮฒ*X for Pos. Polarity at the cost of additional operational overhead to be quantified. In parallel one would need to state what performance impact is acceptable for Atlas and CMS.

15 Conclusion Tentative scenarios identified with levelled luminosity of 1ยท1034 cm-2s-1 and similar performance: Horizontal crossing with two external angles Time lost at each polarity change Vertical crossing with rotation of the crossing plane at flat top Time lost in commissioning the crossing plane rotations (it gave several problems during Run I) Beam screen rotation: is not needed in the present scenarios taking into account triplet lifetime, present options and further optimizations that could be attempted is not feasible option unless: it is possible to reduce orbit tolerances AND disable LHCb during p-Ion runs OR it is possible inject with very large separation. proven feasible for radiation issues. compatible with cost and schedule (in-situ coating developed to avoid intervening on the triplet). Flat beams in LHCb: Can improve luminosity at constant aperture and beam-beam separation in the triplet, with potential detrimental effects on lifetime compared to round at constant aperture (e.g. beam-beam effects). Will be explored after round scenarios are fully validated.

16 Backup

17 Flat optics

18 Constraints at injection
Vertical crossing with critical issues Neg. Spec., 1000 GeV Rotated beam screen -170 ยตrad, +3.5 mm Close encounter moves with energy and needs strict control of the orbit during the ramp.

19 Constraints at injection
Vertical crossing with critical issues Neg. Spec., 1000 GeV Rotated beam screen -200 ยตrad, +2.0 mm Close encounter moves with energy and needs strict control of the orbit during the ramp.

20 Constraints at injection
Vertical crossing with critical issues Neg. Spec., 3000 GeV Rotated beam screen -200 ยตrad, +1 mm Close encounter moves with energy and needs strict control of the orbit during the ramp.

21 Constraints at injection
Vertical crossing with ramped spectrometer Neg. Spec., 450 GeV Rotated beam screen and ramped spectrometer Vertical crossing is straightforward if spectrometer could be ramped with energy.

22 Constraints at injection
Horizontal crossing with extreme conditions Pos. spec., 450 GeV Rotated beam screen -120 ยตrad, +7.0 mm 80 ยตrad (bias) 1.5 mm offset This solution is more robust at injection, but uses about 3 times the typical orbit corrector at injection. As energy increase separation, offset and bias would need to be reduced quickly. Needs validation from injection protection issues.

23 Constraints at injection
Baseline Horizontal crossing. Pos. Spec., 450 GeV -170 ยตrad, +3.5 mm As the LHC, but with double the intensity in HL-LHC This needs to be still validated.

24 Constraints at injection
Baseline Horizontal crossing. Neg. Spec., 450 GeV -170 ยตrad, +3.5 mm As the LHC, but with double the intensity in HL-LHC This needs to be still validated.

25 Constraints at injection
Vertical crossing with critical issues Neg. Spec., 450 GeV Rotated beam screen -170 ยตrad, +3.5 mm Additional close encounters, in particular close to the IP. Not compatible with different ion species runs (e.g. Lead โ€“ Ion). Not compatible with present orbit tolerance specifications for p-p.

26 Constraints at injection
Vertical crossing with critical issues Neg. Spec., 1000 GeV Rotated beam screen -170 ยตrad, +3.5 mm Close encounter moves with energy and needs strict control of the orbit during the ramp.

27 Constraints at injection
Vertical crossing with critical issues Neg. Spec., 1000 GeV Rotated beam screen -200 ยตrad, +1 mm Close encounter moves with energy and needs strict control of the orbit during the ramp.

28 Constraints at injection
Vertical crossing with critical issues Neg. Spec., 3000 GeV Rotated beam screen -200 ยตrad, +1 mm Close encounter moves with energy and needs strict control of the orbit during the ramp.

29 Constraints at injection
Vertical crossing with ramped spectrometer Vertical crossing, - 450 GeV Rotated beam screen and ramped spectrometer Vertical crossing is straightforward if spectrometer could be ramped with energy.

30 Constraints at injection
Horizontal crossing with extreme conditions Neg. Spec., 450 GeV Rotated beam screen -120 ยตrad, +7.0 mm 80 ยตrad (bias) 1.5 mm offset This solution is more robust at injection, but uses about 3 times the typical orbit corrector at injection. As energy increase separation, offset and bias would need to be reduced quickly. Do we need this?


Download ppt "HL-LHC operations with LHCb at high luminosity"

Similar presentations


Ads by Google