T.L. Martin & Associates Copyright © 2008 Chapter 1 Fundamentals of Scheduling T.L. Martin & Associates, Inc. 18552 Office Park Drive Gaithersburg, Maryland.

Slides:



Advertisements
Similar presentations
Chapter 6 Practical Methods to Reveal CPM Covert Activities
Advertisements

Copyright © 2009 T.L. Martin & Associates Inc. Chapter 4 Standard CPM Smoke and Mirror Tricks (Manipulations)
Developing a Project Plan CHAPTER SIX Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
DISTRICT FIVE CONSTRUCTION CONTRACT ADMINISTRATION UPDATE TRAINING Submission of Working Schedule Specification SP A.
Work Breakdown Structures
Chapter 3 Managing the Information Systems Project
Developing a Project Plan
Project Management 6e..
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 2 Key CPM Scheduling Terms.
Importance of Project Schedules
Project Management Techniques.
1 ®  Overview Benefits of a Good Construction Schedule Baseline Schedule Development Schedule Updating and Maintenance Managing Project Changes USACE.
Project Management March 9, 2001 Dr. Richard Chung Dept. Chemical & Materials Engineering San Jose State University.
Lean Six Sigma: Process Improvement Tools and Techniques Donna C. Summers © 2011 Pearson Higher Education, Upper Saddle River, NJ All Rights Reserved.
Project Management Software Tools Cheryl A. Wilhelmsen Lee Ostrom.
Where We Are Now. Where We Are Now Developing the Project Plan The Project Network A flow chart that graphically depicts the sequence, interdependencies,
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 3 Requirements of a realistic CPM schedule.
© 2006 ITT Educational Services Inc. System Analysis for Software Engineers: Unit 5 Slide 1 Chapter 3 Managing the Information Systems Project.
Project Management An overview. What is a Project A temporary job to accomplish a specific task A temporary job to accomplish a specific task Attributes.
Abeer Bin Humaid. Project management is “the application of knowledge, skills, tools, and techniques to project activities in order to meet project requirements”
Lesson №2. is the unique activity that has a beginning and an end time, aimed at achieving a predetermined result/goal, the creation of a specific, unique.
5.1 Principles of Project Management. So what is Project Management? Definition: Is the process of planning, organizing, and managing tasks and resources.
Chapter 4 INFORMATION SYSTEM PROJECT MANAGEMENT PREPARED BY : DIYANA BINTI KAMARRUDIN FARAH IZZATI BINTI MOHAMMAD NOR RAIHAN BINTI MD JOHARI.
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 5 Advanced Techniques of CPM Deception and Mystery.
EGNR 300 Project Management Planning & Scheduling ENGR 300 Dept. of Computer Science and Engineering University of Bridgeport,
~ pertemuan 6 ~ Oleh: Ir. Abdul Hayat, MTI 03-Apr-2009 [Abdul Hayat, Project Time Management, Semester Genap 2008/2009] 1 PROJECT TIME MANAGEMENT.
MS project Abeer Bin Humaid. What is project management? Project management is “the application of knowledge, skills, tools, and techniques to project.
Cost and Time Control. Project completed on time and on budget –Want to get done early –Lower costs –More profit.
Module 7 Session 7.2 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.2 Scheduling and allocating resources with CPM.
IT Project Management, Third Edition Chapter 6 1 Chapter 3: Project Time Management.
Lean Project Management
Managing Engineering Design - Infrastructure. Presentation Overview 1.Tools and Techniques 2.Design and Documentation 3.Estimating and Scheduling.
Chapter 15 Construction Scheduling. Objectives After reading the chapter and reviewing the materials presented the students will be able to: Identify.
Scheduling Resources and Costs CHAPTER EIGHT Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Objectives 4 Understand the basic concepts of project planning and control 4 Explain PERT and Timeline (Gantt) charts.
Phase 3: Scheduling and Cost Estimate Provide the following: 1.Detailed Project Schedule: Bar Chart 2.Cost Estimate 3.List of Trades Construction Process.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
Copyright © 2003 Primavera Systems, Inc Primavera User Conference Schedule Bingo presented by Mike Stone w/Professional Project Management Services.
Office Management Tool - II Institute of Management Sciences Muhammad Shahzad Ali Lec 7: Introduction to MS - PROJECT L E C T U R E 7 INTRODUCTION TO MS.
12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.
PROJECT PLANNING AND SCHEDULLING
1 EASTERN MEDITERRANEAN UNIVERSITY FACULTY OF ENGINEERING DEPARTMENT OF CIVIL ENGINEERING CIVL 493 Construction Management Assoc. Prof. Dr. Ibrahim YITMEN.
Improved Project Control Through CPM Scheduling What Owners, PM’s and CM’s Need to Know t H E T I B U R O N T I B U R O N G R O U P, L L C G R O U P, L.
CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)
Project Time Management Ashima Wadhwa. Schedule Development – Determining start and finish dates for project activities – Without realistic dates, project.
Project Time Management
Microsoft Project 2010 ® Tutorial 1: Planning a Project.
InLoox PM Product Presentation Slide 1 InLoox PM Product Presentation © InLoox, Inc. InLoox PM 8 for Outlook Product Presentation The Project.
SOFTWARE PROJECT MANAGEMENT
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
WEEK 3 Project Planning.
BSBPMG503A Manage Project Time Manage Project Time Project Time Processes Part 2 Diploma of Project Management Qualification Code BSB51507 Unit Code.
Fundamentals of Project Management and Schedule Development.
Presentation On Critical Path Analysis Project Management Series – 1 Powered by: Jazz PresentationJazz Presentation.
Project Management Planning and Scheduling. “Failing to plan is planning to fail” by J. Hinze, Construction Planning and Scheduling Planning: “what” is.
SCHEDULE MANAGEMENT MODULE 8. Required by Specification City/Caltrans Level 1 schedule – simple Less than $1 million, less than 100 working days Advanced.
Project Planning and Implementation
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
& Urban Planning Civil Engineering Department
Project Management -- Scheduling Resources and Costs
Project Management and Information Security
CHAPTER 6 PROJECT TIME MANAGEMENT
ENGINEERING MANAGEMENT (GE 404)
MGT 605: CH-13 Progress and Performance Measurement and Evaluation
Resource Planning, Cost Estimation and Budgeting
CHAPTER 6 PROJECT TIME MANAGEMENT
Where We Are Now. Where We Are Now The Resource Problem Resources and Priorities Project network times are a schedule until resources have been assigned.
Presentation transcript:

T.L. Martin & Associates Copyright © 2008 Chapter 1 Fundamentals of Scheduling T.L. Martin & Associates, Inc Office Park Drive Gaithersburg, Maryland Phone (240) & FAX (240)

T.L. Martin & Associates Copyright © 2008 The Fundamentals The primary goal of a schedule is to manage time. A plan is an order of work. When time frames are applied to a plan, a schedule is created. Critical Path Method is used to forecast when work activities are to take place.

T.L. Martin & Associates Copyright © 2008 When to Use a CPM A CPM is used when the scope of work of a project becomes complex. A bar chart can not capture the many relationships between activities in a complex project. Rule of thumb - any project with over forty (40) definable tasks.

T.L. Martin & Associates Copyright © 2008 Why Use a CPM Schedule Contractor is responsible for planning, scheduling and progressing the work. An Owner and its representatives must assure that the contractor meets its obligations.

T.L. Martin & Associates Copyright © 2008 Why Use a CPM Schedule If a contractor fails: –Then an Owner may withhold progress payments –or default terminate the contractor. The schedule is vital.

T.L. Martin & Associates Copyright © 2008 Bar Chart Schedules The bar chart is an excellent tool. Work tasks or activities are shown as bars across a horizontal calendar. If a bar chart is prepared carefully, the planner logically times the work based on: – physical restraints –contractual restraints –realistic use of men and equipment.

T.L. Martin & Associates Copyright © 2008 Bar Chart Schedule Bars Indicate When in Time a Work Task is Planned to be Performed.

T.L. Martin & Associates Copyright © 2008 Bar Chart Schedule A bar chart can include budgets versus actual. Tasks or activities are resource loaded across the horizontal calendar. This allows a real-time view of budget versus actual highlighting any problems of selected important project components such as: – manpower- costs –equipment- revenue –cash flow- material –activity timing (ahead or behind plan)

T.L. Martin & Associates Copyright © 2008 Bar Chart Schedule Add Planned Resources, Spread to Time Periods of Performance, Sum Total of All Tasks for Each Period.

T.L. Martin & Associates Copyright © 2008 Bar Chart Schedule Planned versus Actual Can be Compared.

T.L. Martin & Associates Copyright © 2008 Bar Chart Schedule Planned versus Actual Costs Can be Compared.

T.L. Martin & Associates Copyright © 2008 Bar Chart Schedule

T.L. Martin & Associates Copyright © 2008 Bar Chart Schedule A bar chart can include important budgets versus actual recorded for each Task. The Bar Chart May become Crowded. It is important to Select the Most Meaningful project components to Monitor. The following Bar Chart is an Example which Monitors: –Man-Hours - Costs- Revenue

T.L. Martin & Associates Copyright © 2008 Budget Revenue is Close to Actual Revenue, Thus Project is on Time Both Man-Hours and Costs are Less than Budgeted, Thus Project so Far is a Winner. Note Actual Timing, Man-Hours, Cost and Earned Revenue are Recorded and Compared with Budgets.

T.L. Martin & Associates Copyright © 2008 Bar Chart Schedules Bar chart does not include logic lines. More complex Projects require interrelated activities. A simple bar chart cannot capture the many relationships and interdependencies between activities on complex projects.

T.L. Martin & Associates Copyright © 2008 The CPM Schedule CPM requires the detailed planning and scheduling of all elements of a project, from start to completion. CPM results in a network of tasks of: –Defined duration, –Tied together by physical, contractual and selected optional relationships.

T.L. Martin & Associates Copyright © 2008 Critical Path Method Schedule The standard Finish-Start relationship. An Activity Finishes so Following Activity can Start.

T.L. Martin & Associates Copyright © 2008 The CPM Schedule Once a network of activities has been created, task start and finish dates can be computed. The longest activity chain, from the start of the project to its completion, is termed the projects Critical Path.

T.L. Martin & Associates Copyright © 2008 The CPM Schedule An activity or task is: –definable –must be accomplished The activity includes: –duration –linked to other activities

T.L. Martin & Associates Copyright © 2008 The CPM Schedule Budget Resources, Costs and Revenue may be assigned to each Network activity. After the CPM is created it can be updated with current project information. –Actual Timing: Start, % Complete, Finish –Resources Used Man-Hours ● Equipment-Hours Material Quantities ● Costs Other Components Monitor Budgets versus Actual Timely.

T.L. Martin & Associates Copyright © 2008 The CPM Schedule - Relationships Physical dependence and requirements between activities generally can not be changed. –One work element builds on a previous one. –Site constraints –Special weather considerations

T.L. Martin & Associates Copyright © 2008 Contractual requirements: –Owner imposed phasing of the work. –Permitting issues, –Owner furnished equipment, –Land procurement, –Early turnover of certain areas of the project. The CPM Schedule - Relationships

T.L. Martin & Associates Copyright © 2008 The CPM Schedule - Relationships Physical and contractual requirements are rigid. Activity relationships based on contractor options are far more flexible. –Manpower –Equipment –Contractor’s approach to the project, the contractor’s “means and methods.”

T.L. Martin & Associates Copyright © 2008 Please Proceed to Chapter 2 Key CPM Scheduling Terms