Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.

Slides:



Advertisements
Similar presentations
Cryogenic system in P4: Possible options S. Claudet & U. Wagner LHC Workshop, “Chamonix XlV” January 2005 (Mostly for RF & beam scrubbing)
Advertisements

M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
LHC HARDWARE COMMISSIONING REVIEW May 2005 CRYOGENIC VACUUM SYSTEM Paul Cruikshank for AT/VAC.
A. Perin, CERN, TE-CRG, 26 May Review of the cryogenic by-pass for the LHC DS collimators 26 May 2011 Modifications to the DFBs, DSLC and cryogenic.
Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005.
New HV test specification for the LHC N. Catalan for the EI section.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
SC - 04Feb'13Cryo Heaters Review Cryogenic Heaters Review Operation use and wishes S. Claudet - A. Suraci LHC Cryogenic Operation.
Large-capacity Helium refrigeration : from state-of-the-art towards FCC reference solutions Francois Millet – March 2015.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
CRYOGENICS AND POWERING
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
HC review - 12 May 2005Luigi SERIO - AT/ACR/OP1 SECTOR COOL DOWN AND CRYOGENIC COMMISSIONING L. Serio.
Introduction to LHC cryogenic system (layout, architecture) Preparation before cool-down (Purge, flushing) Transient operations to reach nominal operating.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
Cryogenics in SPS & LHC (2 K / 4.5 K) LHC-CC11, 14 November 2011 L. Tavian, CERN, TE-CRG With the contribution of N. Delruelle, G. Ferlin & B. Vullierme.
LHC Insertions Upgrade Working Group (LIUWG) Space available in tunnel Y. Muttoni.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
05 Novembre 2003Chamonix XIV Workshop, January How to deal with leaks in the QRL and magnet insulation vacuum Paul Cruikshank for AT/VAC Germana.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
HC review, A. Perin, 12-MAY DFB Project LHC hardware commissioning review May 2005 Hardware commissioning of the DFBs and DSLs and connection.
L. Serio COPING WITH TRANSIENTS L. SERIO CERN, Geneva (Switzerland)
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
JRA on Development of High Temperature SC Link Motivation Work Packages Partners & resources Amalia Ballarino Esgard open meeting CERN,
Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel.
Cryogenics for crab cavities – SPS/LHC 2 nd HiLumi LHC meeting – Frascati (Italy) 15 November 2012 K. Brodzinski and L. Tavian on behalf of cryogenic team.
The cryogenic system of the HIE-ISOLDE project and its related hazards for persons N. Delruelle on behalf of the TE/CRG group HIE-ISOLDE Safety Review.
SM18 cryogenics infrastructure upgrade L. Serio TE-CRG.
CHAMONIX XV QRL installation and first experiences of operation G. Riddone on behalf of the QRL team AT/ACR-cd Acknowledgements to AT/ACR-op and AT/ACR-in.
The integration of 420 m detectors into the LHC
AT-MEL Group Meeting, CERN, 1211 Geneva 23 1 ElQA activities during hardware commissioning N. Catalan Lasheras.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
Can we change a magnet without warming-up a full arc ? Serge Claudet, With help from P. Cruikshank & J-P. Tock (Chamonix Jan’10)
D. Delikaris, TE-CRG, LSC 25th Meeting Page 2 October 18 th, 2013 LS1 Committee (LSC)- 25 th Meeting D. Delikaris, TE-CRG Cryogenics activities.
TE-CRG Activities D. Delikaris, TE-CRG.
LMC 1 (Pre Chamonix) DN200 relief valve position DN200 relief valve position On top wherever possible. Open W bellows for MLI protection. On top wherever.
LHC Machine Advisory Committee Meeting no.19 QRL status 16 June 2006 G. Riddone, AT-ACR On behalf of the QRL team.
5-year operation experience with the 1.8 K refrigeration units of the LHC cryogenic system G. Ferlin, CERN Technology department Presented at CEC 2015.
LHC Cryogenics From cool-down to 1st beams Serge Claudet (LHC Cryo OP), On behalf of cryo teams involved.
LHC Cryogenics, equipment & interventions around P3/P7 S. Claudet, “volunteer” for TE_CRG 16 Oct’14.
Logo area HL LHC IT STRING M. Bajko CERN TE-TM and QXF Review.
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
Workshop on cryogenic & vacuum sectorisation of the SPL Vacuum Sectorisation Paul Cruikshank, CERN Technology Department (TE) Vacuum Surfaces & Coatings.
Workshop on Appraisal of Disassembled Magnets: Lessons learned March 17 th, 2005 Boundary Conditions-Technical Specification Jos Vlogaert.
FCC Infrastructure & Operation Update on the cryogenics study Laurent Tavian CERN, TE-CRG 28 October 2015.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
L. Tavian, TE/CRG, LSC Page 2 February 21 th, 2014 LS1 Committee (LSC) L. Tavian TE-CRG.
LHC experience with installation Katy Foraz March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop ***********************************
SIS 100 Vacuum chamber Recooler String system Components
TE-CRG Activities A. Perin, on behalf on the Cryogenics Group.
Cryogenics storage and distribution
HL-LHC IT STRING and Series test of SC link
Update of cryogenic activities
SPS cryogenic proximity equipment and SM18 validation
CRYOGENICS – strategy, unavailability root causes and limitations
Consequences of warming-up a sector above 80 K
Keeping LHC cold during LS periods Preliminary proposal
Hollow e- lens, Cryogenic aspects
Renovation of the 45-year old PS magnets
ILC Cryogenic Systems Draft EDR Plan
TEST PLANS for HL LHC IT STRING
Teleconference ACS – FREIA 20th February 2018
ILC Experimental Hall Cryogenics An Overview
CTF Users’ Perspective
Summary post TCC#54_02Aug’18
Conceptual design of the Cryogenic System of Comprehensive Research Facility for Key Fusion Reactor Core Systems Liangbing Hu Sep.4.
HL-LHC New MS optimisation WP9, Preliminary cost estimates
Presentation transcript:

Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January 2005

Workshop Chamonix XIV, Contents Overview of the cryogenic system Commissioning of the cryogenic sub-system (refrigeration system, DFBs, DSLs and QRL) Possible shortcuts Conclusions

Workshop Chamonix XIV, Cryogenic overview

Workshop Chamonix XIV, Point 8 as an example Redundant systems for sector commissioning (upon QULA/ex-LEP ref. completion) (no redundancy for sector 2-3) Superconducting link (DSL) 4.5 K refrigerator 1.8 K refrigerator Cryogenic Inter- connection box (QUI) Cryogenic Ring Line (QRL) Electrical feed Boxed (DFB) Local transfer Lines (QUL)

Workshop Chamonix XIV, Cryogenic sub-system commissioning Individual components and sub-systems are manufactured in industry After delivery and installation at CERN each sub-system is individually commissioned The commissioned and qualified sub-systems are then used in a cascade way to commission dependent sub-systems The collective behavior of the cryogenic sub- systems is progressively tested and overall process established

Workshop Chamonix XIV, Commissioning phases Phase 1: »storage »new and existing 4.5 K refrigerators »cryogenic interconnection box »1.8 K refrigerator »transfer lines (vertical and local) Phase 2 »QRL Phase 3 »QRL + DFBs + DSLs + magnets: global pressure test Ready for sector commissioning Refrigeration system

Workshop Chamonix XIV, Refrigerator system /1 New 4.5 K refrigerators: all 4 units installed and commissioned »Capacity and transient test performed »Used for commissioning of QUI, QURC, QRL and magnets »Very valuable experience gained when testing sub-systems together in Point 8 (QSRB, QUI, QURC) Ex-LEP 4.5 K refrigerators »Possibility to use it for commissioning of QRL* »Compressor station upgraded and tested in 1998 »Cold box upgrade foreseen mi-2005 to mi-2006 »Functionality test foreseen (2-3 weeks) »Critical for LHC operation, redundant for LHC commissioning (except sector 2-3) * 1 refrigerator cannot serve the two adjacent sectors in different operation modes

Workshop Chamonix XIV, Refrigerator system /2 1.8 K Refrigerators »Not used for QRL commissioning, critical for magnet testing »Pre-series already capacity tested »Foreseen tests of all 8 units after installation »Test of first unit underground already started Cryogenic interconnection box »Used for the QRL »Installed at P8, P2, P4, P6 and tested at P8 »P8: consolidation under way »Critical for commissioning and LHC operation

Workshop Chamonix XIV, Refrigeration system /3 Storage »Completely installed and tested QPLB (Vertical transfer lines) »Needed for the QRL »First two (of four) lines commissioned and accepted. Last two lines simplified test with positive impact on schedule and resources. QULs (Local Transfer lines) »Will be needed for the sector 2-3. For other sectors, could be used for the QRL upon completion of QULA/QURA/QSRA (end 2005 – mid 2006) »First unit tested. Design validated »Requires adjacent components to be installed, and will be commissioned together with them

Workshop Chamonix XIV, Electrical Feed-boxes (DFB) and Superconducting links (DSL) »Critical for magnet powering »Cannot be tested in situ prior to magnet tests DFB »See presentation of A. Perin DSL »Cannot be completely tested without the DFBL and the magnets »Type test (mechanical and thermal) foreseen in SM18 of 30 m of the line. Powering test requested by EEWG. »Type test to be done in parallel with installation, no impact on schedule

Workshop Chamonix XIV, QRL commissioning Critical for magnet commissioning Tests: »Tests at factory »Warm commissioning during and after installation »Cold commissioning

Workshop Chamonix XIV, QRL / Tests at factory QRL Elements (~300 / sector) Leak test of individual circuits (RT) Global leak test (RT) Pressure test (RT) N2 cooldown Pipe elements (1) 100 % (B+F)100 % (MWP (2) ) at the beginning, then digressive == Fixed points 100 % = Service modules 100 % 10 % Steps/elbows 100 % = (1): absence of penetrating welds (2): MWP, maximal working pressure (e.g bar for header C)

Workshop Chamonix XIV, QRL / Warm commissioning EACH SUB-SECTOR He leak test after installation of each sub-sector: detection of warm leaks SECTOR Combined pressure and leak test: validation of the mechanical integrity at warm condition - No cryogenic sectorisation - Vacuum sectorisation 8 vacuum barriers, 9 vacuum insulation sub- sectors

Workshop Chamonix XIV, QRL / Cold commissioning Cold commissioning  baseline: 8 weeks [12 for the fist sector] »cool down, »thermal cycles, »heat inleaks Validation of: »mechanical design (cold leaks) »thermal design (heat inleaks) »instrumentation and valves (functionality) QRL design »Standard design: QRL in the straight part of the tunnel (same design for all the 8 sectors) »Special design: QRL in the “Junction region (about m)”, from the QUI to the straight part of the tunnel (each JR is unique)

Workshop Chamonix XIV, QRL / Possible shortcuts Helium leak test of the sub-sector »Allocated time: 3 weeks for each sub-sector, done in parallel to the installation of other sub-sectors »Reason of the test: detection of warm leaks, »Benefit of skipping the test: None, no impact on the schedule of the QRL installation »Risks if the test is skipped: detection of leaks during combined pressure and leak tests, when magnets are already transported »Repair if the test is skipped: leak detection in situ, magnet removal, opening of interconnections, repair (if leak is in interconnection) or replacement of the faulty element

Workshop Chamonix XIV, QRL / Possible shortcuts Combined pressure and leak tests »Allocated time: 3 weeks »Reason of the test: validation of the QRL design at warm condition, detection of warm leaks »This test CANNOT be skipped, it can be postponed with large risks: detection of leaks during commissioning of magnets »Repair: leak detection in situ, magnet removal, opening of interconnections, repair (if leak is in interconnection) or replacement of the faulty element

Workshop Chamonix XIV, QRL / Possible shortcuts Cooldown and thermal cycles »Allocated time: 2 days per cycle weeks for instrumentation commissioning »Reason of the test: mechanical validation at cold condition (differential thermal contraction), detection of cold leaks (quality of welds) commissioning of the instrumentation of cold condition »Benefit of skipping the test: Shorter QRL commissioning, at least one cycle is mandatory »Risks if the test is skipped: detection of leaks during sector commissioning, longer instrumentation commissioning during magnet commissioning »Repair: leak detection in situ, magnet removal, opening of interconnections, repair (if leak is in interconnection) or replacement of the faulty element

Workshop Chamonix XIV, QRL / Possible shortcuts Heat inleaks measurements »Allocated time: about 2-3 weeks per test (very difficult to estimate due to the unknown stabilization time) »Reason of the test: validation of the thermal design »Benefit of skipping the test: Shorter QRL commissioning (gain: about 4-5 weeks per sector) »Risks if the test is skipped: higher heat inleaks during sector commissioning, reason (QRL and magnets) cannot be easily identified (cold spots help) »Repair: very difficult to add refrigeration capacity 23 kW11 W320 W

Workshop Chamonix XIV, Conclusions / Refrigerator Systems All tests foreseen can be done without impact on the installation and test of the magnet system Valuable experience will be gained through these tests »Training of operation team »Definition of automatic procedures for connection of sub- systems »Identification of weak points All of which will make us gain time during future LHC commissioning Operational resources can be spared by skipping test, but valuable experience and training will be lost Test should be done as foreseen

Workshop Chamonix XIV, Conclusions / DFBs and DSLs DFBs: see presentation A. Perin DSLs: »Type test to be done in parallel with installation, »No impact on schedule Type test should be kept to verify design

Workshop Chamonix XIV, Conclusions / QRL He leaktightness of the sub-sector should be kept (no schedule impact on the QRL installation) Combined pressure and leak test: cannot be skipped, can be postponed with large risks Cooldown/thermal cycles: »At least one thermal cycle per sector (quick test) »Several thermal cycles (6-7) recommended for sectors with “old” production and might be skipped for sectors with only “new production”

Workshop Chamonix XIV, Conclusions / QRL Heat inleaks measurements »First sector (8-1): the full sector will be measured (old and new production) »Sector 7-8: heat inleaks will be measured on a portion of QRL (subsectors A, B,…), needed a dedicated return box, scaling to rest of the sector might be difficult as sub-sector A is not standard Full sector measurement will be performed if partial measurement reveals higher heat inleaks than specified »Other sectors: measurement on a portion of QRL will not be possible with current AL installation sequence, measurement of at least one full sector with only new production is highly recommended »If measurements are skipped: Critical headers: B and F (contribution from headers C and D are negligible with respect to the dynamic loads) : Header F (41% of total heat load): cold spots might be a reason for higher heat inleaks Header B (89 % of total heat load, factor 2 margin in ultimate operation): measurements are still possible with magnets.