Tuesday 3 rd May 7:30 Access in the SPS to replace injection kicker magnet terminating resistor after radiation cool down overnight 9:45 probes injected.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Monday 4 th to Friday 8 th Technical stop  Coordination: Katy Foraz  Machine back to Operations Friday evening on schedule Major cryogenics intervention.
Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
Friday 23 rd November - morning Coming out of loss maps over night Thu – Fri  in shadow of MKD problem in SPS (and CMS cryo recovery) 07:35 Start pre-cycle.
21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
5/11/2012LHC 8:30 meeting Summary of Week 44 Coordination: Mike Lamont & Jan Uythoven.
LHC Wed 16 Sept 2015 Struggling with cryo o-night Tuesday - Wednesday 07:11 Injecting again 09:00 Dump on injection of train of 144 bunches, losses IP7.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
LHC Status Sat Morning 18-June Bernhard Holzer, Gianluigi Arduini et al Tentative Planning: Luminosity 1092 x 1092 Access: installing low pass filter at.
Saturday 25/11/10 & Night 12:24 Dump fill #1523 after more than 8 hours in physics It takes some time to get back:  Parallel sequences: Fewer clicks to.
LHC 8:30 meetingEBH 1  Cryogenics recovery in point 8  Meanwhile a couple of accesses:  MKI investigation on noise in IP2  Insulation Vacuum.
Friday morning Dump fill due to the trip of the RQF.A78  intervention had been just planned for the morning on the circuit Access, interventions:  RQF.A56/78,
LHC 8:30 meetingEBH 11 Thursday 24 November 2011.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
00:15: Stable beams fill 1883, 1.1E33 cm-2s-1.  Seems the 144 bunches beam 1 doe not fit properly on the injection kicker waveform. Systematically the.
Monday h34: beam (1020b) lost after 10 Hz RF trim. Fill h56: XPOC to be reset by expert. 08h18: Masked QPS_STATE SIS interlocks for RB.A12.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Friday 2 nd November 08:45 Stable beams Fill 3253 Initial luminosity ~7.3e33 cm-2s-1 09:45 Increase RF voltage from 10 MV to 12 MV 12:00 ADT to wideband.
Monday :00 Injection for physics fill # :00 Stable beams fill #1816, luminosity ~1.2x1033 cm-2s-1 11:08 Beams dumped. QPS trigger on detector.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
08h15: Injection.  Correction injection oscillations.  Transfer line steering.  Losses at 30% of dump threshold, limited by SPS scraping. 12h35: Start.
Monday 12 th November 04:50 Beam dump, trip of RF line 4B, integrated L ~120 pb-1. Access for RF. 07:00 Injecting. FBCT phasing. Line steering. 09:59 Beam.
04:01 Injection kicker timing problems B2  Injection pre-pulse shifted, causing BETS to inhibit beam injection. 144 bunches on TDI.  Run without ROF.A81B2.
Tuesday 26 th April – morning shift 08:00 Great news, cryo is back! Unluckily it was followed by many other problems, one after the other one. So, spent.
LHC 8 & 9 May :10: Injection kicker B1 faulty on oil level –Check in UA and RA. Leaks fixed, to be further checked in TS1 10:30: Pre-cycle started.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Lumi scan limits checked (in preparation for next fill VdM scans).  Trims of up to 150 um per beam in IP1 & IP2 both planes both beams were done (IP5.
Injection issues overnight 10:50 Access  QPS & EPC  Vacuum leak SPS – magnet to be replaced Monday – cycling for FT and LHC only over the weekend 12:15.
Another typical LHC day. 06:15 Fill 2000 dumped 08:44 Stable beams – fill 2001  1.675e14  1.21e11  ~2 microns normalized emittance 11:34 Beams dump.
Saturday 14:10 Cryogenics back [26 hours 40 minutes] Pre-cycle 15:30 Beam 2 in  Interlock on TCLIB.6R2.B1. Alessandro Masi found a broken sensor, it would.
Thursday 27 th October 00:57 fill 2257 dumped during squeeze (RQTF.A67B1) 03:52 stable beams fill #2258 4:33 Dumped, problem of LBDS dilution kicker power.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
Tuesday 7/7 & Night 8/7 06:53 Beam lost due to RF problem, understood  08:30 Access –VIP, Experiments, QPS, EPC, ABT, RF, BI, …. 15:15 Access over, expert.
Monday Recover after trip of RB.A81  Cause of the trip not clear. MP3? 09:00-13:00 Re-inject and Injection verification. In parallel investigations on.
Machine Coordinators: G. Arduini, J. Wenninger
Friday 15th June 01:11 Injection.
Monday :00 Stable beams 9_6_6_6 13:40 Access.
Friday 30th September 06:00 Operator dump fill #2171, int. lumi about 75 pb-1 Previous operator dump from physics was on 14 September ! 07:00 Start of.
Summary Friday h38: Ramp down and pre-cycle.
Tuesday Fill lost #1855 at 7:28 due to the trip of RQX.R1. This was traced to a software bug in the FGC… The Class 51 (LHC_PC) FGC software has been upgraded.
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Monday 6th August & night
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Wednesday 31 October: Morning
Bernhard Holzer, Joerg Wenninger
Friday day 00:51 Fill #1862 Beams lost to inner triplet skew quad power converter fault. Delivered lumi 33 pb-1 Access required for repair RQSX3.L1 converter.
LHC Status Sun Morning 20-Mai
Friday :00 machine setup for luminosity run. Better b-to-b stability from injectors. 01:58 stable run with 228 bunches 11:00 luminosity leveling.
Saturday – Morning 7:36 beams dumped
Finally.... We had to wait a long time.... We had many problems....
Friday Morning 7:30 injection for fill 2908
Monday 24 October hours of 25ns MD
Friday 25 bunch fill dumped just before (BLM in 5)
Saturday 3rd November - morning
Fill 1743 Peak luminosity ~6.7 e32 Integratated lumi ~20 pb-1
Monday 6th 07:39 Dump fill #1854, RQ6.L2 tripped, followed by access
Saturday Wire scans at end of fill 1253 B1H : 4.2 B1V : 4.3 B2H : 5 B2V : 7.2 Beams dumped (after ~14h of collisions) Some issues during refill.
Friday 8/10/10 - Morning Planned to keep fill until the afternoon
Cold compressor speed S45
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Thursday
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Tuesday 24/5 Fill # :00 Stable beam fill # bunches
Wednesday morning Waiting for PS – problem on RF cavity.
Saturday 28th 08:17 Fill #1812: Stable beams, peak luminosity ~1.1x1033 cm-2s-1 19:00 Go to adjust for RF-checks; Record fill lumi of 31.7 pb-1 for CMS.
Saturday 26 November 2011.
Tuesday
Presentation transcript:

Tuesday 3 rd May 7:30 Access in the SPS to replace injection kicker magnet terminating resistor after radiation cool down overnight 9:45 probes injected in the LHC but some SPS problems 11:45 Filling for physics fill #1756  13:45 Stable beams  14:03 Beam dumped due to Uninterruptable Power Supply (UPS) problem point 5 (EBS 11/56) UPS problem point 5  20:15 External company on site to fix faulty UPS  Smoke alarm due to UPS fault and search lost  Presently waiting for additional, external UPS experts to arrive LHC 8:30 meeting 04/05/2011

Fill #1756 Injection not very clean, oscillations and losses in the transfer line Some bunches vertically blown up (see below) Lumi’s around 730 Hz/ub  Max values Atlas 725, CMS 730 Hz/ub  Atlas corrected published lumi downwards, now agrees with CMS Only lasted 18 minutes – dump UPS LHC 8:30 meeting 04/05/2011 Bunch sizes before dump:

UPS broken in UJ56 Fault at 14:03  Decided not to continue while shunting out with other UPS External company required  20:15 External piquet on site Tried elements from UPS in IP4 to fix broken UPS IP5  04: Did not work Waiting for more experts to arrive at 9 am More news asap LHC 8:30 meeting 04/05/2011

Plan 6:00 Start of MD period  Until Monday morning, when the TS will start First MD of Werner cancelled Will pick up the MD program with a working machine as soon as possible LHC 8:30 meeting 04/05/2011