Proton Driver at Fermilab Keith Gollwitzer Accelerator Division Fermilab IDS-NF 7 th Plenary Meeting Oct 17-19,2011.

Slides:



Advertisements
Similar presentations
1 Project X Proton Driver David Neuffer September 2011.
Advertisements

ISS meeting, (1) R. Garoby (for the SPL study group) SPL-based Proton Driver for Facilities SPL-based Proton Driver for Facilities at CERN:
ISIS Accelerator Division
Ion Accelerator Complex for MEIC January 28, 2010.
Muon Collider 2011 Workshop Jun 27-July 1 in Telluride, CO Gollwitzer & Nagaitsev presented Attending: Ankenbrandt, Lebedev, Pasquinelli, Popovic, and.
Task Force on Project X for Muon Collider Keith Gollwitzer Accelerator Division Fermilab.
Project X – MAP Task Force Keith Gollwitzer Accelerator Division Fermilab Project X Collaboration Meeting Oct 25, 2011.
Thomas Roser Snowmass 2001 June 30 - July 21, MW AGS proton driver (M.J. Brennan, I. Marneris, T. Roser, A.G. Ruggiero, D. Trbojevic, N. Tsoupas,
Paul Derwent 30 Nov 00 1 The Fermilab Accelerator Complex o Series of presentations  Overview of FNAL Accelerator Complex  Antiprotons: Stochastic Cooling.
Front End Test Stand Klystron Commissioning Alan Letchford UKNF Plenary Meeting 22 nd April 2009.
Brookhaven Science Associates U.S. Department of Energy AGS Upgrade and Super Neutrino Beam DOE Annual HEP Program Review April 27-28, 2005 Derek I. Lowenstein.
Simultaneous Delivery of Parallel Proton Beams with the EURISOL Driver
Fermilab, Proton Driver, Muon Beams, Recycler David Neuffer Fermilab NufACT05.
Proton Driver: Status and Plans C.R. Prior ASTeC Intense Beams Group, Rutherford Appleton Laboratory.
F Project X Overview Dave McGinnis October 12, 2007.
EDM2001 Workshop May 14-15, 2001 AGS Intensity Upgrade (J.M. Brennan, I. Marneris, T. Roser, A.G. Ruggiero, D. Trbojevic, N. Tsoupas, S.Y. Zhang) Proton.
Secondary Particle Production and Capture for Muon Accelerator Applications S.J. Brooks, RAL, Oxfordshire, UK Abstract Intense pulsed.
Muon Collider Design Workshop, BNL Dec-09112/01/2009 C.W. Linac Options (talk not much different from talk at High Intensity Proton Accelerator Application.
January 5, 2004S. A. Pande - CAT-KEK School on SNS MeV Injector Linac for Indian Spallation Neutron Source S. A. PANDE.
J. Pasternak First Ideas on the Design of the Beam Transport and the Final Focus for the NF Target J. Pasternak, Imperial College London / RAL STFC ,
Alexander Aleksandrov Oak Ridge National Laboratory
Proton Delivery to Target Keith Gollwitzer Accelerator Division Fermilab MAP 2012 Winter Meeting March 7, 2012.
Proton Driver Main Linac Parameter Optimization G. W. Foster Proton Driver General Meeting Jan 19, 2005.
PROTON LINAC FOR INDIAN SNS Vinod Bharadwaj, SLAC (reporting for the Indian SNS Design Team)
HWDB: Operations at the Spallation Neutron Source Workshop on Accelerator Operations August 6-10, 2012 Glen D. Johns Accelerator Operations Manager.
Project X Injector Experiment (PXIE) Sergei Nagaitsev Dec 19, 2011.
Proton Driver Keith Gollwitzer May 31, Initial Design Overview For design purposes, the following is assumed –H - beam comes from PIP II and follow-on.
Proton Beam for PRISM Keith Gollwitzer Accelerator Division Fermilab 5 th Workshop Project X Physics – Muons November 8, 2010.
Fermilab Proton Driver and Muons David Johnson Fermilab Neutrino Factory Muon Collider Collaboration Meeting March 14, 2006.
ICFA-HB 2004 Commissioning Experience for the SNS Linac A. Aleksandrov, S. Assadi, I. Campisi, P. Chu, S. Cousineau, V. Danilov, G. Dodson, J. Galambos,
Project X RD&D Plan Beam Transfer Line and Recycler Injection David Johnson AAC Meeting February 3, 2009.
Proton Source & Site Layout Keith Gollwitzer Accelerator Division Fermi National Accelerator Laboratory Muon Accelerator Program Review Fermilab, August.
WG2 (Proton FFAG) Summary G.H. Rees. Proton Driver Working Group  Participants: M. Yashimoto, S. Ohnuma, C.R. Prior, G.H. Rees, A.G. Ruggiero  Topics:
Fermilab and Muons Proton Driver (for ν-Factory, μ + -μ - Collider, …) David Neuffer Fermilab.
Booster Losses Keith Gollwitzer PIP and MI 700 kW review January 2015.
DTL Option for MEIC Ion Injection Jiquan Guo, Haipeng Wang Jlab 3/30/
Preliminary MEIC Ion Beam Formation Scheme Jiquan Guo for the MEIC design study team Oct. 5,
Comparison of Fermilab Proton Driver to Suggested Energy Amplifier Linac Bob Webber April 13, 2007.
Proton Driver / Project X Keith Gollwitzer Fermilab August 30, 2012.
F A Fermilab Roadmap Dave McGinnis May 28, f Fermilab Roadmap - McGinnis Timelines  Divide the road map into three parallel paths  ILC - Energy.
Early Beam Injection Scheme for the Fermilab Booster: A Path for Intensity Upgrade Chandra Bhat Fermi National Accelerator Laboratory DPF2015, ANN ARBOR,
Status of Project X Keith Gollwitzer Accelerator Division Fermilab MAP Winter Meeting - March 1, 2011.
Proton Driver Design Keith Gollwitzer Fermilab February 19, 2014.
NuFACT06 Muon Source at Fermilab David Neuffer Fermilab.
Protons for Neutrinos: Mid-Term and Project-X Bob Zwaska Fermilab Intensity Frontier Neutrino Working Group Meeting October 24, 2011.
F Project X: Recycler 8.9 GeV/c Extraction D. Johnson, E. Prebys, M. Martens, J. Johnstone Fermilab Accelerator Advisory Committee August 8, 2007 D. Johnson.
Overview of Project X ICD and RD&D Plans David Neuffer material from Paul Derwent & Sergei Nagaitsev (AAC Meeting, February 3, 2009)
Project X: Accelerators Sergei Nagaitsev September 2, 2011.
Proton Driver Keith Gollwitzer Accelerator Division Fermilab MAP Collaboration Meeting June 20, 2013.
N.Solyak (on behalf of PrX team) Fermilab Project X Collaboration Meeting, FNAL, Oct.25-27, 2011 N.Solyak, Pulsed Linac1 PrX Collab. Meeting, FNAL, Oct.25-27,
F Sergei Nagaitsev (FNAL) Aug Project X ICD2 Briefing.
Neutrino Factory by Zunbeltz, Davide, Margarita, Wolfgang IDS proposal.
Presenter : Yang Wu McMaster University Work conducted at IHEP.
Project X as a Muon Facility Platform Keith Gollwitzer Fermilab Accelerator Advisory Committee November 7-9, 2011.
Booster/Muon Campus Stage 1+ 1 GeV Nuclear/Booster-Muon Campus Stage 1 3 GeV Linac/1GeV program Stage 2 3 GeV 3-Way split Stage 2 3 GeV-8 GeV Linac Stage.
FFAG Studies at BNL Alessandro G. Ruggiero Brookhaven National Laboratory FFAG’06 - KURRI, Osaka, Japan - November 6-10, 2006.
F Sergei Nagaitsev (FNAL) Webex meeting Oct ICD-2 chopper requirements and proposal #1.
PSI, Zurich February 29 – March Session classification : Accelerator Concepts Tuesday, March 1, 2016 Introduction Vyacheslav Yakovlev Fermilab,
Steve Holmes DNP Meeting/Santa Fe November 6, 2010 Project X: A Multi-MW Proton Source at Fermilab.
UK Neutrino Factory Conceptual Design
SuperB Injection, RF stations, Vibration and Operations
Injector Chain General and more about p-RCS
Muon Acceleration using 8 GeV Proton Driver Linac
Superbeams with SPL at CERN
Progress towards Pulsed Multi-MW CERN Proton Drivers
General Issues for a Multi-MW driver
DTL for MEIC Ion Injection
MEIC New Baseline: Part 9
JLEIC 200 GeV ion beam formation options
RF system for MEIC Ion Linac: SRF and Warm Options
Presentation transcript:

Proton Driver at Fermilab Keith Gollwitzer Accelerator Division Fermilab IDS-NF 7 th Plenary Meeting Oct 17-19,2011

Project X Review/Intro October 18, 2011Gollwitzer -- 7th IDS-NF Meeting2

Project X Review/Intro October 18, 2011Gollwitzer -- 7th IDS-NF Meeting3 Front End (warm) H- ion source, RFQ, MEBT, Programmable Chopper System Initially 5mA Programmable Chopper Capable of bunch by bunch 162.5MHz Will suppress beam to limit beam current down stream to 1mA average

Project X Review/Intro October 18, 2011Gollwitzer -- 7th IDS-NF Meeting4 3 GeV CW SRF Linac Average beam current 1mA 325 and 650MHz

Project X Review/Intro October 18, 2011Gollwitzer -- 7th IDS-NF Meeting5 Splitters Pulsed Dipole to switch from 3GeV experiment area and Pulsed Linac Transverse RF beam splitter synchronized with programmable chopper

Project X Review/Intro October 18, 2011Gollwitzer -- 7th IDS-NF Meeting6 Pulsed Linac 1.3GHz SRF 3-8 GeV 5% duty factor at 10Hz

Project X Review/Intro October 18, 2011Gollwitzer -- 7th IDS-NF Meeting7 Recycler/Main Injector/Beam Lines Upgrades to handle increase beam power Stripping H- and accumulation of protons at 8GeV

Project X Summary CW Linac will support average beam current of 1 mA to 3 GeV Pulsed Linac (3-8 GeV) will have a ~5% duty factor Possible 8 GeV beam power of 320 kW Programmable Chopper System (part of H- source) will provide appropriate bunch structure for the linac experiments as well as fill the appropriate part of the RF buckets in the accumulating Recycler Ring October 18, 2011Gollwitzer -- 7th IDS-NF Meeting8

October 18, 2011Gollwitzer -- 7th IDS-NF Meeting9 Chopping and Splitting Average

October 18, 2011Gollwitzer -- 7th IDS-NF Meeting10 Fine Chopping Average

Neutrino Factory Upgrade Project X –4 MW at 8 GeV Increase particles per linac bunch Increase pulsed linac duty factor Repackage linac beam for ~60 Hz delivery –Accumulator Ring Collect linac beam into bunches –Compressor Ring Narrow bunches to <= 3 ns –Single Bunch Transfer/Extraction October 18, 2011Gollwitzer -- 7th IDS-NF Meeting11

Neutrino Factory Layout October 18, 2011Gollwitzer -- 7th IDS-NF Meeting12 Accumulator Ring Compressor Ring 4MW Target ??

Task Force Fermilab Management established a group to identify the upgrade path from Project X and look into feasibility of providing the desired 4MW beam Agreed on Project X upgrade numbers –Increase to 5 mA average current –Increase pulse linac duty factor to 10% Outlined options/limitations –Striping –Accumulator and Compressor Rings Discussing instability limitation for rings October 18, 2011Gollwitzer -- 7th IDS-NF Meeting13

Project X Upgrade Neutrino Factory October 18, 2011Gollwitzer -- 7th IDS-NF Meeting14 Front End (warm) H- ion source, RFQ, MEBT, Programmable Chopper System Initially 5mA Run at 10mA (Ion source is capable) Programmable Chopper Capable of bunch by bunch 162.5MHz Will suppress beam to limit beam current down stream to 5mA 1mA average Entire front end is being designed for 10mA

Project X Upgrade Neutrino Factory October 18, 2011Gollwitzer -- 7th IDS-NF Meeting15 3 GeV CW SRF Linac Average beam current 1mA 5mA 325 and 650MHz Retuning of couplers to be efficient May set initially for higher current

Project X Upgrade Neutrino Factory October 18, 2011Gollwitzer -- 7th IDS-NF Meeting16 Pulsed Linac 1.3GHz SRF 3-8 GeV 10% 5% duty factor at 10Hz 15Hz More RF power Upgrade of couplers More cryo capicity

Rings’ Concepts Simple numbers to start –T rev ~ 800 ns –f rf ~ 10 MHz –h = 8 –Injection scheme ~50 ns beam ON followed by ~50 ns NO beam Evolution of design –Increase of circumference (~300m) –Space for RF and Injection/Extraction components –Concerns Injection: Stripping Instabilities Beam size in Compressor after bunch rotation –Several designs and will settle on one October 18, 2011Gollwitzer -- 7th IDS-NF Meeting17

Costing? Fermilab engineering resources are busy A little work has been done for Project X upgrades –Project X has been doing lots of costing exercises Rings (& new beam lines – inc. Final Focus) –Need to settle on lattice –Get count for components, cables, power supplies, RF.... October 18, 2011Gollwitzer -- 7th IDS-NF Meeting18

Plan Set rings and beam lines lattice Studies of instabilities Write Task Force report on feasibility Move onto costing October 18, 2011Gollwitzer -- 7th IDS-NF Meeting19