STATUS OF THE MEG CRYOSTAT Construction status Schedule ____________________________________________________________ 04/Agust/06 F. Raffaelli, L. Delfrate.

Slides:



Advertisements
Similar presentations
Xenon Detector Status Liquid Xenon Group. 1 Outline Cryostat construction –Honeycomb panel test at Pisa –Assembly –Cryogenic test at SIMIC –Leak test.
Advertisements

Vacuum Vessel Production Readiness Review
GlueX Solenoid Recent progress and Coil cold tests Paul Brindza September 9, 2004.
VELO RF box status at Nikhef Report at the Meeting for new VELO RF foil development Tjeerd Ketel, Erno Roeland a.o., Nikhef Tjeerd Ketel, Nikhef.
SRF Cryomodule Assembly Facility Plans Tug Arkan AAC, May 10-12, 2005.
June 26, 2009TLH, NFMCC Friday Meeting1 MICE Updates MICE News Overview ISIS and MICE Schedules DAQ Review Spectrometer Update Aspirational Schedule Terry.
CEA DSM Irfu - Bernard GASTINEAU - R3B Technical Board Meeting -April 4, Reactions with Relativistic Radioactive ions Beams GSI Large Acceptance.
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
AMS-02 tracker mechanics status of assembly and integration Inner tracker integration completion: - Assembly and cabling - Temperature and magnetic field.
1 Xenon Detector Xenon Detector Group. 2/22 Contents  Construction Status Cryostat PMT mounts  PMT Pisa PMT test PSI PMT test Trouble report  Neutron.
Clear Fiber and Wave Guide Fab. Makoto YOSHIDA (Osaka Univ.) July MICE FT
Cryo Capture Cavity II Progress Mike McGee April 6, 2005.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Xenon Detector Xenon Detector Group. 1 Contents Cryostat Construction Detector Preparation Schedule.
Aluminum bellows for experiments
Fcal upgrade for sLHC: Cryogenics modifications – TE-CRG/ C.Fabre 1 ATLAS FCal Upgrade for sLHC: Modifications to the Calorimeter Cryogenic.
Construction of Wendelstein 7-X Max-Planck-Institut für Plasmaphysik
R&D Status and Plan on The Cryostat N. Ohuchi, K. Tsuchiya, A. Terashima, H. Hisamatsu, M. Masuzawa, T. Okamura, H. Hayano 1.STF-Cryostat Design 2.Construction.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
Office of Science Coupling Coil Status S. Gourlay August 1, 2012.
RICH WG M.Lenti. Outlook Mirror Support Vidyo meeting on June 12, 20, 27 and on July 4 and 11 RICH WG meeting on august 27  Vessel status (see Ferdi’s.
16-Oct-15S.Movchan Straw manufacturing and QC1 Straw machine status polished anvil new welding configuration software for on-line seam quality control.
15 October 2013 CHANTI Status Report F. Ambrosino, T. Capussela, D. Di Filippo, P. Massarotti, M. Mirra, M. Napolitano, L. Roscilli, G. Saracino Università.
News on mechanics Photon veto F. Raffaelli INFN – Sezione di Pisa CERN, January r 02 th, Status of tender Anti Status of the supporting.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
THE VACUUM BOX FOR COMPASS CRYOSTAT MUNICH 23/10/2007 G. GIRAUDO I.N.F.N. TORINO 1.MECHANICS – OVERWIEV 2.WINDOWS 3.INTEGRATION WITH HODOSCOPE.
1.3GHz Input Coupler for ILC
Matthew Moulson (Frascati) for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 17 July 2012 LAV construction & installation status.
General News M.Lenti. Outlook Reminder of the RICH schedule PMs and sockets: what we have Mirrors What would change for PM holding disks if vacuum inside.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
MEG Cryostat Fabrizio Raffaelli INFN sezione di Pisa
Endcap Signal Feedthrough Overview Endcap Signal Feedthroughs are constructed and tested in Victoria by Victoria and TRIUMF staff. Each feedthrough unit.
D. Greenfield CLRC1 UK-V End-cap Engineering 15 July 2003 Debbie Greenfield, RAL.
Status of Anti project. F. Raffaelli,A. Checchetti,C. Capoccia. INFN CERN, July 14 th, Status of the Anti construction test and schedule. -Status.
Lavs Issues Lav 12. Tube Planning future activities. Conclusions.
10/7/2003Thomas Schneider1 Status report of CERN/PNPI Tooling support for PNPI M2R2 Prototype Plans towards the PRR.
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
28-Feb-16S.Movchan Straw manufacturing and QC1 Straw machine status straw welding machine QC by microscope control by computer straw welding speed optimization:
The integration of 420 m detectors into the LHC
Installation of the T600 at Fermilab CSN2, September 22,
Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 11 December 2012 LAV construction & installation status.
D. Delikaris, TE-CRG, LSC 25th Meeting Page 2 October 18 th, 2013 LS1 Committee (LSC)- 25 th Meeting D. Delikaris, TE-CRG Cryogenics activities.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
S1-Global status report KEK Norihito Ohuchi 2008/11/171ILC08-GDE-Meeting-Chicago.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
Tracker cooling plant refurbishment Project status Revised plan Financial impact.
RF Module Update MICE Collaboration Meeting 44 Andrew Lambert Lawrence Berkeley National Laboratory March 30 th, 2016.
S A Griffiths CM42 June 2015 Electrical & Control.
Teleconf ACS – FREIA 28th March 2017
Cryostats for superconducting magnets
Ti/SS transitions A.Basti INFN-PISA*
Common Projects Status
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973/7200
News about the WA104 Programme
Teleconference ACS – FREIA 10th May 2017
Cryostat design Mechanical design: Thermal screens: Specifications:
Far Detector Activities Late 2017 – Early 2018
Design of Distribution Feedbox at LHC P7
Liquid Xenon Detector Xenon Detector Group 2018/11/18.
Teleconference ACS – FREIA 20th February 2018
Prototype cryomodule development
Undulator System Components Status Dean Walters
Double-Spoke Cavities
Teleconference ACS – FREIA 19th June 2017
UPPSALA UNIVERSITY_GERSEMI PROJECT
Magnetic shielding and thermal shielding
SNS Coupler Shipping Plans
SC1R Cold Box PDR Assembly Sequence
JLAB CHL 2K COLD BOX REPLACEMENT
Presentation transcript:

STATUS OF THE MEG CRYOSTAT Construction status Schedule ____________________________________________________________ 04/Agust/06 F. Raffaelli, L. Delfrate

CONSTRUCTION STATUS The vacuum vessel is going to be tested today (04/August/2006). The vacuum window was tested last week. The cold window is going to be tested after the 20 th of August. The Cold vessel is ready for installing the cold window, It has everything (pre-cooling circuit flanges etc). The thin foil of the cold window is going to be welded next week The Honeycomb panel is going to be delivered to SIMIC the 12 th of August. After the 20 th of August the cold window is going to be tested and the last week of August the cold vessel will be tested. The goal is to have the two vessels ready for assembly at the beginning of September. ____________________________________________________________ 04/August/06 F. Raffaelli, L. Delfrate

CONSTRUCTION STATUS We try to investigate the time nodded for the rest of the operations. Simic is agreed with the following planning.. ____________________________________________________________ 04/August/06 F. Raffaelli, L. Delfrate

CONSTRUCTION STATUS Planning 14166_7 (July 21, 2006) July Pressure test of a warm window in the test box (performed on 20 July). Second warm window construction. Cold window mould construction July Warm window welding to the warm vessel. Cold window mould machining. 31 July Delivery by INFN of the honeycomb panel at SIMIC’s workshop 1-11 August Leak tests of the warm vessel. Cold window welding to the test box. Pressure/leak tests of a cold window in a test box with the honeycomb. Second cold window shaping. ____________________________________________________________ 04/August/06 F. Raffaelli, L. Delfrate

CONSTRUCTION STATUS August SIMIC CLOSED 21 August – 4 September Cold window Welding to the cold vessel. Auxiliary internal structure installation (hold - to verify). Pressure/leak tests of the cold vessel. Cold vessel drying. Helicoflex Helium test. Internal structure positioning (hold - to verify) September Temperature sensors installation. Super-insulation installation. Assembly of warm and cold vessel. ____________________________________________________________ 04/August/06 F. Raffaelli, L. Delfrate

CONSTRUCTION STATUS September Welding chimneys Helium test. 02 – 06 October Cold vessel polishing. Cold vessel cleaning and drying October Preparation of Cryogenic test Cryogenic test Leak test again. Shipping. ____________________________________________________________ 04/August/06 F. Raffaelli, L. Delfrate

The windows now are welded on the body directly. A leak test is performed on this weld on the body. This design implies modification of the honeycomb the production of some additional pieces. ____________________________________________________________ 04/August/06 F. Raffaelli, L. Delfrate

How can we do to solve the problems on the Honeycomb. We are changing a material to be able to avoid a transition between the high module fiber to low module fiber in the edge and replacing the filler material non the edges. Right now we have six plies of fiber on each side +45/-45/0/-45/+45 for a total of thickness on.7 mm. In the edge we need to (inter laminar method) a low module fiber to be able to make the bend and a filler material epoxy with glass micro sphere is inserted. The thickness of the honeycomb is 19 mm and the density is 50 Kg/m 3. We are going to use a thicker honeycomb 26.4 mm with the same density to increase the inertia and a fabric fiber with intermediate module will be used to avoid the transition. So an internal reinforcement will be made at the edges. After we contacted the Excel experts We change the adhesive proposed by Playform that was not usable at the Nitrogen temperature ____________________________________________________________ 04/August/06 F. Raffaelli, L. Delfrate

____________________________________________________________ 04/Agust/06 F. Raffaelli, L. Delfrate Conclusions Cryostat construction: The delivery of the cryostat is now at the end of October. The schedule proposed is in agreement with the company. We are doing our best to push the company.