The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.

Slides:



Advertisements
Similar presentations
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Advertisements

Cryogenic system in P4: Possible options S. Claudet & U. Wagner LHC Workshop, “Chamonix XlV” January 2005 (Mostly for RF & beam scrubbing)
Sc Magnet test facility Consolidation Project presentation M. Bajko for the TEMB on behalf of the MSC TF section team 31. Aug
Cold Powering of the HL-LHC magnet system WP6 Motivation Work Package description Tasks Partners & resources Amalia Ballarino HL-LHC Design Study – 3 rd.
Cryogenic Experts Meeting (19 ~ ) Helium distribution system for Super-FRS dipoles and multiplets MT/FAIR – Cryogenics and Magnets Y. Xiang,
Status of VLPC Cryo-Cooler Cryostat Design Russ Rucinski (Alan Bross) Fermilab.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Large-capacity Helium refrigeration : from state-of-the-art towards FCC reference solutions Francois Millet – March 2015.
CRYOGENICS AND POWERING
HQ TEST CERN by Marta Bajko CERN TE-MSC TF For Hi Lumi and LARP the 16 th of November 2011 CERN.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Cryogenic Experts Meeting (19 ~ ) Cooling scheme discussion for 300 Tm High Energy Beam Transfer line (HEBT) with large inclination MT/FAIR –
IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009.
A. Siemko and N. Catalan Lasheras Insulation vacuum and beam vacuum overpressure release – V. Parma Bus bar joints stability and protection – A. Verweij.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
11/07/20071 Hardware Commissioning Forum: DFBs R. Rabehl AT-ACR.
Cryogenics in SPS & LHC (2 K / 4.5 K) LHC-CC11, 14 November 2011 L. Tavian, CERN, TE-CRG With the contribution of N. Delruelle, G. Ferlin & B. Vullierme.
LHC Insertions Upgrade Working Group (LIUWG) Space available in tunnel Y. Muttoni.
LAUC Proposal: Feedboxes and System Engineering bnl - fnal - lbnl - slac US LHC Accelerator Research Program Michael Lamm LARP+LAUC DOE Review June 21,
Spectrometer Solenoid: Plans to Fix Magnet 2 Steve Virostek Lawrence Berkeley National Lab Spectrometer Solenoid Review November 18, 2009.
Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Review-LHC Interaction Regions - Upgrade Phase I Amalia Ballarino, 31 st July 2008 Cold Powering Options Conceptual Design Review of the LHC Interaction.
19./20. September 2007 Current leads for FAIR Cryogenic Expert Meeting 19./20. September 2007 Birgit Weckenmann.
Hall D Target System Review J. FochtmanSeptember 28,2011 Preliminary Design Work.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
AT-MEI-PE, RD, LIUWG 31-JUL R. Denz AT-MEI-PE LHC Luminosity Upgrade Protection of the Inner Triplet, D1, Correctors and Superconducting Links/Leads.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
HC review, A. Perin, 12-MAY DFB Project LHC hardware commissioning review May 2005 Hardware commissioning of the DFBs and DSLs and connection.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Integration studies – Part 1 Inner triplet Y. Muttoni TS-ICC-LI 31 July 2008.
5 th Joint Hi-Lumi LHC-LARP Annual Meeting 2015 SC Link Protection A.Ballarino 28/10/2015.
JRA on Development of High Temperature SC Link Motivation Work Packages Partners & resources Amalia Ballarino Esgard open meeting CERN,
5 th Joint Hi-Lumi LHC-LARP Annual Meeting 2015 Cold Powering New Baseline A.Ballarino 27/10/2015.
Cryogenics for crab cavities – SPS/LHC 2 nd HiLumi LHC meeting – Frascati (Italy) 15 November 2012 K. Brodzinski and L. Tavian on behalf of cryogenic team.
Heat loads and cryogenics L.Tavian, D. Delikaris CERN, Cryogenics Group, Technology Department Accelerators & Technology Sector Friday, October 15, 20101HE-LHC'10.
Superconducting Technologies for the Next Generation of Accelerators CERN, Globe of Science and Innovation 4-5 December Superconducting Links for the Hi-Lumi.
Dimensions, pressures and temperatures of cryogenic circuits for the SPL U. Wagner TE-CRG.
A. BallarinoEucard MeetingCERN,20/03/2013 High-Tc Superconducting Links for the LHC WP 7 – Task 5 A.Ballarino, TE-MSC, CERN Task 5 participants : A. Ballarino,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Cryogenic Cooling Schemes for the SPL U. Wagner TE-CRG.
Cryogenic scheme, pipes and valves dimensions U.Wagner CERN TE-CRG.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
ILC Cryogenic System Shallow versus Deep Tunnel Tom Peterson Dubna Meeting 5 June 2008.
8/29/07K. C. Wu - Brookhaven National Lab1 Major Components in ILC IR Hall Interchangeable Detectors.
Logo area HL LHC IT STRING M. Bajko CERN TE-TM and QXF Review.
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
FCC Infrastructure & Operation Update on the cryogenics study Laurent Tavian CERN, TE-CRG 28 October 2015.
TDR Cryogenics Parameters Tom Peterson 28 September 2011.
ESS | Helium Distribution | | Torsten Koettig Linac – Helium distribution 1.
R. van Weelderen and U. Wagner CERN
SIS 100 Vacuum chamber Recooler String system Components
Existing Prototype Test Facility (PTF) and planned Series Test Facility Schroeder, Claus Cryo-Review Darmstadt
HL-LHC IT STRING and Series test of SC link
M Chorowski, H Correia Rodrigues, D Delikaris, P Duda, C Haberstroh,
SLHC –PP WP6 LHC IR Upgrade - Phase I.
HFM Test Station Main Cryostat
Innovative He cycle Francois Millet.
SPS cryogenic proximity equipment and SM18 validation
Cryogenics for sc links, a short update
Hollow e- lens, Cryogenic aspects
Circuits description and requirements - Closed Session-
Design of Distribution Feedbox at LHC P7
WP3 Meeting – December the 10th 2015 H. Prin
HL LHC WP3 (magnets) TASK 2 ADVANCEMENT
Cooling aspects for Nb3Sn Inner Triplet quadrupoles and D1
Summary post TCC#54_02Aug’18
Cryogenic management of the LHC Run 2 dynamic heat loads
Power Leads for Test Stands
J. Fleiter, S. C. Hopkins, A. Ballarino
Presentation transcript:

The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme 7 Capacities Specific Programme, Grant Agreement Cryogenics for cold- powering at LHC P1 and P5 U. Wagner CERN

17/11/2011 1st HiLumi LHC / LARP2 Topics Given boundary conditions Mechanical Lay-out Process, Overview of considered cooling solutions for the cryogenic circuit Influence on the energy consumption. List of open questions.

Boundary conditions  Considered DFB’s  DFBA: Current feed box for the arc; connected to existing refrigerator.  DFBL: Current feed box for the matching section; connected to new refrigerator  DFBX: current feed box for the inner triplet; connected to new refrigerator. 17/11/ st HiLumi LHC / LARP 3

Boundary conditions 17/11/ st HiLumi LHC / LARP 4 Defined by existing equipment Defined only by tunnel geometry

Assumptions (as in previous presentation)  He consumption for current lead cooling:  As published by A. Ballarino in CERN/AT /11/ st HiLumi LHC / LARP 5  The following assumptions were first formulated in  They are still the baseline today  Link SC is MgB 2  Splice LTS to MgB 2 (magnet to link) requires liquid helium bath.  Max MgB 2 temperature 20K  Max. helium temperature 17 K

17/11/2011 1st HiLumi LHC / LARP6 The DFBA and the existing refrigerators The following slides only concern the DFBA integrated in the existing cryogenic system. The following slides only concern the DFBA integrated in the existing cryogenic system. The total DFBA current is considered to be 220 kA. The total DFBA current is considered to be 220 kA.

17/11/2011 1st HiLumi LHC / LARP7 Helium conditions at interface DFBA Average actual values Sector 4-5Sector 5-6Sector 8-1Sector 1-2 LineT [K] P [kPa] T [K] P [kPa] T [K] P [kPa] T [K] P [kPa] C D E F Not relevant for cooling Worst case considered for study of all points

Transfer line options  See previous presentation  Flexible “Nexans” line  Custom line 17/11/ st HiLumi LHC / LARP 8

Conclusions from 2011 presentation  High current case P1 and P5  The cooling for the current lead defines the helium flow.  Heat load on transfer lines of second order.  Invest design effort to obtain a current lead with low coolant consumption. 17/11/ st HiLumi LHC / LARP 9

17/11/2011 1st HiLumi LHC / LARP10 Cost of cooling comparison Two reference cases Two reference cases Actual cooling with DFB in the tunnel. Actual cooling with DFB in the tunnel. Lower limit. Lower limit. Reference for comparison as this case does not solve our problem. Reference for comparison as this case does not solve our problem. LTSC link, as already realised in LHC P3 LTSC link, as already realised in LHC P3 Upper limit Upper limit Used only as reference! Used only as reference! Unlike for P7 the link in P3 is not sufficient as a demonstrator. Additional R&D might be necessary. Unlike for P7 the link in P3 is not sufficient as a demonstrator. Additional R&D might be necessary.

17/11/2011 1st HiLumi LHC / LARP11 As in previous presentation! Current Base concept (all sites) Helium from line C Helium at max. 17 K

17/11/2011 1st HiLumi LHC / LARP12 Studied cooling options DFBA Several different cooling options were studied Several different cooling options were studied The only relevant solution is: The only relevant solution is: Shield cooling with 20 K gas, mixing of gas for the cooling of the copper part. Shield cooling with 20 K gas, mixing of gas for the cooling of the copper part. Two options: Two options: “Nexans like” line “Nexans like” line Custom line Custom line

17/11/2011 1st HiLumi LHC / LARP13 Cooling methods sketch DFBA The current lead consumption is such that the mixing temperature of the two flows is sufficiently low to cool the copper part. Difference due to heat load of the two TL options.

17/11/2011 1st HiLumi LHC / LARP14 Comparison of cooling methods DFBA Values without uncertainty / overcapacity margin Additional capacity T at Lead [K] T at HTS top [K] Relative Cost [-] K [W] K [g/s] Actual LHC Custom line Nexans line LTS solution * Capacity margin(only if add. Refrigerators)~ 10000~ 10.0 Reference Kept in mind if integration of Nexans line impossible * 50 – 70 K shield load not shown for LTS

17/11/2011 1st HiLumi LHC / LARP15 Conclusion DFBA cooling The additional capacity for the link cooling can be easily covered by the existing refrigerator The additional capacity for the link cooling can be easily covered by the existing refrigerator Provided we have new refrigerators in P4, P1 and P5. Provided we have new refrigerators in P4, P1 and P5. Challenge: Challenge: The total pressure difference for the 20 K gas between supply and return is only about 150 mbar The total pressure difference for the 20 K gas between supply and return is only about 150 mbar The pressure loss budget at the moment is: The pressure loss budget at the moment is: 50 mbar in the link line, 50 mbar in the Current lead, 50 mbar in the return line. 50 mbar in the link line, 50 mbar in the Current lead, 50 mbar in the return line.

17/11/2011 1st HiLumi LHC / LARP16 The DFBX, DFBL and the new refrigerator The following slides concern the DFBX, the DFBL integrated with the new cryogenic system. The following slides concern the DFBX, the DFBL integrated with the new cryogenic system. The total currents are considered to be: The total currents are considered to be: 150kA for DFBX 150kA for DFBX 80 kA for DFBL 80 kA for DFBL As the refrigerator is still to be defined: As the refrigerator is still to be defined: No limits on cooling capacity No limits on cooling capacity No limits on existing lines, pressure or temperatures. No limits on existing lines, pressure or temperatures. We still consider the nominal LHC values for temperature and pressure as boundary condition in the tunnel. We still consider the nominal LHC values for temperature and pressure as boundary condition in the tunnel.

17/11/2011 1st HiLumi LHC / LARP17 Cost of cooling comparison Two reference cases (as before) Two reference cases (as before) Actual cooling with DFB in the tunnel. Actual cooling with DFB in the tunnel. LTSC link, as already realised in LHC P3 LTSC link, as already realised in LHC P3 Considered cooling options Considered cooling options Again the two transfer line options, “Nexans” and custom. Again the two transfer line options, “Nexans” and custom. For the DFBX: For the DFBX: like DFBA, i.e. shield cooling with 20 K gas, mixing of gas for the cooling of the copper part. like DFBA, i.e. shield cooling with 20 K gas, mixing of gas for the cooling of the copper part. For the DFBL: For the DFBL: like above, but as additional option for the “Nexans” solution add flow from the 20 K level in order to limit the mixing temperature to 50K. like above, but as additional option for the “Nexans” solution add flow from the 20 K level in order to limit the mixing temperature to 50K.

17/11/2011 1st HiLumi LHC / LARP18 Cooling methods sketch Shield with 20 K gas and mixing. Calculated for all cases. Shield with 20 K gas and mixing plus additional flow through heater. Nexans line for DFBL only

17/11/2011 1st HiLumi LHC / LARP19 Comparison of cooling methods DFBX Required capacity T at Lead [K] T at HTS top [K] Relative Cost [-] K [g/s] K [g/s] Actual LHC Custom Nexans LTS solution * Reference Kept in mind if integration of Nexans line impossible * 50 – 70 K shield load not shown for LTS

17/11/2011 1st HiLumi LHC / LARP20 Comparison of cooling methods DFBL Required capacity T at Lead [K] T at HTS top [K] Relative Cost [-] K [g/s] K [g/s] Actual LHC Custom Nexans Nexans add flow LTS solution * Discussion: see next slide

17/11/2011 1st HiLumi LHC / LARP21 Cooling of the link for DFBL P1 / P5 The cost of cooling for the Nexans solution is nearly identical as for a LTS solution. The cost of cooling for the Nexans solution is nearly identical as for a LTS solution. From the view point of saving primary energy there is little interest. From the view point of saving primary energy there is little interest. The MgB 2 basically only allows for a transfer line with high heat load. The MgB 2 basically only allows for a transfer line with high heat load. To be verified: To be verified: The highest temperature necessary for the lead cooling. The highest temperature necessary for the lead cooling. Possibility to integrate the MgB 2 cable for DFBX and DFBL in the same cryostat (transfer line). Possibility to integrate the MgB 2 cable for DFBX and DFBL in the same cryostat (transfer line). This would lead to a cost of cooling as for the DFBA. This would lead to a cost of cooling as for the DFBA. Even if of little interest for the cost of cooling, the Nexans line might still be a valid option as discussed before. Even if of little interest for the cost of cooling, the Nexans line might still be a valid option as discussed before.

17/11/2011 1st HiLumi LHC / LARP22 Uncertainties and recommendations How to link the different power supply lines in the tunnel for the matching section? How to link the different power supply lines in the tunnel for the matching section? At least a concept should be fixed. At least a concept should be fixed. (courtesy L. Tavian) Separate cryostats, how to link together? LTS or MgB2?

Conclusions DFBA and existing refrigerator  From the aspect of “cost of cooling” the reference solution with a flexible transfer line can be easily covered by the existing refrigerators.  Uncertainties remain as for the lead performance and concerning the low available pressure difference for the cooling. 17/11/ st HiLumi LHC / LARP 23

Conclusions DFBX, DFBL and new refrigerator  We can establish a budget for the cost of cooling to contribute to the refrigerator specification.  The concept of how to link the stand alone magnets of the matching section (DFBL) to the link should be addressed. 17/11/ st HiLumi LHC / LARP 24