Projectsunder JnNURM Scheme Construction of traffic transit management centres Procurement of buses
Procurement of buses under JnNURM
Procurement of buses under JnNURM Details of Funding – GoI, GoK and BMTC 3 Particulars Total Grants GoI share (35%) GoK share (15%) BMTC share (50%) Purchase of 1000 buses Total No. of buses approved No. of buses received Approve d cost (Rs. in crore) GoI share (35%) (Rs. in crore) GoK share (15%) (Rs. in crore) Released Amount (Rs. in crore) Balance Amount (Rs. in crore) GoIGoKGoIGoK (Amount in Rs.Crores)
Construction of 10 Traffic and Transit Management centers was taken up. 9 out of 10 TTMC’s have been commissioned and 10 th TTMC will be commissioned shortly. Traffic and Transit Management Centres (TTMCs) Under JNNURM Scheme BMTC is the first urban transport organization to get JNNURM funding for a national pilot project for an innovative idea called TTMC
To meet some of the objectives of the national urban transport policy. To Provide an integrated transportation facility with adequate facilities and amenities to cater to the requirements of all user groups. To minimize/ reduce congestion on main road through efficient traffic movement. Smooth flow of all types of traffic to and from the terminal such that there is no congestion/disturbance caused to traffic along the main road. Minimum /no conflict between various traffic types-Passengers, buses and private vehicles and to achieve minimum passenger and vehicle processing time. To encourage use of public transport and provide first-mile connectivity through provision of park and ride facilities in the proposed bus terminal. Concept of TTMC
Facilities at T T M Cs Bus terminal Bus bays Platforms Seating & lighting Public conveniences Information systems Safety and security Bus maintenance depot Maintenance bays, washing platform Bus parking Services and Utilities Fuel filling station Amenities for crew Passenger amenities Bangalore One centers Other citizen amenity centers ATMs Daily needs shopping Park and Ride facilities
Park and Ride Facilities Traffic and Transit Management Centre –First and last mile connectivity –Aim to provide at least 500 4W and 2W parking space –Integrated with main bus terminal building
JNNURM PROJECT FINANCIAL SHARING DETAILS Rs in Lakh
JNNURM PROJECT –Progress Review Sl No Name of TTMC Approved Cost (Rs. in crores) Ampount spent (Rs. In crores) % Achievement Targetted date of completio n Target Action taken 1Shantinagar Jul ITPL Whitefield Jul Koramanagala Jul Kengeri Jul Vijayanagar Jul Banashankari Jul Yeshwanthpura Jul Jayanagara Jun Domlur Jul Bannerughatta Jul-2010 Total
TTMC Jayanagar 4 th Block Project Cost : Rs Crore Date of Commission: