CNGS ISSUES - THAT COULD DISTURB A SMOOTH OPERATION IN 2009 Thanks to colleagues who contributed to the slides: E. Gschwendtner, A. Pardons, H. Vincke,

Slides:



Advertisements
Similar presentations
Accelerator Complex Status P. Collier. Linac2, Booster and PS Startup on-time, according to the schedule. Only minor problems Rapidly set-up the major.
Advertisements

20/01/09 OPERA general meeting Nagoya CNGS report.
Now2008 Paola Sala for the CNGS SBWG CNGS status Paola Sala, INFN Milano on behalf of the CNGS Secondary beam working group.
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 1 I) CNGS status radiation damage on electronics strip line repair II) OPERA issues Based on the work.
1 The CNGS Reflector Water distribution system Outer conductor Inner conductor Drain connections  5 Drain tube Support and alignment frame Transport chassis.
TARGET STATION INFRASTRUCTURE THE CNGS EXPERIENCE D. Autiero, I. Efthymiopoulos, A. Ferrari, E. Gschwendtner, A. Guglielmi, A. Pardons, P. Sala, H. Vincke,
ISS, 23 September 2005E. Gschwendtner, CERN1 Beam Instrumentation at CNGS 1. Introduction 2. Layout 3. Beam Instrumentation 4. Summary.
CNGS Operation Results 2008 Edda Gschwendtner AB/ATB on behalf of the CNGS team.
Performance and Operational Experience of the CNGS Facility Edda GSCHWENDTNER, Dario AUTIERO, Karel CORNELIS, Ilias EFTHYMIOPOULOS, Alfredo FERRARI, Alberto.
The CNGS Operation and Perspectives l Edda Gschwendtner, CERN.
HIRADMAT IN THE WANF TUNNEL I. E FTHYMIOPOULOS, EN/MEF  HIRADMAT-Exp.Area Working Group  EN/MEF : I. Efthymiopoulos, A. Pardons, M.Lazzaroni, N. Gilbert.
CURRENT STATUS OF CV INSTALLATIONS, WORKS DURING LS1 AND PROBLEMS ENCOUNTERED DURING START-UP NORTH AREA Bill Bannister / Jani Lehtinen EATM – 7 th October.
NBI March 2002 The MiniBooNE Horn Ioanis Kourbanis For The MiniBooNE Collaboration.
WIN’11 CERN Neutrinos to Gran Sasso: The CNGS Facility at CERN l Edda Gschwendtner, CERN WIN’11, Cape Town, South Africa, 31 st Jan – 5 th Feb 2011.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
Next generation of ν beams Challenges Ahead I. Efthymiopoulos - CERN LAGUNA Workshp Aussois, France, September 8,2010 what it takes to design and construct.
NuMI NuMI Overview NBI 2002 S. Childress (FNAL) 14 March ‘02 NuMI / MINOS Overview.
NuMI NBI2006 September 6, 2006 NuMI Target Experience Jim Hylen / FNAL Page 1 Experience with the NuMI Target Max. Proton/spill Max. Beam Power Integrated.
NUMI NuMI Internal Review July 12, 2001 Infrastructure: Radiation Safety Page 1 Technical Components NuMI Beamline Radiation Safety Issues Radiation Safety.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
Integration of the Experimental Facility in West Area & CNGS 1Ans Pardons, 18/10/2012 Integration of experimental facility in West Area and CNGS With input.
WP2 Superbeam Work Breakdown Structure Version 2 Chris Densham (after Marco Zito version 1 )
Status and results from OPERA Tomoko Ariga LHEP, University of Bern on behalf of OPERA Swiss groups of Bern and ETHZ.
All Experimenters’ Meeting February 09, Accelerator Operation Summary Calendar Week # 06 NuMI Weekly Integrated Intensity 6.69 E18 protons Beam.
MG - IEFC meeting 22/01/20101 Linac 3 shielding S. Gilardoni, M. Giovannozzi, S. Baird, R. Brown, S. Damjanovic, T. Otto, M. Widorski, Acknowledgements:
General RP guidelines for CENF CENF secondary beam study group H. Vincke07/05/
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
Status of North Area Target (TCC2) & prospects EATM 28/07/2015D. Grenier1 Targets (T2, T4, T6 and T10) replaced in 2014 during LS1 (+ 4 spares) Previous.
PSB dump: proposal of a new design EN – STI technical meeting on Booster dumps Friday 11 May 2012 BE Auditorium Prevessin Alba SARRIÓ MARTÍNEZ.
1 Target Station Design Dan Wilcox High Power Targets Group, Rutherford Appleton Laboratory EuroNu Annual Meeting 2012.
6 April 2006E. Gschwendtner, CERN AB/ATB1 CNGS Project: Secondary Beam 1. Layout 2. Beam Instrumentation 3. Commissioning Plans for the Secondary Beam.
ATC/ABOC days, 24 January 2007Edda Gschwendtner1 CNGS : Status and Outlook Edda Gschwendtner, AB/ATB Summary of CNGS 2006 Reflector Repair OPERA Brick.
 Overview of the run 2009 for CV  Major improvements in Water treatment - Demineralised water production - Cooling control  Major concerns for.
The Stripping Foil Test Stand in the Linac4 Transfer Line
Status of LS1 collimator maintenance O. Aberle – 03/03/14 With input from P. Bestmann, S. De Man and J. Lendaro.
Lau and Niels, NA62 TD meeting, 17 March Complete the crane consolidation in TCC8 Reinstall front-end after alignment checks Consolidation of T10.
Background Simulations for the LHCb Beam Condition Monitor Overview: ● The LHCb Beam Condition Monitor (BCM) – Purpose, Design and Function – Implementation.
All Exp Mtg July 7, 2008 NuMI-MINOS Status Report – Laura Loiacono FAR DETECTOR: FD live time was 95.7% for cosmics last week (ROP7 problems reported at.
First radiological estimates for the HIRADMAT project H. Vincke and N. Conan 1.
Radiation Protection aspects for SHIP Doris Forkel-Wirth, Stefan Roesler, Helmut Vincke, Heinz Vincke CERN Radiation Protection Group 1 st SHIP workshop,
Secondary beam production facility layout discussions SBLNF meeting 5 th Dec M. Calviani, A. Ferrari, R. Losito (EN/STI) H. Vincke (DGS/RP)
7 November 2003 Status of CNGS NBI presented by K. Elsener 1 Status of CNGS Konrad Elsener CERN – Accelerators+Beams Division.
All Experimenters’ Meeting January 26, Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
CNGS Operation Summary Edda Gschwendtner, CERN. Outline Introduction CNGS Performance Highlights since last NBI 2010 in Japan Issues Summary 2E. Gschwendtner,
All Experimenters’ Meeting October 20, 2014 Photo by Greg Vogel.
6 April 2006Malika Meddahi 1 CNGS Project: primary beam 1.Project Overview 2. Proton beam line overview and status 3. Target status 4. Commissioning preparation.
HIGH RADIATION TO MATERIALS: HIRADMAT STATUS HiRadMat Scientific Board, 23/4/2012 Outline  Location  Status  Beam line  Infrastructure  Exp. Area.
EUROnu Costing Workshop May 2011 Beta-Beam Costing Exercise Elena Wildner, CERN 25/05/11 1 EUROnu Costing Workshop, CERN May 2011.
T2K Status Report. The Accelerator Complex a Beamline Performance 3 First T2K run completed January to June x protons accumulated.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
WP2 progress on safety E. Baussan EUROnu CB Meeting Monday 10th & Tuesday 11th June 2011 CERN, Geneva, Switzerland.
ATC-ABOPC Days 2008: Session 1 Summary ATC-ABOC days Summary Session; February Session coordinated by B. Mikulec AB-OP and O. Br ü ning AB-ABP Operation.
NBI2006 Starting OPERA data-taking with the CNGS beam D.Autiero IN2P3/IPN Lyon 5/9/2006.
18, 19, 20 February 2002 Power Converters for magnets (PBS 1.2.3) R. GENAND SL/PO 1 Power Converters for Magnets –Introduction –Specification Magnet characteristics.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
T2K Remote Handling T. Sekiguchi (KEK) on behalf of Tada (KEK) 2012/11/10.
CNGS: First Year of Operation E. Gschwendtner AB/ATB on behalf of the CNGS team.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
SECONDARY BEAM HANDLING AND INFRASTRUCTURE DESIGN STATUS BRUNO FERAL (CERN/EN) DIAMANTO SMARGIANAKI (CERN/EN) Project Leader: I.Efthymiopoulos (Cern/EN)
High Energy Dump of the Super Proton Synchrotron at CERN – Present and Future designs A. Perillo-Marcone (EN-STI) Contributions from several colleagues.
Task # 3 Task # kW Target Station Layout proposal Presented by L.Bruno CERN AB Experimental Areas, Targets and Secondary Beams Group.
CV works in the non- LHC accelerator complex during 2008 and plans for 2009 ATOP days 2009.
CENF SB WG report CENF PTM meeting 25 th July 2013 M. Calviani for the CENF SB team.
Long-Baseline Neutrino Facility LBNF News and brief overview of Beamline plans for the next few months Vaia Papadimitriou Beamline Technical Board Meeting.
SPS High Energy LSS5 Thermal contact & cooling aspects
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
V. Raginel, D. Kleiven, D. Wollmann CERN TE-MPE 2HiRadMat Technical Board - 30 March 2016.
CNGS Run 2007: Radiation Issues
Use of Beam Loss Monitor type detectors in CNGS muon station
Presentation transcript:

CNGS ISSUES - THAT COULD DISTURB A SMOOTH OPERATION IN 2009 Thanks to colleagues who contributed to the slides: E. Gschwendtner, A. Pardons, H. Vincke, S. Girod, D. Autiero, R. Losito ATOP Days CERN March 6, 2009 Outline CNGS run in 2008 – overview 2008 shutdown – major works Horn/reflector cooling system Waste water handling Prospects for the 2009 run I. Efthymiopoulos, EN/MEF

CNGS Run in 2008  Smooth running, excellent performance of the facility  No radiation problems/effects in the electronics  No problems with the major elements of the secondary beam: target, horn/reflector  OPERA Experiment  10’100 on-time events  1’700 candidate interactions in the bricks I.Efthymiopoulos, EN/MEF 2 ATOP Days, March 2009 Performance Average rate Reference sample: Long tracks (>5 TT planes × 20) CNGS on time events

CNGS Run in 2008 I.Efthymiopoulos, EN/MEF 3 Primary beam 48s supercycle : FT + 3 CNGS + LHC + MD  37.5% CNGS duty cycle 50.4s supercycle : 7 CNGS + LHC  83% CNGS duty cycle Integrated efficiency: 60.94% ATOP Days, March 2009

Physics run in 2008 I.Efthymiopoulos, EN/MEF Beam statistics 4 18kV cable repair MD PS magnet exchange, septum bakeout MD SPS timing fault: vacuum leak & magnet exchange CNGS maintenance: Horn water filter exchange, Hadron stop sump emptying SPS extraction line: Magnet ground fault 1.78E19 pot on November 3 rd Integrated protons on CNGS target 1.4E19 4.0E18 8.0E18 6.0E18 1.0E18 2.0E18 18-JuneJuly 2008August 2008September 2008October 2008 MD CNGS maintenance: Horn water filter exchange 1.0E19 1.2E19 1.6E19 November2008 ATOP Days, March 2009

Protons on Target per Day Beam to CNGS, North Area, LHCBeam to CNGS only CNGS duty cycle: 37.5%, 54%37.5%, 43% 37.5%, 45%, 54% 56%-83% 3.5E17 CNGS Facility – Performance 2008 E. Gschwendtner – AB Seminar Nov’08

Target Beam Position Excellent position stability; ~50microns over entire run. No active position feedback is necessary –1-2 small steerings/week only CNGS Facility – Performance 2008 Horizontal beam position on the last BPM in front of the target E. Gschwendtner – AB Seminar Nov’08

Beam Stability seen on Muon Monitors Position stability of muon beam in pit 2 is ~3cm rms Beam position correlated to beam position on target. –Parallel displacement of primary beam on T40 Horizontal centroid pit 2 Vertical centroid pit 2 CNGS Facility – Performance 2008 E. Gschwendtner – AB Seminar Nov’08

8 Muon Monitors Very sensitive to any beam changes ! –Offset of beam vs target at 0.05mm level CNGS Facility – Performance 2008 Muon Profiles Pit 1 Muon Profiles Pit 2  5cm shift of muon profile centroid  ~80  m parallel beam shift  Centroid of horizontal profile pit2 –Offset of target vs horn at 0.1mm level Target table motorized Horn and reflector tables not E. Gschwendtner – AB Seminar Nov’08

CNGS Run in 2008 I.Efthymiopoulos, EN/MEFATOP Days, March  Very interesting experience to stress the facility  duty cycle : up to 83% (1-2 days only), with ~75-80% of designed pulse intensity  Note: CNGS design of equipment and RP considerations for 2×2.4×10 13 protons/6s, 100% duty cycle Target design with ×2 safety for “ultimate” intensity of 2×3.5×10 13 protons/6s, 100% duty cycle Observations: No unexpected temperature rise in horn/reflector and electrical circuit  Several temperature probes (mainly around the target station) died  Expected, due to integrated intensity  Action : nothing to do!  Increased temperature at the first He-tank window Action : not an issue, should be kept in mind for future (upgrades?)  Lifetime of horn/reflector cooling circuit filters Understood, due to integrated intensity but shorter than expected No degradation of horn/reflector itself Action : work during 2008/09 shutdown High-duty cycle operation

10 CNGS duty cycle: 37.5%, 54%37.5%, 43% 37.5%, 45%, 54% 56%-83% Helium Tube Entrance Window Temperature CNGS Facility – Experience of Operating a 500kW Facility E. Gschwendtner – AB Seminar Nov’08

Helium Tube Entrance Window Temperature Measurements –0.3mm thick –0.8m inner diameter –Clamped with seal between flanges shielding horn ionization chamber target TBID collimator BPM beam Helium tube Ti-window Temperature Measurement Clamping bolt Entrance window Seal Titanium Grade (Ti-6Al-4V) –Ultimate stress: >900MPa >870MPa >850MPa From calculations: - When ventilation vs. beam is such that temp. at flange = 66°C:  Window: Temp. <100°C & Stress <250MPa  Safety factor 3 ensured. From temperature measurements during operation (extrapolate): - If temp. measured < 85°C  Window: Temp. <150°C & Stress <300MPa  Safety factor 2.5 ensured. CNGS Facility – Experience of Operating a 500kW Facility Courtesy of A. Pardons

CNGS Run in 2008 I.Efthymiopoulos, EN/MEFATOP Days, March Helium Tube Entrance Window Horn Beam He window

CNGS Run in 2008  TBID detector broke down on July 19, only after 1.2×10 18 pot)  the ionization chambers can be used for setting up  reduced handle to verify target integrity and beam steering I.Efthymiopoulos, EN/MEF 13 TBID Detector TBID signal Ionization Chamber ATOP Days, March 2009 Origin of the problem  Short circuit in the isolation bias of the screens  Could be either in the cable, the connectors, or in the device itself

CNGS Run in 2008 I.Efthymiopoulos, EN/MEFATOP Days, March TBID Detector TBID Target Horn Beam Possibility to repair?  Radiation levels are rather high  ~27mSv/h at floor level  Difficult to remove it due to cables  No spare available  Review again with BE/BI & RP before startup if something can be done, also in view of other operations…

Major shutdown activities  Repair of the ventilation unit in TCV4  Modifications to the horn/reflector cooling system to improve the filter lifetime  Evacuation and handling of the CNGS sumps water  Inspection of target unit CNGS Preparation for 2009 I.Efthymiopoulos, EN/MEF 15 ATOP Days, March 2009

TCV4 Ventilation repair  Leak of chilled water in one of the TCV4 units(1 st floor)  small leak, triggered no alarm, but still ~2.5m3 of water in the floor and on top of equipment  no damages except in one of the cameras  the water became radioactive as it washed the nearby filters of the ventilation unit  Repair ongoing along with standard maintenance of all ventilation units  work next to the filters, had to wait for cool- down I.Efthymiopoulos, EN/MEF 16 Solutions  Difficult to install detection system for such small leaks; small fraction of total water flow in the CNGS area  Install additional cameras to monitor the TCV4 cavern !! ATOP Days, March 2009

Cooling system for the horns  Resin filters are used to maintain a low conductivity level in the circuit  Two reasons: avoid short-circuit inside the horn limit long-term corrosion effects  About 1/3 of the flow goes through the filters  Required level: [0.1,10.0]  S/cm  Two filters in place (active + spare) equipped with quick connectors  Filters get activated – temporarily stored in TSG4 for initial cool-down Main issues:  Filter lifetime before saturation  wished to be one year, but really unknown  2008 run showed they saturate much sooner !!  long access (>20h stop) each time to replace them (10min)  The filters used have plastic pieces (tubes) inside; not a real issue but better to avoid  The filters are radioactive waste, their use must be optimized I.Efthymiopoulos, EN/MEF 17 Filters ATOP Days, March 2009

Cooling system for the horns I.Efthymiopoulos, EN/MEF 18 Filter lifetime - horn Filter exchange Limit for safe operation : 10  S/cm 7.5E18 pot 45 days  This would imply ~6 filter exchanges for a nominal CNGS year (4.5×10 19 pot) ! Water conductivity Integrated pot ATOP Days, March 2009

Cooling system for the horns I.Efthymiopoulos, EN/MEF 19 Filter lifetime - reflector Filter exchange  Filter exchange at 1.15E19 pot  4 filter (4.5×10 19 pot) ! ATOP Days, March 2009

Cooling system for the horns I.Efthymiopoulos, EN/MEF 20  Increase the filter capacity of the system  use 2 × 50(100) lt filters instead of single 40lt today  × 2.5 gain, survive a full nominal year with only one exchange  New optimized filter container design  allow easier manipulation (installation/removal) of the filters  maintain the quick connectors  possibility to empty the resin and re-use the container  less radioactive waste design to be validated by safety and RP Modifications for 2009 ATOP Days, March 2009

Cooling system for the horns I.Efthymiopoulos, EN/MEF 21 Horn/reflector cooling system – modifications shutdown 2009 ATOP Days, March 2009  New chassis to add to existing one  Enough space for 2(3) cartridges of 50(100) lt  Additional metallic filter to capture resin debris in case of an accident

CNGS sumps I.Efthymiopoulos, EN/MEF 22 Layout ATOP Days, March 2009

CNGS water handling 1.Sumps TNM41 – TNM42  infiltrations along the decay tube (1-1.5lt/h) – nothing can be easily done to reduce it  Requires access to TI8 line – foreseen during the injector MD periods 2.Sumps in TSG4  water inflow from condensation in the ventilation system : 1 evacuation during operation, ~4 during shutdown 3. Horn/reflector cooling water  2× 600 lt ; highly radioactive (up to 80 MBq/lt)  Yearly exchange 4. Hadron stop cooling water  ~2000 lt, highly radioactive I.Efthymiopoulos, EN/MEF 23 ATOP Days, March 2009 Summary

CNGS water handling I.Efthymiopoulos, EN/MEF 24  Evacuate the water from the different areas  Special equipment for TI8/hadron stop available Can pass under the vacuum pipe in TI8 tunnel  Transfer the water in special containers for storage  Accumulate the water for one operational year  Elimination path(s)  Via CEA Marcoule A complete chemical analysis needs to be done each time before they can accept the water  Evaporator NUMI uses a such a system for their tritiated alkaline water can treat 85gallons(320lt)/day of 90’000pCi/ml (3.4MBq/lt) H3 contained water of PH  Discussions ongoing in a working group with A&T safety and RP colleagues Plan for 2009 ATOP Days, March 2009

CNGS water handling I.Efthymiopoulos, EN/MEF 25 Transient water storage in BA4  Retention bag connected to L3 alarm  Foreseen space for 18 containers (18m 3 )  Isolation against freezing if needed (cost an issue) ATOP Days, March 2009

TARGET inspection I.Efthymiopoulos, EN/MEF 26  During the standard maintenance, a problem appeared in the motorization for the target rotation  From investigations so far it seems the torque needed to turn the target unit exceeds the capacity of the motor and the torque limiter  Proposed plan:  Open the target shielding to view the status of the target unit with the crane camera  Install a test stand upstream in TCC4 and bring the target unit for further observations with cameras and if possible prepare tooling to do rotation tests.  The EN/STI experts are already working on the spare unit to optimize the manipulations in CNGS  More news in the coming weeks… ATOP Days, March 2009

TARGET inspection I.Efthymiopoulos, EN/MEF 27 ATOP Days, March 2009  CNGS target magazine during assembly

TARGET inspection I.Efthymiopoulos, EN/MEF 28 TCC4 inspection – outside the shielding ATOP Days, March 2009  Signs of rust are observed in parts of the motorizations and limit switches  Could be the origin of the torque increase  To be investigated once the target is out from its shielding.

TARGET inspection I.Efthymiopoulos, EN/MEF 29 Target magazine inspection in TCC4  Work in the area to be defined and discussed in collaboration with SC/RP  Lab tests with the spare unit would allow to optimize the time needed in agreement with the ALARA principle Target magazine in its transport chassis Camera locations ATOP Days, March 2009 Pb screens

CNGS Preparation for 2009 I.Efthymiopoulos, EN/MEF 30  Floor rectification for the traveling of the PPP-TSG41 plug  Make new solid flat surface for the big plug to roll  Consolidation/preventive maintenance of horn/reflector power supplies  Small consolidation project for 2009/2010  preventive maintenance to replace thyristor capacitance charges  cross-check all bus-bars connections and screws to avoid similar incident as last year  Improvements in the irradiation test installation – CNRAD test area  Complete installation of all four stations, correct powering problems  Support stands for irradiation samples (not laying everything on the floor)  Complete RADMON installation and define reference positions  Finalize access and material handling procedures … and  Standard maintenance of various systems 2008/2009 Shutdown activities ATOP Days, March 2009

LNGS News I.Efthymiopoulos, EN/MEF 31  OPERA is advancing with the analysis of the 2008 data  They accumulated in 2008 about on time events, mostly interaction in the rock, among which 1700 neutrino interactions in the bricks  They aim in completing the analysis of 2008 data by the start of 2009 run  OPERA looks forward to a smooth run in 2009 with integrated intensity as close as possible to the nominal value of pot   They transmit their thanks to all the accelerator teams for their continuing efforts to support the beam line and the LNGS physics ATOP Days, March 2009

OPERA Event Gallery I.Efthymiopoulos, EN/MEFATOP Days, March  Charm mesons produced in um interactions  2.1 expected charm events during  Seen: 2 charm-like topologies Event analysis - preliminary

CNGS – prospects for Beam to CNGS, LHC, FT, MD Beam to CNGS, LHC, FT Beam to CNGS, MD 2009 : 175 days with beam  2.80×10 19 pot for 2.0×10 13 prot/extr  3.36×10 19 pot for2.4×10 13 prot/extr (MTE)  3.70×10 19 pot with 2.0×10 13 prot/extr  4.44×10 19 pot with 2.4×10 13 prot/extr (MTE)  4.80×10 19 pot with 2.0×10 13 prot/extr  5.76×10 19 pot with 2.0×10 13 prot/extr (MTE) I.Efthymiopoulos, EN/MEFATOP Days, March 2009

 2008 was a very good year for CNGS  Many thanks to those who worked hard during last year’s shutdown,  and the operations teams for providing the beam to the facility and the experiments  2009 shutdown work is advancing well, getting ready for the startup  but still some last minute surprises like with the target  Looking forward for a smooth and efficient run in 2009 Summary I.Efthymiopoulos, EN/MEF 34 ATOP Days, March 2009