October 13, 2006 Global Design Effort 1 International Linear Collider Machine Detector Interface Materials for discussion at Engineering Forum: experiences.

Slides:



Advertisements
Similar presentations
SiD Surface assembly Marco Oriunno (SLAC) MDI-CFS Meeting Sep. 4-6, 2014, Ichinoseki (Japan)
Advertisements

Question from the GDE : Could local “doughnut” type muon spoilers like those in SLC be substituted for the 5 meter magnetized wall? 5m magnetized wall.
Assembly Hall in Hybrid-A’ and ILD 2014/9/6 Yasuhiro Sugimoto 1.
Global Design Effort Goals and Introduction Andrei Seryi, SLAC, September 17, 2007.
Large Platforms For Push-pull Hitoshi Yamamoto 18-Sep-2007 IRENG07.
1 IR Hall for GLD Oct Y. Sugimoto KEK. 2 Underground hall HybridPure CMS IR hall area (WxL)25x55 Beam height8.6 Crane max hook height20.5 Largest.
Summary of wg2a (BDS and IR) Deepa Angal-Kalinin, Shigeru Kuroda, Andrei Seryi October 21, 2005.
Global Design Effort Detector concept # Plenary introductory talk IRENG07 Name September 17, 2007.
8-Nov-06 GDE Valencia Global Design Effort 1 MDI Related Potential Design Changes Barry Barish Caltech / GDE 8-Nov-06.
Beam Delivery, MDI related updates Andrei Seryi for BDS Area GDE/LCWS meeting at Bangalore March 10, 2006.
DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1.
Experimental hall in Japanese mountain site Y. Sugimoto ILD MDI/Integration 1.
Global Design Effort Detector concept Plenary introductory talk IRENG07 Kurt Krempetz September 17, 2007.
September 21 - November 6, 2006 Global Design Effort 1 Technical evaluation of push-pull September 21 - November 6, 2006 Draft to be presented by A.Seryi.
Status of ILC Barry Barish Caltech / GDE 17-Aug-07.
November 07, 2006 Global Design Effort 1 Beam Delivery System updates BDS Area leaders Deepa Angal-Kalinin, Hitoshi Yamamoto, Andrei Seryi Valencia GDE.
3 March 2009M. Breidenbach1 SiD LoI Costs M. Breidenbach.
1 GLD Surface Assembly Y. Sugimoto KEK
1 Alternative assembly option of ILD Y.Sugimoto 2010/10/18 ILD Integration
Experimental hall in Japanese mountain site Y. Sugimoto 1.
Global Design Effort Push-pull studies How to proceed LCWS07 June 1, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi.
1. Civil Engineering works for Linear Colliders* : -Brief introduction on the overall machine layout (just for CLIC at this stage) -Experimental Area.
Global Design Effort BDS updates SLAC 1:30 Monday meeting Andrei Seryi November 5, 2007 Previous update – August 20, 2007.
February 4, 2007 Global Design Effort 1. February 4, 07 Global Design Effort IR&MDI: 2 Contents Will describe design of Beam Delivery System, focusing.
ILC MDI Andrei Seryi JAI with input from many colleagues working on MDI IWLC
Global Design Effort Beam Delivery System => EDR LCWS07 June 2, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi Yamamoto.
Beam Commissioning Marco Oriunno (SLAC), May 14, 2014 ALCW 2014, Fermilab Engineering Issues.
Thanks to Andrei for slides October 26, 一般報告 Hitoshi Yamamoto, Oct 26, 2006.
Philip Burrows SiD Meeting, Paris 11/02/081 Machine Detector Interface Issues Philip Burrows John Adams Institute Oxford University Thanks to: Tom Markiewicz.
MEA Machine and Experiment Assembly 1 Norbert Meyners, MEA Engineering Forum at CERN 12.Okt Thoughts about LDC Hall and Assembly (Work is not finished.
Si D in 14mrad/14mrad/z=0 ILC T. Markiewicz/SLAC SiD Advisory Group 14 August 2006.
MSL - SLAC11 Radiation Protection studies for SiD Mario Santana, SLAC / RP 2010 Linear Collider Workshop & International Linear Collider Meeting Tsinghua.
27 Nov 07 VM Workshop Global Design Effort 1 ILC – Superconducting Linear Collider Marc Ross, Project Manager GDE Fermilab.
Global Design Effort Critical Interaction Region Issues, Report from the IR engineering workshop Andrei Seryi, SLAC October 24, 2007.
The ILC IR John Amann ILC Mechanical Engineering 09/12/06.
1 BDS and Detector schedules for discussion at MDI meeting August 15, 2006 Andrei Seryi with input from Martin Gastal, Yasuhiro Sugimoto et al.
A. Hervé - 17 Oct CLIC-Workshop CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN.
1 Target Station Design for Neutrino Superbeams Dan Wilcox High Power Targets Group, Rutherford Appleton Laboratory NBI 2012, CERN.
ILD requirement for assembly space and time 2015/11/3 Yasuhiro 1.
November 07, 2006 Global Design Effort 1 Beam Delivery System / Machine Detector Interface BDS Area leaders Deepa Angal-Kalinin, Hitoshi Yamamoto, Andrei.
Experimental Areas Studies Lessons learnt at CMS M Gastal & CMS Technical Coordination (A Ball, W Zeuner)
ILC D RAFT P ROJECT S CHEDULE K LYCLUSTER 500GeV K Foraz & M Gastal ILC Mechanical & Electrical Review and CFS Baseline Technical Review Many thanks to.
Philip Burrows SiD Meeting, SLAC 27/10/06 Machine Detector Interface Issues Philip Burrows John Adams Institute Oxford University.
Global Design Effort CLIC-ILC BDS & MDI work Materials for discussion Daniel Schulte, Rogelio Tomas and Emmanuel Tsesmelis for CLIC team Andrei Seryi for.
Global Design Effort Working Group C Conventional Facilities Parallel Session IRENG07 V. Kuchler, A. Enomoto, J. Osborne September 19, 2007.
11/15/20051 Radiation Protection Issues for ILC (not exhaustive) A. Fassò, N. Noriaki, H. Vincke Radiation Physics.
GLD experimental hall and detector assembly Y.Sugimoto KEK 27 Sep
Assembly scenario of ILD Si trackers 2015/4/21 Yasuhiro 1.
Philip Burrows MDI Panel Meeting 15/08/06 Philip Burrows John Adams Institute Oxford University SiD and IR/MDI Issues.
ILD and SiD in Japanese site (from discussions in SiD/ILD E/D Interface Working Meeting) Yasuhiro Sugimoto, Marco Oriunno 2011/12/15 SiD
Experimental hall in Japanese mountain site 2011/11/30 Yasuhiro CFS Webex meeting 1.
MEA Machine and Experiment Assembly Norbert Meyners, MEA 12. July 2007ILC IRENG07 WG-A1 LDC Engineering Design (Status) Introduction General Design Detector.
Implication of gamma-gamma on 14mr tunnels discussion (questions for discussion with WG-C and WG-A) Valery Telnov Budker INP IRENG07, Sept.19, 2007, SLAC.
An idea of ILD general assembly plan 2015/10/8 Yasuhiro Integration Meeting 1.
1 Update of detector hall in mountain regions Y.Sugimoto in Granada.
Experimental Hall in Mountain Regions
CLIC Civil Engineering Update
Detector Utility/Service Cavern
Yasuhiro Sugimoto 2012/2/1 ILD integration meeting
Experimental hall design in Japanese site
ILC Interaction Region and Machine Detector Interface
Update of experimental hall in Japanese mountain site
Detector Service Cavern for ILC
Design Concept Update – Platform Moved on Hillman Rollers
SiD LoI Costs M. Breidenbach 29 July 2010 M. Breidenbach.
Radiation Physics requirements for the IR
Detector hall in mountain regions
Extract from today’s talk given to DCB
RDR Baseline Layouts for Interaction Region
Fassò, N. Nakao, H. Vincke Aug. 2, 2005
Presentation transcript:

October 13, 2006 Global Design Effort 1 International Linear Collider Machine Detector Interface Materials for discussion at Engineering Forum: experiences from LHC detectors conception and construction CERN, October 13 Andrei Seryi, Hitoshi Yamamoto

Oct 13, 06 Global Design Effort ILC-MDI: 2 Thanks To many colleagues from CERN and other labs who were involved in discussion and work on the issues described in this talk To everyone who organized this meeting, who were guiding the tour, and who are participating in this meeting

Oct 13, 06 Global Design Effort ILC-MDI: 3 Contents Introduction, ILC and BDS layouts Detector assembly, hall sizes, arrangements, etc –Adopted on-surface assembly concept for ILC –Consider pure CMS or modified CMS assembly Questions associated with study of push-pull –Detector design and radiation shielding –Moving detector parts –Location of services and electronics, etc Goal of this meeting: learn CERN experience and consider how to best apply it to ILC

Oct 13, 06 Global Design Effort ILC-MDI: 4 ILC layout This shows central location of DR which is not yet officially accepted

Oct 13, 06 Global Design Effort ILC-MDI: 5 Beam Delivery System layout IP2 IP1 10m 1km beam dump service hall alcoves 9m shaft for BDS access polarimeter laser borehole muon wall tunnel widening

Oct 13, 06 Global Design Effort ILC-MDI: 6 beam dump service hall alcoves 9m shaft for BDS access & service hall beam dump and its shield muon wall tunnel widening Beam Delivery System tunnels

Oct 13, 06 Global Design Effort ILC-MDI: 7 Couple of particular features It is worth to attract attention and discuss couple of particular assumptions: –Do not include (unlike LHC) a separate service cavern for detector equipment and electronics. All what is needed is placed in the collider hall. –Do not have access shafts than those 2 in IR hall, and these shafts are equipped with elevators and stairs: (The nearest shafts for machine assess are ~600m from IP) Picture shows a solenoid being lowered down in an IR hall shaft

Oct 13, 06 Global Design Effort ILC-MDI: 8 On-surface (a la CMS) assembly Schedules of ILC CFS work developed by Martin Gastal and his colleagues –According to tentative CF&S schedule, the detector hall is ready for detector assembly after 4y11m after project start –If so, cannot fit into the goal of “7years until first beam” and “8years until physics run” Surface assembly allows to save years and allows to fit into this goal –The collider hall size may be smaller in this case –A building on surface is needed, but savings may be still substantial Adopted on-surface assembly for ILC

Oct 13, 06 Global Design Effort ILC-MDI: 9

Oct 13, 06 Global Design Effort ILC-MDI: 10 On-surface detector assembly Underground detector assembly VERY TENTATIVE start date is arbitrary

Oct 13, 06 Global Design Effort ILC-MDI: 11 Versions of on-surface assembly Accepted on-surface assembly Still, discuss variations –pure CMS assembly (config B) –modified CMS assembly (config A) Assemble smaller (than CMS) pieces on surface, lower down and perform final assembly underground May affect schedule (?), but preliminary looks by a small bit less expensive than “B” Details of assumptions shown on next pages –would like to clarify our understanding and perhaps refine the ILC assumptions during this visit to CERN

Oct 13, 06 Global Design Effort ILC-MDI: 12 Table if IR assumptions continued at next page=>

Oct 13, 06 Global Design Effort ILC-MDI: 13

Oct 13, 06 Global Design Effort ILC-MDI: 14 Single IR questions GDE is studying a design with single IR and two detector (“push-pull” case) Questions associated with study of push-pull –Detector design and assembly –Radiation shielding –Moving detector parts and shielding –Location of services and electronics, etc Detailed list of questions here: Some tentative conclusions are below

Oct 13, 06 Global Design Effort ILC-MDI: 15 Example of questions What is the suitable way to move (rails, air-pads) the detector? –air-pads seems as a possibility For quick change-over, do we need to make detector self shielding? –It would help, but self-shielding is not absolutely required for quick change-over What are the design changes needed to make the detector self shielded? –For GLD, self-shielding has been shown in simulations. For the fourth detector concept (double solenoid with no iron), implementing self- shielding may be difficult If there is a need in shielding wall between detectors, what is the method of its removal and assembly? –The shielding wall, if needed, can consist of two parts and move on air- pads in hours What arrangements or reinforcements (such as imbedded steel) are needed for the floor of the collider hall? –Steel plates (~5cm thick, welded) to cover the collider hall floor How the connections of electrical, cryo, water, gas, etc, systems are arranged? –Part of electronics and services can be placed on a platform which moves with detector. Flexible connections to stationary systems needed.

Oct 13, 06 Global Design Effort ILC-MDI: 16 accessible during run (radiation worker) accessible during run (general personnel) not accessible during run fence Platform for electronic and services (~10*8*8m). Shielded (~0.5m of concrete) from five sides. Moves with detector. Also provide vibration isolation. Concept which does not rely on self-shielding detector

Oct 13, 06 Global Design Effort ILC-MDI: 17 Detector assembly and its radiation safety properties Although not required, eliminating the shielding wall would facilitate the push-pull case –In this case, If the off-beamline detector is to be accessible, the detectors should be self-shielded Preliminary study indicate that most of ILC detectors can be made self-shielded even for pessimistic assumption of full beam loss (18MW) Question is: are there any particular constraints, due to on-surface assembly, which complicates design of self-shielded detector?

Oct 13, 06 Global Design Effort ILC-MDI: 18 Results show that GLD can be self-shielded even if assume criteria of 25rem/h (250mSv/h) for maximum credible incident [SLAC rule] at any place (=loss of 18MW beam at thick target) Shield around beamline was not included Self-shielding study of GLD

Oct 13, 06 Global Design Effort ILC-MDI: 19 Yasuhiro Sugimoto GLD modified to improve self-shielding

Oct 13, 06 Global Design Effort ILC-MDI: 20 The 4 th detector concept Magnetic field lines of the 4th Concept, showing the dual solenoids and the “wall of coils” on the ends. A cut-away view of the dual solenoids and the “wall of coils” that terminate the solenoid field in the 4 th Concept. Featuring the dual solenoids and no need for the iron return yoke The calorimeter, solenoids and supporting structures give some shielding but certainly not sufficient self-shielding If it were to be made self-shielding, ~2-3m of concrete would need to be added around the detector. Or has to rely on external shielding wall

Oct 13, 06 Global Design Effort ILC-MDI: 21 IR hall with shielding wall No shield around beam With shield around beam May need additional curtain wall on top of main wall. May need shaft cover. Do not need full height wall. The height could be decrease from what shown.

Oct 13, 06 Global Design Effort ILC-MDI: 22 A.S: Is it possible to avoid the gaps between slices, in particular for cables, or at least avoid direct view to the beam through the gaps? A.Herve: Minimum gaps are needed for cables and gas/cooling pipes. But gap do not point on IP Surface assembly & self shielding

Oct 13, 06 Global Design Effort ILC-MDI: 23 A.S. Q: Is it possible to arrange layers of irons in such a way that the direct view to the beam through the gaps would be avoided? As is, with gapsModified A.Herve: For CMS, to see the beam pipe is not a problem for the gap is behind the calorimeter. Field map would be affected and more complicated. Closure of the detector would be more complex. 3D interface instead of 2d IP A.S. Q: For total self shielding we probably has to assume that the beam loss can happen not only at IP, but at any place?

Oct 13, 06 Global Design Effort ILC-MDI: 24 Summary Looking forward to discuss the issues of detector assembly, radiation safety design, IR hall arrangements, etc.

Oct 13, 06 Global Design Effort ILC-MDI: 25 Backup slides

Oct 13, 06 Global Design Effort ILC-MDI: 26 Self-shielding study color scale is different in two cases 18MW on Cu target 9r.l at s=-8m Pacman 0.5m iron and 2m concrete 18MW on Cu target 9r.l at s=-8m Pacman 1.2m iron and 2.5m concrete 18MW at s=-8m: Packman dose at pacman external wall dose at r=7m Fe: 0.5m, Concrete:2m 120rem/hr (r=3.5m) 23rem/hr Fe: 1.2m, Concrete: 2.5m 0.65rem/hr (r=4.7m) 0.23rem/hr A proper beamline shielding can reduce the dose below 25rem/hr Desired thickness is in between of these two cases Alberto Fasso et al

Oct 13, 06 Global Design Effort ILC-MDI: 27 If detector does not provide any radiation protection: For 36MW maximum credible incident, the concrete wall at 10m from beamline should be ~3.1m Wall 18MW loss on Cu target 9r.l \at s=-8m. No Pacman, no detector. Concrete wall at 10m. Dose rate in mrem/hr. 25 rem/hr 10m Alberto Fasso et al