1 Portfolio Committees on Correctional Services and Public Works Kimberley Correctional Centre 18 August 2010.

Slides:



Advertisements
Similar presentations
Fleurieu Regional Aquatic Centre Project summary October 2013 council meetings.
Advertisements

Open Procurement Process Gauteng Provincial Treasury Process Mapping 30 th October 2014.
John Boon ZUT November Procurement Systems The organisation of the interaction between the purchaser of a new building and the suppliers of goods.
PRESENTATION TO THE SELECT COMMITTEE ON APPROPRIATION 19 OCTOBER 2010.
DEPARTMENT OF COOPERATIVE GOVERNANCE AND TRADITIONAL AFFAIRS PRESENTATION TO THE PORTFOLIO COMMITTEE Municipal Infrastructure Grant (MIG) Projects and.
North West Department of Education Presentation to the Select Committee on Appropriation Parliament of the Republic of South Africa Wednesday 21 April.
Process Engineer’s Role in Project Management Dr Abdullah Malik.
Performance of Contractor Agreements: Practical Issues Kyiv, September 2012 Kristina ARTEMENKO EU Project "Harmonisation of Competition and Public Procurement.
Briefing to the Portfolio Committee on Police, National Assembly PROPERTIES OCCUPIED BY ICD V227, Second Floor, Old Assembly Building Parliament, Cape.
PRESENTATION TO THE PORTFOLIO COMMITTEE ON CORRECTIONAL SERVICES ON CERES, VANRHYNSDORP AND BRANDVLEI CORRECTIONAL CENTRE'S 22 FEBRUARY 2012.
Constructing West Midlands Martin Merrix Divisional Manager, Urban Design.
Audit of Public Procurement
ANALYSIS OF THE NCERA FARMS INVESTIGATION REPORT AND RECOMMENDATIONS TO THE PORTFOLIO COMMITTEE 1.PURPOSE T O INFORM THE PORTFOLIO COMMITTEE ON THE STEPS.
S10 CONS5Q25 Lara Tookey. Review of estimators workings Decision on what margin to apply Bid submission details Submit your Tender.
Practical Problems Experienced with Industrial DSM Projects Marius Kleingeld 15 August 2012.
1 1 DOJ & CD Briefing to the Select Committee on Security and Constitutional Affairs 13 October 2009.
YOUNG PROFESSIONALS SEMINAR CIVIL ENGINEERING CHALLENGES Venue: CSIR International Convention Centre Gauteng Date: 22 November 2013 Presenter: Vikash.
Specification & Quantities Estimating
1 Mpho Mathabathe: Researcher Portfolio Committee on Correctional Services Analysis of DCS Annual Report (2011/12)
Financial Reporting (Overview & EFIS Users). 2 General Reporting Requirements  Reporting requirements are outlined in the 2011/12 Child Care Business.
1 DPW Presentation to the Portfolio Committees on Correctional Services and Public Works Kimberley Correctional Centre 24 November 2010.
Report on the Challenges in the Planning and Procurement of Services for the Ceres and van Rhynsdorp Correctional Facilities Portfolio Committee on Correctional.
ARC 807: Professional Practice and Procedure Department of Architecture, Federal University of Technology, Akure, Nigeria ARC 807: Professional Practice.
FEEDBACK TO PORTFOLIO COMMITTEE: 24 NOVEMBER 2010.
DEPARTMENT OF LABOUR Expenditure – 30 JUNE MAIN DIVISIONS OF THE VOTE.
Marketing & Tendering. Budget Forecasting Profit is the key to Business Success – Profit is amount of money after all expenses Materials Labour Insurances.
DEPARTMENT OF HEALTH HEALTH PORTFOLIO COMMITTEE BRIEFING: HOSPITAL REVITALISATION PROGRAM Infrastructure Management 5 September 2012.
Presentation to the Portfolio Committee on Sport and Recreation – funding of 2010 stadia Presented by: Mike Marsden, Executive Director: Service Delivery.
Presentation to Portfolio Committee on Police on SAPS Communication Projects By: Mr Sithembiso Freeman Nomvalo
1 Public hearing on conditional grants and capital expenditure: 3rd quarter Presentation to Select Committee on Finance Northern Cape’s Department of Agriculture.
Department of Correctional PRESENTATION ON THE DEVELOPMENT OF THE “NEW GENERATION” CORRECTIONAL FACILITY PROTOTYPES DEPARTMENT OF CORRECTIONAL SERVICES.
MASIBAMBANE CO-ORDINATING COMMITTEE MEETING PROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP) 22 nd JUNE 2012 MASIBAMBANE CO-ORDINATING.
Standing Committee on Appropriations Quarter 4 Expenditure 2012/ June 2013 The Presidency Department of Performance Monitoring and Evaluation.
Department of Correctional Services NEW GENERATION CORRECTIONAL CENTRES BRIEFIENG SYNOPSIS DEPARTMENT OF CORRECTIONAL SERVICES.
PORTFOLIO COMMITTEE on HEALTH
1 PRESENTATION TO THE PORTFOLIO COMMITTEE ON THE OVERVIEW OF THE NDPW PRESENTED BY THE TOP MANAGEMENT COMMITTEE 26 MAY 2004.
Themba Wakashe Director - General Department of Arts and Culture 2009 / 10 DIVISION OF REVENUE BILL PRESENTATION TO SELECT COMMITTEE ON FINANCE NCOP 3.
Briefing to the Portfolio Committee on the Comparison on Procurement Methodologies 6 June 2006.
1 CONTRACTING. 2 WHAT IS CONTRACTING ? CONTRACTING IS BASICALLY AN AGREEMENT BETWEEN TWO PARTIES, ONE CALLED THE CONTRACTING PARTY AND THE OTHER THE CONTRACTED.
DEPARTMENT OF EDUCATION EDUCATION INFRASTRUCTURE PROGRAMME OF ACTION Portfolio Committee Presentation Cape Town 15 February 2005.
Presentation to Portfolio Committee Progress on the Departmental Under-Expenditure and Recovery Plans -Mr. T. Zulu Director-General 1.
11 PUBLIC HEARINGS ON CONDITIONAL GRANTS AND CAPITAL EXPENDITURE 2008/2009 PARLIAMENT 27 AUGUST 2008.
DPW PRESENTATION TO PORTFOLIO COMMITTEE ON CORRECTIONAL SERVICES 09 FEBRUARY 2010.
Joint Report to Select Committee on Appropriations by Northern Cape Department of Health Northern Cape Department of Roads & Public Works supported by.
1 Mpho Mathabathe: Researcher Portfolio Committee on Correctional Services Analysis of SONA (2012)
Parliamentary submission on the eradication of the Bucket Toilet System 22 & 23 February 2007 Cllr. Derrick Ndlovu.
1 Hospital Revitalization Grant Performance Report: Free State.
Preparation of the Self-Study and Documentation
OVERVIEW OF DEPARTMENT OF ARTS AND CULTURE SERVICES INFRASTRUCTURE PORTFOLIO DATE: 06 SEPTEMBER 2016.
Standing Committee on Appropriations Quarter 3 Expenditure 2012/2013
E305, 3rd Floor New Wing, Parliament
Systems Analysis and Design in a Changing World, 4th Edition
DCS PORTFOLIO COMMITTEE PRESENTATION NEW CORRECTIONAL CENTRES
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
Bond and Override Report
PUBLIC PROCUREMENT SYSTEM IN UZBEKISTAN
PRE-BID MEETING ITB UNDP Design and Construction of a new medical warehouse in Bissau, Guinea Bissau 15th August 2017 Presented by Antoine Fadoul UNDP-
GRANT – RECAPITALIZATION OF LIBRARY SERVICES SEPTEMBER 2009
PROGRESS REPORT ON THE SABC
Adjustments Appropriation Bill Portfolio Committee on Finance
FIRST QUARTER ANALYSIS REPORT
Pre-contract Planning and Practice
Provincial Treasury Western Cape NCOP Select Committee on Finance Public Hearings Conditional Grant and CAPEX 4 February 2008.
SELECT COMMITTEE ON APPROPRIATIONS 11 August 2010
ADD NAME/TITLE HERE Rural Household Infrastructure Programme Presentation to: Human Settlements Portfolio Committee by Chief Director: Ms Tamie Mpotulo.
PRESENTATION ON THE FINANCIAL MANAGEMENT INFORMATION 3rd QUARTER IRO 2007/ FEBRUARY 2008.
SELECT COMMITTEE ON FINANCE PUBLIC HEARINGS ON CONDITIONAL GRANT
MPUMALANGA 4TH QUARTER EIG PERFOMANCE
HOME AFFAIRS IDENTIFICATION SYSTEM (hanis)
TOTAL COST CONTROL ON CONSTRUCTION PROJECTS
Presentation transcript:

1 Portfolio Committees on Correctional Services and Public Works Kimberley Correctional Centre 18 August 2010

2 CONTENTS 1.Project Tender History 2.Form of Contract 3.Project Cost Analysis 4.Time Frames 5.Achievements 6.Challenges (Risks)

3 PROJECT TENDER HISTORY September 2004 –Preliminary estimate (R 287, 8 million) Desk top estimate based on high level needs assessments received from User Department; Estimate based on concept/blueprint (at this stage design, documentation, Bills of Quantities not started) Estimate excluded site-specific elements such as bulk earthworks, foundations including surface beds, external works (all site works, soil- and storm water drainage, water supply), municipal expenses (traffic lights, storm water connection, etc), on-going changes to security installation and professional fees; This estimate only takes into consideration building costs (provision not made for CPAP and unforeseen expenditure); Provision in estimate not made to unknown details w.r.t. specialised security installations and equipment. March 2005 –Pre-tender estimate (R 540 million) The first estimate based on a complete set of documents and information April 2005 (1 st invitation of tenders) –Tenders closed on 20 April 2005.

4 PROJECT TENDER HISTORY (CONTINUE) May 2005 –Tender recommended – R499,4 million; –Following Departmental processes DCS was requested to confirm availability of funds to award bid; –Confirmation of funds not received; tender could therefore not be awarded; –DCS commissioned an investigation into tender prices received in relation to the pre-tender estimate; –Outcome of investigation not provided; in mean time tender validity lapsed; –Instruction received from DCS to re-invite tenders. July 2006 (Fourteen Months after closing of first bid) –Revised pre-tender estimate R 638,2 million. July 2006 (2 nd invitation of tenders) –Tenders closed for a second time on 19 July 2006; –Tender recommended – R662,3 million –Funding approval was received from User Department to proceed with awarding of bids. November 2006 –Bid awarded to GRINAKER-LTA / KEREN KULA JV on 14 November 2006.

PROJECT COST ANALYSIS

8 –The project was financed from the DCS Capital Works budget. –Tender awarded: R (November 2006) –Funds spent on construction as at 30 July 2010: R –Final construction cost: R (Draft Final Account) –Contract instructions due to essential scope changes and requests: R

10 FORM OF CONTRACT JBCC (The Joint Building Construction Committee) contract used on this project. –Main features of the contract:-  Contractor provides construction program and cash flow.  Contractor is entitled to extension of time under certain circumstances such as: –Rain (Vis-Major)– extension without cost –Extra work – extension with cost –Delays caused by the client - extension with cost –Delays caused by the contractor – no extension  Contractor entitled to escalation [Base month: July 2006] (Haylett Formula with BER indices generally known as CPAP)  Contractual clause to compensated contractor for inflation  Based on Haylett Formula  Indices provided by Stats SA per workgroup  Contract divided into workgroups e.g. earthworks, concrete, metalwork (approx. 32 workgroups)  CPAP calculated per workgroup (lnflation differs per workgroup)

11 FORM OF CONTRACT (Special Requirements of the Contract) Defects liability period:  6 months on building construction work.  12 months on security equipment, electrical and mechanical equipment. Contract Participation Goal (value of work to be subcontracted to HDI subcontractor companies) - 29,79%. Local procurement of material.

12 TIME FRAMES Contract commencement date: 14 th Nov 2006 Contractual completion date: 14 Nov 2008 Actual Practical completion date: 30 October 2009 DCS occupation of facility: Early December 2009 Works completion date: 15 February 2010 Final inspections of “retention defects”: In process Extension of time awarded in terms of JBCC (11 Months & 2 weeks)  Rain (Vis-Major)  Unavailability of municipal services  Shortage of material  Additional work requested by DCS  Discrepancies in procurement documentation  Delay in approval of funds for additions requested by DCS

13 ACHIEVEMENTS Job Creation  1168 Work opportunities created for local unemployed.  Ex-offenders (137) and woman (96) on site Skills Development/ Transfer  86 of the 100 NYS students successfully completed program. Empowerment of Emerging Contractors (subcontracts)  14 HDI subcontractors appointed Saving of R as a result of re- measuring of work done

14 CHALLENGES (RISKS) Unavoidable Risks Excessive inclement weather. Country wide steel shortages (steel price escalate with +/- 60%). Country wide power shortage / load shedding. Shortage of qualified artisans. Price escalation determined by BER indices.

Questions posed during oversight visit Why, despite the delays in construction, the centre has to date still not been completed? –Practical completion was taken on 30 October 2009 –Works completion was taken on 28 April A breakdown of the total cost of the project as well as reasons for the reported escalation; –Breakdown was provided in the presentation. A comprehensive list of all construction still in progress; –All construction has been completed.

Questions posed during oversight visit Copies of the IT procurement contracts; –N/A A list of all the suppliers/service providers responsible for the substandard infrastructure reported; –Suppliers/service providers appointed by DPW were not responsible for substandard work Plans for the installation of toilets in all the hospital wards; –Generic design did not make allowance for toilets in the hospital wards – discussions in process between two Departments to address this requirement

Questions posed during oversight visit The centre’s maintenance plan; –DPW in process to compile facilities contract/s. How inmates were selected/screened for incarceration at the centre; –N/A Update on the investigation into the 3 August incident and the events that had led to the riot; –N/A Measures to be put in place to prevent re-occurrence of the riot; –N/A Measures put in place to address gang-activity at the centre; –N/A

18 Thank You