Injection test1 Injection test in 2006 The installation schedule version 1.7 recently approved includes a ‘possible injection test’ - foreseen in April.

Slides:



Advertisements
Similar presentations
IEFC Workshop – 22/03/2011 JJ Gras on behalf of BE-BI 1.
Advertisements

Requirements Specification and Management
K. Potter RADWG & RADMON Workshop 1 Dec WELCOME TO THE 4th RADWG & RADMON WORKSHOP 1 December 2004.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
Injection test? Mike Lamont For initial discussion.
Machine Detector Interface for the HL (MDI) CERN, April 15, 2011 Austin Ball, Helmut Burkhardt, Marzio Nessi.
1 BROOKHAVEN SCIENCE ASSOCIATES Preparations for Linac Commissioning Ray Fliller, Associate Physicist 8 th ASAC meeting for NSLS-II Project May 10-11,
LHC ACCESS SYSTEM 1Authors: P, Ninin, S. Grau & LHC access team EDMS: Access System during the LHC Injection tests P. Ninin, S. Grau - TS/CSE Workshop.
Proposal for Decisions 2007 Work Baseline M.Jonker for the Cocost* * Collimation Controls Steering Team.
J. G. Weisend II Deputy Head of Accelerator Projects April 2, 2014 Actions at ACCSYS Resulting from the Recommendations of the Annual Review.
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
Experimental equipment interacting with beam operation D. Macina TS/LEA Many thanks to my colleagues both from the experiments and the machine for their.
R2E Report M. Brugger for the R2E Study Group RadWG Meeting, August 20 th 2009.
MG - IEFC meeting 22/01/20101 Linac 3 shielding S. Gilardoni, M. Giovannozzi, S. Baird, R. Brown, S. Damjanovic, T. Otto, M. Widorski, Acknowledgements:
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
LHC Sector Test1 LHC Sector Test - Beam IntroductionMike LamontIntroductionMike Lamont Proposed tests with beamBrennan GoddardProposed tests with.
Stefano Redaelli Beam Department - Operations Group Operational Aspects of the Phase II Crab Cavity System LHC-CC09 3 rd LHC Crab Cavity Workshop European.
HC Review, May 2005 Hardware Commissioning Review Hardware Commissioning Review Quality Assurance and Documentation of Results Félix Rodríguez Mateos,
Project Management Mark Palmer Cornell Laboratory for Accelerator-Based Sciences and Education.
Eric Thomas - Safety systems for LHC experiments 1 Safety Systems for LHC experiments Baseline specifications – Additional needs – Actions taken.
CesrTA Experimental Plan M. Palmer for the CesrTA Collaboration November 17, 2008.
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Commissioning Samuel Krinsky-Accelerator Physics Group Leader NSLS-II ASAC Meeting October 14-15, 2010.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
The Stripping Foil Test Stand in the Linac4 Transfer Line
LHC Sector Test 1 Roger Bailey, Helmut Burkhardt, Paul Collier, Brennan Goddard, Stephen Jackson, Lars Jensen, Rhodri Jones, Verena Kain, Alex.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
Injection Energy Review D. Schulte. Introduction Will review the injection energy So could answer the following questions: Which injection energy can.
Schedule IT General Schedule 9 th, September 09 Today.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
Running scenario 2009/10 Run through components – and then synthesis.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
1 Sector Test – Preparation Layout in LSS7 Jan Uythoven (AB/BT) Thanks to Mike Lamont and the other ‘sector testers’
( LHCMAC Chamonix Summing-upLHC MAC June 15, Third LHC Project Workshop January 2006.
Chamonix 2006, B.Dehning 1 Commissioning of Beam Loss Monitors B. Dehning CERN AB/BDI.
LHC Injectors Upgrade Project 1/12/2010 R. Garoby.
Transfer Line Test preparation meeting V. Kain, R. Alemany.
LHC sector test - summary 1 14/03/2008 Possible injection into part of the machine Options etc.Mike Lamont Stopping the beamStefano Redaelli Proposed Tests.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
CERN Jan 2006 Specific safety Issues for 2006 compared to 2004 P. Cennini AB Safety Requirement in case the Installation activities are going on.
Interface of FP420 to LHC FP420 meeting 28-Sep-2006.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
LHC machine protection close-out 1 Close-out. LHC machine protection close-out 2 Introduction The problem is obvious: –Magnetic field increase only a.
Commissioning Strategy - Chamonix LHC Commissioning with Beam Overall Strategy Mike Lamont AB-OP 17 th January 2005 Chamonix XIV B.D.S.
Fabio Follin Delphine Jacquet For the LHC operation team
Mandate Priorities Other tasks Membership Forthcoming reports to CTC
LHC Commissioning with Beam
Minimum Hardware Commissioning – Disclaimer
Installation of an Instrument on a CERN machine
LHC schedule.
The LHC - Status Is COLD Is almost fully commissioned
LV Safe Powering from UPS to Clients
Consolidation and Upgrade of the LHC Experimental Vacuum Systems
Autonomous Robotics in the Nuclear Industry
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
Collimator Control (SEUs & R2E Outlook)
Remote setting of LHC BLM thresholds?
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
LHC Beam Operations Past, Present and Future
HL-LHC operations with LHCb at high luminosity
Collimators: Operations - Baseline Assumptions
The LHC Beam Interlock System
Managing Project Work, Scope, Schedules, and Cost
ThomX – Commissioning Meeting – 25/01/2018
Thursday - setup 10:00 Starting pre-cycle. 11:30 Injection.
Review of hardware commissioning
Close-out.
Reliability, MPS, Operations and Tuning Work Packages
Presentation transcript:

Injection test1 Injection test in 2006 The installation schedule version 1.7 recently approved includes a ‘possible injection test’ - foreseen in April 2006 Injection of beam down TI8, into LHC at the injection point right of point 8, though IP8 (LHCb) through sector 8-7 to a temporary beam dump located after the Q6 quadrupole just right of the warm insertion of point 7 Many good arguments for performing this test (as outlined at Chamonix 2003 session 7) Also numerous consequences (some of which were presented at Chamonix 2003 session 4)

Injection test2 Motivation Powerful diagnostic tool –Mechanical aperture checks –Field quality checks –Test diagnostic systems –Test controls, correction circuits, BPMs etc. –First hardware exposure to beam, quench limits… Major challenge/opportunity to bring everything together: full- blown systems tests, highlight oversights, debug. –Magnets, power converters, controls, timing, beam transfer etc. Provide a very important milestone for beam-based instrumentation, diagnostics and control Public relations Strongly endorsed at Chamonix 2003

Injection test3 Downside On-going installation of 3-4, 5-6, 6-7 Hardware commissioning 4-5 Will clearly pull in resources from the above –Preparation for the test –Test itself Force the installation schedule of some systems –e.g. access and interlocks Interrupt the installation and commissioning schedule of LHCb Potentially force 7-8 to be declared simple controlled radiation area with some knock-on effects

Injection test4

5 Test outline Coupled with preparation time and high operational inefficiencies

Injection test6 Classification of Radiation Areas Areas with dose rates below an average of 2.5 µSv/h are called surveyed areas. There is no restriction on access to such areas. Simple controlled areas have average dose rates of up to 25 µSv/h. –They are marked by warning signs and are generally enclosed in physical boundaries. –Persons working in such controlled areas must wear their film badge all the time. Even at extremities of proposed beam intensity envelop (several nominal bunches) – “not disastrous” In any case one should anticipate that the areas that have seen beam to be declared a “simple controlled area” Life would be a lot simpler if we remain below 2.5  Sv/h NB LHCb expects minimal losses, and will need to be classified only as “surveyed” after the test Studies and discussions ongoing

Injection test7 Point 8 TDI Can be closed fully during injection optimisation Reasonable aperture  20  Detuned insertions Smaller beam size Low emittance pilots injected

Injection test8 Access Either the planned access point between the experimental service cavern and the LHCb experiment must be operational and the shield wall in place, or a new interlocked gate must be placed at the top of PZ85

Injection test9 Injection test in 2006? Critically evaluate the arguments used to justify injecting beam into sector 8-7 of the LHC. Establish the required duration for the test and find the optimum time-slot taking into account the availability of injectors and its potential impact on the installation schedule. Elucidate requirements of, and the consequences for, the injector chains. Fully define the foreseen beam parameters and, in particular, estimate the integrated beam intensity involved. Detail the test itself and elaborate requirements: To obtain project-wide approval we need to; and …

Injection test10 Injection test in 2006? Injectors : –Elucidate requirements of, and the consequences for, the injector chains. Radiation after the event –Quantify the expected activation levels resulting from the test and potential knock-on effects due to remnant radiation, e.g. access, traceability. Consequences of installation and commissioning of other sectors –before, during and after the test. Preparation time for test. Consequences of installation and commissioning LHCb –Identify the consequences for installation and commissioning of before, during and after the test. Access Evaluate the requirements, the cost of implementation and potential impact for the access system. Evaluate possible shortcuts. Interlock system Evaluate the requirements, the cost of implementation and potential impact Evaluate required resources. What can go wrong? We need to elaborate and detail the consequences of the test:

Injection test11 Injection test in 2006 Fully define the beam parameters, the studies to be performed, and draw up detailed planning for the test itself. Fully define the required configuration for the sector. Fully define requirements of machine protection and interlock systems. Liaise with those responsible to ensure that installation and test schedule will meet requirements. Fully define requirements for controls, instrumentation, and beam-related equipment. Liaise with those responsible to ensure that installation and commissioning schedule will meet requirements. Fully define the access requirements of the test. Liaise with groups involved to ensure requirements established above are met. Define the access conditions after the test. Define the radiation monitoring needed during and after the test. Establish how to deal with any implications of remnant radiation (access, traceability). Liaise with hardware commissioning team and establish responsibilities during overlap. Establish detailed consequences for installation and commissioning of other sectors of the machine, before, during and after the test. Establish detailed consequences for installation and commissioning of LHCb before, during and after the test. Establish a detailed planning from now to the test Ensure that the necessary formalities required by INB are in place If go ahead is given:

Injection test12 Plan Fully define test conditions Impact analysis Elaborate and detail consequences of test. Seek project wide approval Detail requirements, consequences and planning YE S JUNE 2003 WORKING GROUP REPORTING TO LHCOP REPORT TO PARIS (INB) MID 2004 Minimise the impact and cost: –Before, during the test and after Maximise the efficiency of the test: Ensure the test can be performed safely Ensure INB requirements are met