Gek 16/6/041 ITRP Comments on Question 19 GEK 9/06/04 19) For the X-band (warm) technology, detail the status of the tests of the full rf delivery system.

Slides:



Advertisements
Similar presentations
Q20: The X-band collider has much tighter requirements for the alignment of the beam orbit with the structure axis, yet the basic instrumental precision.
Advertisements

Industry and the ILC B Barish 16-Aug May-05ILC Consultations - Washington DC2 Why e + e - Collisions? elementary particles well-defined –energy,
Working Group 1: Microwave Acceleration Summary 10 July 2009.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
EM vs. PM Quads Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center Undulator.
BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnetic Specifications and Tolerances Weiming Guo, NSLS-II Project In this presentation I briefly introduced the.
Question 27: Outline the key steps for industrialization of machine components and the likely remaining vulnerabilities in achieving them. Achieving industrialization.
Mercury Laser Driver Reliability Considerations HAPL Integration Group Earl Ault June 20, 2005 UCRL-POST
GRD - Collimation Simulation with SIXTRACK - MIB WG - October 2005 LHC COLLIMATION SYSTEM STUDIES USING SIXTRACK Ralph Assmann, Stefano Redaelli, Guillaume.
5 th CLIC X-band collaboration meetingWalter Wuensch16 May 2011 CLIC rf structure program.
Question 25: Delineate the R&D program remaining before a technical design review (TDR) and full cost estimate can be prepared. What are the major projects.
Drive Beam and CTF 3 International Workshop on Linear Colliders 2010 October 22, 2010 Erik Adli, Department of Physics, University of Oslo and CERN Bernard.
Summary of AWG4: Beam Dynamics A. Latina (CERN), N. Solyak (FNAL) LCWS13 – Nov 11-15, 2013 – The University of Tokyo, Japan.
Lutz Lilje DESY -MPY- Module Issues XFEL Linac Review R. Lange/L. Lilje Ongoing Tests Module Designs Future tests.
NLC MAC Meeting 6-8 Nov Linac Girder Studies and Plans C. Boffo Slide 1 Linac Girder Studies and Plans C. Boffo – E. Borissov – H. Carter Fermilab,
Summary of WG1 K. Kubo, D. Schulte, P. Tenenbaum.
MICE Target - Risk Lara Howlett University of Sheffield.
1 Flux concentrator for SuperKEKB Kamitani Takuya IWLC October.20.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
Undulator parameters choice/wish based on a simplified XFEL cost model Jürgen Pfingstner 29 st of July 2015.
D.Proch, DESY; GDE meeting Vancouver 06 Technical systems: Cavity Report Overview on costing activities for ILC –European costing method Overview industrial.
January 25, 2002David Finley to FARDOG using Harry Carter’s Slides Slide 1 Update to FARDOG: Technical Division Xband Activities Fermilab NLC Activities.
ILC Beam Delivery System / MDI Issues for LCC-phase (~
NLC Status and Milestones D. L. Burke ISG9 KEK December 10-13, 2002.
WORKSHOP SUMMARY. 2 Workshop summary CWRF08: finally we have: 54 ~10 33 talks Number of participants rose by almost 6dB.
CLIC main activities and goals for 2018 Design and Implementation studies: CDR status: not optimized except at 3 TeV and not adjusted for Higgs discovery,
Reliability and availability considerations for CLIC modulators Daniel Siemaszko OUTLINE : Give a specification on the availability of the powering.
Development of the Room Temperature CH-DTL in the frame of the HIPPI-CARE Project Gianluigi Clemente,
Linac RF Source Recommendations for Items 22,23,24,46,47 Chris Adolphsen.
CLIC TDR Task Force CLIC Zero, cost & schedule considerations R. Corsini.
Next Linear Collider 8-Pack Project D. Atkinson System Review, April 3 The 8-Pack Project at NLCTA An overview of the status and schedule for the project.
The CNGS Target Station By L.Bruno, S.Péraire, P.Sala SL/BT Targets & Dumps Section.
CLIC Workshop th -17 th October 2008 Thomas Zickler AT/MCS/MNC 1 CLIC Main Linac Quadrupoles Preliminary design of a quadrupole for the stabilization.
NLC - The Next Linear Collider Project Tor Raubenheimer The NLC Design Linear Collider Workshop 2000 FNAL October 24 th, 2000.
Beam Dynamics WG K. Kubo, N. Solyak, D. Schulte. Presentations –N. Solyak Coupler kick simulations update –N. Solyak CLIC BPM –A. Latina: Update on the.
13 September 2006 Global Design Effort 1 ML (x.7) Goals and Scope of Work to end FY09 Nikolay Solyak Fermilab Peter Tenenbaum SLAC.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
CLIC Stabilisation Day’08 18 th March 2008 Thomas Zickler AT/MCS/MNC/tz 1 CLIC Quadrupoles Th. Zickler CERN.
Emittance Tuning Simulations in the ILC Damping Rings James Jones ASTeC, Daresbury Laboratory.
Main Linac Tolerances What do they mean? ILC-GDE meeting Beijing Kiyoshi Kubo 1.Introduction, review of old studies 2.Assumed “static” errors.
Introdcution to Workpackage/Activity Reflection D. Schulte.
N. Walker, K. Yokoya LCWS ’11 Granada September TeV Upgrade Scenario: Straw man parameters.
Jan Low Energy 10 Hz Operation in DRFS (Fukuda) (Fukuda) 1 Low Energy 10Hz Operation in DRFS S. Fukuda KEK.
Round Table discussion Norbert Holtkamp SNS Oak Ridge National Laboratory August 11, 2004.
CERN, 27-Mar EuCARD NCLinac Task /3/2009.
FP7: EuCARD after a year of preparation… A.Jeremie.
DRAFT: What have been done and what to do in ILC-LET beam dynamics Beam dynamics/Simulations Group Beijing.
TBL experimental program Status and Results  Introduction  Status  Experimental program for 2010 and beyond  Outlook ACE, Steffen Döbert.
The ILC Outlook Barry Barish HEP 2005 Joint ECFA-EPS Lisbon, Portugal 23-July-05.
1 Comments concerning DESY and TESLA Albrecht Wagner Comments for the 5th meeting of the ITRP at Caltech 28 June 2004 DESY and the LC What could DESY contribute.
11/18/2008 Global Design Effort 1 Summary for Gamma-Gamma Mayda M. Velasco Northwestern University November 20, 2008 LCWS08 -- UIC, Chicago.
Beam dynamics and linac optics studies for medical proton accelerators
CTC Work Packages ver 2.1 HS for CTC. CTC-001SC wigglers Cooling design, hor. or ver. Racetrack coil Nb3Sn or NbTi cable Prototypes construction Experimental.
CERN, 27-Mar EuCARD NCLinac Task /3/2009.
The Engineering Test Facility for nLC
For Discussion Possible Beam Dynamics Issues in ILC downstream of Damping Ring LCWS2015 K. Kubo.
Second SPL Collaboration Meeting, Vancouver May 2009
TBL, Status, Plans, Experiments
Chris Adolphsen Sergei Nagaitsev
Application of the moderate peak power (6 MW) X-band klystron’s cluster for the CLIC accelerating structures testing program. I. Syratchev.
What Should We Do?.
CLIC: from 380 GeV up to 3 TeV Will also study klystron based machine for initial stage.
Background With new accelerators delivering beams always smaller and more energetic, requirements for very precise beam alignment become more and more.
High Gradient Cavities: Cost and Operational Considerations
Klystron Modulator Systems for CLIC 500
CLIC Klystron based. Updates 2017.
Measurements, ideas, curiosities
Linac LLP Outline LINAC Long Lead Procurements
Linac Design Update P. Emma LCLS DOE Review May 11, 2005 LCLS.
Breakout Session SC3 – Undulator
Presentation transcript:

gek 16/6/041 ITRP Comments on Question 19 GEK 9/06/04 19) For the X-band (warm) technology, detail the status of the tests of the full rf delivery system. What vulnerabilities still exist, and how much R&D is required to reach a full technical design? Note: This was interpreted in the responses by GLC/NLC as only referring to the SLEDII pulse compression system. I will interpret it more broadly

gek 16/6/042 Summary: R1:  Validation of performance of low group velocity structures with acceptable performance. Achieved, but testing with a significant number of structures only just started. Trip rates and damage needs more thorough investigation.  Demonstrate full power and energy handling capabilities of the dual-moded SLED-II pulse compression system. Achieved. R2:  Full test of a PPM klystron at 120 or 150 Hz Achieved, but only with 1 klystron so far, others in pipeline.

gek 16/6/043 Summary, (cont.): R2 (cont):  Klystrons to be tested with NLC modulator (at full specs and include arcing tests)………….. The tests should be made with beam. Partially achieved??? Tests done with 8 accelerator structures (1 girder), but some of these structures used the 8- stack modulator and it is not clear if they were powered by the only full spec. klystron.  Static tuning studies, including dynamic effects during correction, must be completed. In progress, but much has been done.  A detailed prototype of the main linac module (girder) must be developed to provide info. about on girder vibration. ????????

gek 16/6/044 Summary (cont.): R2 (cont.)  The performance of beam based tuning procedure to align magnets and structures must be demonstrated by complete simulations, in the presence of a wide variety of errors, in both the beam and in the components. Much has been done, but I believe much more needs doing. R3  The low level rf system needs further improvements ………. This is a complex and critical system. ??????  Long term testing of rf modules is required before mass production. Yes!!!  Continuation of R&D to develop the NLC PPM klystron…… Being done at KEK/Japanese industry, but v. important.

gek 16/6/045 Summary (cont): R3 (cont):  Development of the JLC-X linear induction modulator should continue ……… to improve the overall performance and reliability. I think this is happening at KEK.  The test recommended in R2 with a girder should be extended to a full test, with beam, of a complete linac unit, with 24 structures and 8 klystrons. I believe this is highly desirable as it would start to test linac rather than the components. However it is not likely to occur for some time, due at least in part to the availability of 8 PPM klystrons!  The magnetic centre stability (at the 1-10micron level) required in the quads must be demonstrated, over the relevant time scales of minutes to days. Yes! Not sure if this is being actively worked on we have heard almost nothing about the quads in the system

gek 16/6/046 Summary (cont): R3 (cont)  For the linac, the tuning procedures require structure alignment as well as quadrupole centering. There is a need to evaluate the systems aspects of a large interrelated alignment system. I believe that this is a crucial point in achieving the integrated luminosity goals of the machine. The complexity, size and tolerances of the whole machine is hugely challenging compared to anything yet achieved.

gek 16/6/047 Conclusions: (Vulnerabilities and R&D needed for a full technical design) 1.Klystrons Need to obtain several full spec. PPM klystrons from more than one manufacturer and lifetime test them under operating conditions. Further work on design of klystron to improve lifetime would be highly desirable both to reduce the labour of frequent replacement and replacement cost. 2.Modulator 2-pack modulator design still needs finalising and testing with two PPM klystrons. 3.Pulse compression SLED II has been demonstrated to meet spec. It requires engineering to improve manufacturability and therefore reduce price. DLDS (Delay Line Distribution System) development should, if possible be pursued, it should be more power efficient, cheaper??

gek 16/6/048 Conclusions (cont) 4.Accelerator Structures Industrialisation of full construction, not just components should be pursued. Larger assemblies of structures (at least 24) should be tested under full operating conditions in order to learn more about breakdown and damage as well as stability. Enough structures incorporating the quads and BPM and moving mechanisms should be assembled so that the stability can be verified. This will require powering and cooling. Further optimisation of the basic design to achieve even higher gradients would clearly be beneficial. 5.System integration This is a major concern for the warm machine. So far the largest unit is an 8-structure beam. Even this was not quite of final design. Really need a much larger prototype.

gek 16/6/049

10

gek 16/6/0411

gek 16/6/0412  Will not discuss the 8-pack Project, but assume that the modulator of choice is the “Next Generation Induction Modulator” the “Two Pack”.  This is a Solid State Induction Modulator using Insulated Gate Bipolar Transistors

gek 16/6/0413

gek 16/6/0414  The present 2-pack modulator undergoing tests is not the final version and has a lower efficiency than design.

gek 16/6/0415

gek 16/6/0416

gek 16/6/0417

gek 16/6/0418

gek 16/6/0419

gek 16/6/0420

gek 16/6/0421 YES HYBRID UNDER TEST< NO FINAL DESIGN ONLY 2 TUBES BUILT OPERATING AT 120 Hz. ANOTHER TUBE BEING TESTED. EXPENSIVE AND INEFFICIENT, BUT MEETS SPECS.

gek 16/6/0422 NEED TO UNDERSTAND BETTER CAUSE AND EFFECT OF BREAKDOWNS INDUSTRY NOT YET MADE ANY FULL STRUCTURES? STILL VERY SMALL SCALE, 5m OUT OF 10000m!