LAT-TD-08116-011 GLAST LAT ProjectJune 28, 2006 Mechanical Systems GLAST LAT Mass Properties Test Readiness Review Mechanical Systems GLAST LAT Mass Properties.

Slides:



Advertisements
Similar presentations
FDR Station 3 lift fixture, laser screens and brackets T. Brown and L. Morris with analysis support from A. Brooks December 3, 2007.
Advertisements

GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Document: LAT-PR-0XXXX Section 7.1 Stress Analysis 1 GLAST Large Area Telescope:
Design the Moving and Handling Fixture for the DECAM Imager Edward Chi Fermilab November 17, 2008.
GLAST LAT ProjectLAT I&T Subsystem CDR, March 28, 2003 Document: LAT-PR Section 4 - Page 1 GLAST Large Area Telescope: I & T Peer Review Performance.
GLAST LAT ProjectLAT Engineering Meeting, April 1, 2003 GLAST Large Area Telescope: Performance & Safety Assurance Darren S. Marsh Stanford Linear Accelerator.
October 21, 2003LST Mechanical Design Review - SLACN. Yu BaBar IFR Upgrades An FEA Study of the Effects of Adding Brass Plates in the IFR.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware November 2004 Status Marc Campell, Subsystem Manager.
GLAST LAT ProjectApril 27, 2006: LAT Pre-Ship Review 1 Presentation 8 of 12 Integration and Test GLAST Large Area Telescope: Pre-Shipment Review Integration.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware July 2005 Status Marc Campell, Subsystem Manager.
GLAST LAT ProjectACD CDR, January 7 & 8, 2003 Section 10 Integration and Test 1 GLAST Large Area Telescope: ACD Integration & Test Jim La/ACD I&T Lead.
GLAST LAT Instrument LAT Monthly Status Review Aug 1, 2007 W N Johnson, NRL 1 GLAST Observatory TVAC at NRL Aug 1, 2007 Neil Johnson NRL
Tracker Subsystem1 GLAST LAT Project FM4/5 PSR, May 31, 2005 GLAST LAT Tracker Tower-4/5 Pre-Ship Review INFN-Pisa.
LAT Environmental Test PDR1 GLAST LAT Project3-4 May 2005 LAT Environmental Test Planning and Design Review 3-4 May Dynamics Tests LAT Environmental.
GLAST LAT Project November 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: I&T Integration Readiness Review Integration, Facility, Configuration.
Page 1 GLAST LAT ProjectAugust 30, 2004 GLAST Large Area Telescope: LAT Accelerometer and Thermal Instrumentation Review Presented by Leonard Lee John.
1 GLAST LAT Arrival at Spectrum Assuming That the LAT Transport Container Arrives on Flatbed Truck Question: Can Transport Cover Support Crane Lift With.
High Bay Operations1 GLAST LAT ProjectMarch 2005 LAT Engineering Meeting 14 March March 2005 LAT High Bay Operations Supporting Test Events LAT.
TMT M1CS Actuator Pre-ship Meeting Avasarala Technologies Limited Bangalore, India September 13 th, 2013.
GLAST LAT Project ACD CDR Jan 7-8, Section 7 Mechanical Ground Support Equipment GLAST Large Area Telescope: AntiCoincidence Detector (ACD) Mechanical.
GLAST Large Area Telescope:
CTC / MTC 222 Strength of Materials Final Review.
Multiple Coil Lift Calculation. Purposes of the Study  To investigate the stress distribution in the MCWF and the lifting device.  To make sure mounting.
STARLight PDR 3 Oct ‘01 F.1.1 Rashid STARLight STARLight Mechanical Tahir Rashid STARLight Mechanical Engineer (734)
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Section Mechanical Systems X-LAT Assy1 GLAST Large Area Telescope: Mechanical.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Document: LAT-PR-0XXXX Section 5.1 Grid Box Design 1 GLAST Large Area Telescope:
FOOTINGS. FOOTINGS Introduction Footings are structural elements that transmit column or wall loads to the underlying soil below the structure. Footings.
LATLAT Beam Test Workshop 20th March GLAST Program Beam Test Workshop CU Outer Shipping Container Michele Pinchera
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Document: LAT-PR-0XXXX Section 6.0 Subsystem Verif. Test Plan 1 GLAST Large Area.
2.5.5 Student Book © 2004 Propane Education & Research CouncilPage Coordinating Loading and Unloading of ASME Tanks Using Contractor- Operated.
NCSX Modular Coil Turning Fixture FDR. Background Modular Coil winding forms are cast structures which provide the foundation on which the coils are constructed.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct. 2, I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist WBS
LAT-TD GLAST LAT Project 1x4 Grid Lift Fixture Weld Analysis September 19, 2003 Youssef Ismail.
1 BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnet and Girder Integration Lewis Doom, NSLS-II Project National Synchrotron Light Source II (NSLS-II) will.
LAT-TD GLAST LAT Project Tracker Inner Shipping Container Analysis and Test Results Tracker Inner Shipping Container Analysis and Test Results August.
High Bay Operations1 GLAST LAT ProjectMarch 2005 LAT Engineering Meeting 16 March 2005 LAT High Bay Operations Supporting Non-Test Events LAT Engineering.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW Boom PER 30 June RBSP EFW Spin Plane Booms Greg Dalton Space Sciences.
LAT-PR Section 33-1 GLAST LAT ProjectMechanical Design Integration Peer Review, March 2003 Mechanical Design Integration Peer Review, March 2003.
NRL Pathfinder Planning Meeting1 GLAST LAT Project07 September 2005 NRL Pathfinder Planning Meeting Dynamics Testing Update NRL Pathfinder Planning Meeting.
C osmic R Ay T elescope for the E ffects of R adiation Mechanical Design CRaTER and the Electronics Assembly Matthew Smith Mechanical Engineer (617)
LAT Environmental Test PDR1 GLAST LAT Project3-4 May 2005 LAT Environmental Test Planning and Design Review 3-4 May 2005 Overview LAT Environmental Test.
GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 1 Integration and Test Presentation 11 of 12 GLAST Large Area Telescope: LAT Pre-Shipment Review.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Section Mechanical Systems Radiator Assy1 GLAST Large Area Telescope: Mechanical.
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review Presentation 10 of 12 Mechanical Test 1 GLAST Large Area Telescope Pre-Environmental Test.
Solar Probe Plus A NASA Mission to Touch the Sun March 2015 Instrument Suite Name Presenter's Name.
TVAC Trolley Design Review1 GLAST LAT Project8 September 2005 TVAC Trolley Design Status Review 8 September 2005 TVAC Trolley Design Status Review 8 September.
LAT Environmental Test PDR1 GLAST LAT Project3-4 May 2005 LAT Environmental Test Planning and Design Review 3-4 May 2005 Operations and Logistics LAT Environmental.
LAT Transport Container1 GLAST LAT Project8 September 2005 LAT Transport Container Design Review 8 September 2005 LAT Transport Container Design Review.
BoltJoin ppt P. Rogoff 3/24/2011. NSTX Supported by P. R. 3/9/2011 Update Ring Bolted Joint Design and Recommend the Joint Geometry using bolts.
Beam Design Beams are designed to safely support the design loads.
LAT Design Integration and Analysis1 GLAST LAT Project24 May 2005 LAT Monthly Status Review 24 May 2005 Design Integration and Analysis LAT Monthly Status.
LAT-PR GLAST LAT ProjectManufacturing Readiness Review, Oct. 12, 2005 LAT Test Stand Manufacturing Readiness Review 1.Introduction Bill Olson.
DON LYNCH NOVEMBER 6, AGENDA November 4, BABAR Magnet Update Global Design Concept – Update Outer HCal Structural Analysis (2 nd pass) sPHENIX.
GLAST LAT Project I&T Integration Kickoff Meeting 03/09/04 LAT I&T MGSE Page 1 of 11 GLAST Large Area Telescope: I&T Integration Kickoff Meeting MGSE March.
GLAST LAT Project April 27, 2006: LAT Pre-Ship Review Presentation 10 of 12 Mechanical Test 1 GLAST Large Area Telescope LAT Pre-Shipment Review Mechanical.
TORSION OF A SHAFT WITH A SHOULDER FILLET
6-Mar-2016 Dan Wenman | FC Installation 1 APA installation and integration at CERN Shipment of APAs APA handling Acceptance testing Tools needed.
LAT-TD Page 1 GLAST LAT ProjectEnvironmental Test TIM, Day 1: Structural Tests, March 14, 2005 Agenda: LAT Environmental Test TIM, Day 1: Structural.
GLAST Large Area Telescope:
Gayle K. Martin November 14, 2016
SPP FIELDS V1234 Thermal PSR
Integration and Test GLAST Large Area Telescope:
GLAST LAT Acoustic Vibration Test Readiness Review
GLAST Large Area Telescope:
Thermal Vacuum Test: Plans and Procedures
Stress Analysis on SunSiphon Rack Design
GLAST Large Area Telescope:
Integration and Test Organization Chart
GLAST Large Area Telescope:
Design Integration and Analysis
SNS PPU Cryomodule Space Frame
Presentation transcript:

LAT-TD GLAST LAT ProjectJune 28, 2006 Mechanical Systems GLAST LAT Mass Properties Test Readiness Review Mechanical Systems GLAST LAT Mass Properties Test Readiness Review

LAT-TD GLAST LAT ProjectJune 28, 2006 Contents Test Plan Review –Document List –Objectives and Pass/Fail Criteria for the Testing –Deviations from flight and configuration –Test Configuration Pre-Test Analysis –Calculation Tools –Alignment and Accuracy –Summary Test Procedure –Expected Test Durations –Personnel –Facility Readiness and Schedule Action Item Form

LAT-TD GLAST LAT ProjectJune 28, 2006 Mechanical Systems GLAST LAT Mass Properties TRR: Test Plan Review Mechanical Systems GLAST LAT Mass Properties TRR: Test Plan Review

LAT-TD GLAST LAT ProjectJune 28, 2006 Mass Properties Test – Document List

LAT-TD GLAST LAT ProjectJune 28, 2006 Mass Properties Test Plan – Objectives The LAT will be set atop of a test platform where mass properties testing will be performed to accomplish the following objectives: –Measure the overall mass and CG of the fully integrated LAT –Verify the following three IRD requirements: –LAT mass does not exceed 3000kg –By Analysis, show Z cg is a maximum of 185mm above the LAT Interface Plane (LIP) –By Test, show X-cg and Y-cg are within 20mm of the LAT Coordinate System (LCS) Z-axis A secondary goal is to verify that the measured mass properties coordinate with the math model mass matrix

LAT-TD GLAST LAT ProjectJune 28, 2006 Mass Properties Test Plan – Entrance/Exit Criteria The Mass Properties Testing is performed following the LAT thermal vacuum test. The following criteria is to be met before the mass properties testing can begin: –LAT radiators have been removed and the LAT, flexures, and TIP have been moved into the mass properties test area- visual inspection verifies that all the LAT has been re- configured correctly. All travelers verified to be complete. The LAT is in its flight configuration, except as detailed in the test procedure and Slide 7. –Remove triple joint cover plate (non-flight) –Remove chiller bars –All subsystem units/modules function—each subsystem has passed its CPT following TVAC. Any performance discrepancies have been clearly documented. –Ensure all E-GSE cable harnesses have been removed from the LAT prior to test. –All load cells, support equipment, and electronics are in place and functioning properly. Instrumentation has been mounted in correct locations and orientations following the protocol in the test procedure. All non-fly-away accelerometers and other test instrumentation, cables and harnesses are removed or offloaded –Pass this Mass Properties Test TRR Whether or not the mass properties testing is successful will be determined by the following exit criteria: –Visual inspection of the LAT verifying that there is no visual damage –Preliminary examination of the recorded data; all data is usable for analysis

LAT-TD GLAST LAT ProjectJune 28, 2006 Mass Properties Test Plan – Deviations From Flight The following flight hardware is not installed for the mass properties test –Radiators not installed –Radiator Blankets –Fly away instrumentation shorting plugs –Miscellaneous tape and sealants Additionally, the following non-flight items are installed –Connector savers –ESD/Contamination control Bag Remove LAT from test stand and move to mass properties plate Remove Radiators

LAT-TD GLAST LAT ProjectJune 28, 2006 Mass Properties Test – Test Configuration The LAT is mounted to the test interface plate The test interface plate is then lowered onto the test platform which will take the mass and cg measurements The test platform comprises –An octagonal plate (LAT DS-08303) to transfer the weight of the LAT to the three load cells without inducing detrimental distortion to the TIP –Three load cells (5K Beowulf model 200-S P/N: LC2030 ) arranged in an equilateral triangle whose centroid is aligned with the LCS –NRL Modal survey plate which provides a stable platform for the test Test Platform Top View: Octagonal test plate and locations of the three load cells Test Configuration LC1 LC3 LC2

LAT-TD GLAST LAT ProjectJune 28, 2006 Test Spreadsheet

LAT-TD GLAST LAT ProjectJune 28, 2006 Test Spreadsheet, page 2

LAT-TD GLAST LAT ProjectJune 28, 2006 Alignment and Accuracy Alignment –To calculate mass and CG of the LAT, the load cell positions must be known w.r.t. the LAT coordinate system. To accomplish this, the following true positions are known: Load cell positions w.r.t. indexing pin locations Indexing hole and slot positions w.r.t. LAT coordinate system –From these positions, the load cell positions in LAT coordinate system is known. –From the Load cell positions, a sum of moments about the LCS is performed to calculate X cg and Y cg Accuracy –The 5 KIP load cells have been calibrated to be accurate within 0.5%, or ±25 lb f –A dry run was performed on 9/10/ lb f reference mass weighed in at 3007, 3012, 3011, and 3010 in four readings Additional reference mass was added, which showed accuracy to 2.5 ± 0.5 lb f –Worst case aggregate error on mass is believed to be on the order of 10 lbf, or less than 0.5% –CG calculations will be taken in four orientations (0°, 90°, 180°, 270°) and then averaged in order to cancel round-off errors

LAT-TD GLAST LAT ProjectJune 28, 2006 Mass Properties Test analysis - Summary Mass properties platform has been analyzed to evaluate the following structural elements: –Distortion under load – peak distortion is inches (minimal rotation) out of plane, which is on the same order of magnitude as plate flatness – under 1g load, this is insignifcant –Stresses in the plate – maximum stress under load is 2.54 ksi  margins high –Tip-over loads – minimum lateral load for tip-over is over 1000 lb f, which is not credible –Handling loads – 2-point lift margins are high Mass properties spreadsheet has been updated to include –97.8% measured mass ( kg) –2.2% calculated mass (61.8 kg) –Total mass = kg –Current Predictions (including radiators) Xcg = mm Ycg = -1.2 mm Zcg = mm Analysis is provided in the Back-up slides

LAT-TD GLAST LAT ProjectJune 28, 2006 Expected Test Schedule and Durations Date of Test: 9/12/06 – 9/13/06 TimeDurationTask 1 hour Position LAT on the platform, get load cell reading 1 hour Lift LAT off platform, rotate 90 degrees, remount to plate, get load cell reading 1 hour Lift LAT off platform, rotate 90 degrees, remount to plate, get load cell reading 1 hour Lift LAT off platform, rotate 90 degrees, remount to plate, get load cell reading 1 hour Lift LAT off platform, rotate 90 degrees, remount to plate, get load cell reading

LAT-TD GLAST LAT ProjectJune 28, 2006 Personnel RoleNameTelephone Number Project RepresentativeScott Clough Paul Baird (301) (301) Test DirectorJohn Ku(408) Test Conductor, Primary Instrumentation/Data Support Bob Haynes(202) I&T SupportBill Olson Eliazar Ortiz Leo Manger Tom Nieland Dave Kheil Quality Assurance SupportJoe Cullinan Doug Bartholemew (650) Facilities Logistical SupportBill Rayner(202) High Bay Logistical SupportPaul Dizon(202) The following personnel are responsible for the procedures of the test:

LAT-TD GLAST LAT ProjectJune 28, 2006 Mass Properties Facilities Readiness and Schedule Facilities ready to go –Mass properties test dry-run complete on 9/10/06  all systems go LAT ready to go –LAT extracted from TV chamber 9/10/06 –LAT rotation complete 9/10/06 –Radiator removal estimated completion 9/11/06 LAT ready to test 9/12/06 – 9/13/06 Preliminary report complete 9/14/06

LAT-TD GLAST LAT ProjectJune 28, 2006 Mass Properties TRR Action Item Form Topic / presentation slide number: Submitted by: Actionee: Request: Reason / Comment:

LAT-TD GLAST LAT ProjectJune 28, 2006 Mechanical Systems GLAST LAT Mass Properties TRR: Back-up Slides Mechanical Systems GLAST LAT Mass Properties TRR: Back-up Slides

LAT-TD GLAST LAT ProjectJune 28, 2006 Finite Element Models Finite Element Models Shown above are the displacements (inches) of the octagonal plate when the LAT and test interface plate are mounted on top and secured Shown below are the stress reactions (lbs/in^2) of the octagonal plate when the LAT and test interface plate are mounted on top and secured f

LAT-TD GLAST LAT ProjectJune 28, 2006 Finite Element Models Shown above are the stress concentrations (lb/in^2) of the load cell base plate when a force strong enough to tip the load cell occurs Shown below are the displacements (inches) of the load cell base plate when a force strong enough to tip the load cell occurs

LAT-TD GLAST LAT ProjectJune 28, 2006 Calculations Final Results of the Hand Calculations and Finite Element Modeling Max Stress Max Displacement Load Cell Base < 11,800 lb/in^2 < in Test Plate 2540 lb/in^ in Tip-Over Force for Load Cell 1118 lbs Tip-Over Force for Entire LAT 5010 lbs ** The force for the load cell was calculated as if the force were applied at the top edge of the load cell, while the force for the entire LAT were calculated as if it were applied at the CG of the entire system **

LAT-TD GLAST LAT ProjectJune 28, 2006 Calculated Torques Required torques were calculated for three crucial fasteners in the mass properties testing Fastener TypeTorque #10-32 UNF40 in x lb ½ -13 UNC100 ft x lbs 1 – 14 UNF190 in x lbs A tear out shear was calculated for the swivel rings Calculated as a two-point lift A36 steel has a yield of 36 ksi (21.6 ksi when the shear to tension yield ratio is considered) The allowable shear would be 21.6 ksi, while the swivel had a tear out shear of only 7.9 ksi The threat of a tear out is not realistic with the 1.5” plate

LAT-TD GLAST LAT ProjectJune 28, 2006 Drawings for the Load Cell Base and Octagonal Plate Shown above is the drawing for the load cell base plate Shown below is the drawing for the octagonal plate