The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,

Slides:



Advertisements
Similar presentations
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Advertisements

Cryogenic system in P4: Possible options S. Claudet & U. Wagner LHC Workshop, “Chamonix XlV” January 2005 (Mostly for RF & beam scrubbing)
Going towards LHC Run2 CRYOGENICS 5 th Evian Workshop 2-4 June 2014 SESSION 4 - Systems 2 - Status and commissioning plans (HW perspective) Krzysztof Brodzinski.
Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005.
Laurent Tavian Thanks to contribution and helpful discussions with M. Jimenez, V. Parma, F. Bertinelli, J.Ph. Tock, R. van weelderen, S. Claudet, A. Perin,
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
SC - 04Feb'13Cryo Heaters Review Cryogenic Heaters Review Operation use and wishes S. Claudet - A. Suraci LHC Cryogenic Operation.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Large-capacity Helium refrigeration : from state-of-the-art towards FCC reference solutions Francois Millet – March 2015.
CRYOGENICS AND POWERING
23 Jan 2007 LASA Cryogenics Global Group 1 ILC Cryomodule piping L. Tavian for the cryogenics global group.
FCC Study Kick-off Meeting Cryogenics Laurent Tavian CERN, Technology Department 14 February 2014 Thanks to Ph. Lebrun for fruitful discussions.
E. Todesco PROPOSAL OF APERTURE FOR THE INNER TRIPLET E. Todesco CERN, Geneva Switzerland With relevant inputs from colleagues F. Cerutti, S. Fartoukh,
Accelerators for ADS March 2014 CERN Approach for a reliable cryogenic system T. Junquera (ACS) *Work supported by the EU, FP7 MAX contract number.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
Introduction to LHC cryogenic system (layout, architecture) Preparation before cool-down (Purge, flushing) Transient operations to reach nominal operating.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Cryogenics in SPS & LHC (2 K / 4.5 K) LHC-CC11, 14 November 2011 L. Tavian, CERN, TE-CRG With the contribution of N. Delruelle, G. Ferlin & B. Vullierme.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
AT-MEI-PE, RD, LIUWG 31-JUL R. Denz AT-MEI-PE LHC Luminosity Upgrade Protection of the Inner Triplet, D1, Correctors and Superconducting Links/Leads.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
L. Serio COPING WITH TRANSIENTS L. SERIO CERN, Geneva (Switzerland)
5 th Joint Hi-Lumi LHC-LARP Annual Meeting 2015 SC Link Protection A.Ballarino 28/10/2015.
C.KotnigFCC Design Meeting FCC Beam Screen cooling Claudio Kotnig.
R. van Weelderen, LIUWG, IT upgrade phase I: Status of cryogenic scheme evolution (in work) Outline - Old & new layout - Design constraints.
Cryogenics for crab cavities – SPS/LHC 2 nd HiLumi LHC meeting – Frascati (Italy) 15 November 2012 K. Brodzinski and L. Tavian on behalf of cryogenic team.
Heat loads and cryogenics L.Tavian, D. Delikaris CERN, Cryogenics Group, Technology Department Accelerators & Technology Sector Friday, October 15, 20101HE-LHC'10.
SM18 cryogenics infrastructure upgrade L. Serio TE-CRG.
MAGNET#1MAGNET#2MAGNET#3 SATELLITE VB#1 SATELLITE VB#2 SATELLITE VB#3 PRECOOLER#1PRECOOLER#2 DISTRIBUTION VALVE BOX DVB CP#1CP#3CP#2 BUFFER DEWAR LHe 5m.
TE-CRG Activities D. Delikaris, TE-CRG.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Crab cavities – cryogenics for SPS and LHC LHC-CC13, 6 th LHC Crab Cavity Workshop – CERN, Geneva, Switzerland 9-11 December 2013 K. Brodzinski on behalf.
LMC 1 (Pre Chamonix) DN200 relief valve position DN200 relief valve position On top wherever possible. Open W bellows for MLI protection. On top wherever.
8/29/07K. C. Wu - Brookhaven National Lab1 Major Components in ILC IR Hall Interchangeable Detectors.
Project X Workshop - Cryogenics1 Project X CRYOGENICS Arkadiy Klebaner.
5-year operation experience with the 1.8 K refrigeration units of the LHC cryogenic system G. Ferlin, CERN Technology department Presented at CEC 2015.
Cryogenics for SuperB IR Magnets J. G. Weisend II SLAC National Accelerator Lab.
Logo area HL LHC IT STRING M. Bajko CERN TE-TM and QXF Review.
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
ILC : Type IV Cryomodule Design Meeting Main cryogenic issues, L. Tavian, AT-ACR C ryostat issues, V.Parma, AT-CRI CERN, January 2006.
FCC Infrastructure & Operation Update on the cryogenics study Laurent Tavian CERN, TE-CRG 28 October 2015.
FCC Refrigeration cost vs magnet temperature Laurent Tavian CERN, ATS-DO 15 February 2016.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
FCC Week 2016, Roma Cryogenics overview Laurent Tavian, CERN, ATS-DO On behalf of the FCC cryogenics study collaboration 14 April 2016.
R. van Weelderen and U. Wagner CERN
Cryogenics storage and distribution
HL-LHC IT STRING and Series test of SC link
M Chorowski, H Correia Rodrigues, D Delikaris, P Duda, C Haberstroh,
SLHC –PP WP6 LHC IR Upgrade - Phase I.
Innovative He cycle Francois Millet.
SPS cryogenic proximity equipment and SM18 validation
S. Claudet, Daniel Berkowitz & A. Perin (TE-CRG)
CRYOGENICS – strategy, unavailability root causes and limitations
Hollow e- lens, Cryogenic aspects
Accelerator and Experiment Interface Session: LS2, LS3
The HL-LHC project, and associated Cryogenics
Daniel Berkowitz (TE-CRG)
on behalf of FCC cryogenic team
Circuits description and requirements - Closed Session-
COOLING & VENTILATION INFRASTRUCTURE
Cooling Update (27 March 2014)
TEST PLANS for HL LHC IT STRING
Cooling aspects for Nb3Sn Inner Triplet quadrupoles and D1
Cooling Update (27 March 2014)
Summary post TCC#54_02Aug’18
Cryogenic management of the LHC Run 2 dynamic heat loads
Laurent Delprat CERN, Geneva, Switzerland
HL-LHC New MS optimisation WP9, Preliminary cost estimates
Presentation transcript:

The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme, Grant Agreement Overall plans for Cryogenics for HL-LHC Laurent Tavian, Cryogenic Group, Technology Department, CERN With the contribution of K. Brodzinski, G. Ferlin, U. Wagner & R. van Weelderen

Content Overall HL-LHC layout Overall HL-LHC layout Cryogenic layout proposals at: Cryogenic layout proposals at: Point 1 and Point 5 Point 1 and Point 5 Point 4 Point 4 Point 7 Point 7 Local and global cryo-limitation in Sectors Local and global cryo-limitation in Sectors Specific studies and tests Specific studies and tests Schedule and conclusion Schedule and conclusion

Overall HL-LHC layout HL-LHC cryo-upgrade: HL-LHC cryo-upgrade: 2 new cryoplants at P1 and P5 for high luminosity insertions 2 new cryoplants at P1 and P5 for high luminosity insertions 1 new cryoplant at P4 for SRF cryomodules 1 new cryoplant at P4 for SRF cryomodules New cooling circuits at P7 for SC links and deported current feed boxes New cooling circuits at P7 for SC links and deported current feed boxes Cryogenic design support for cryo-collimators and 11 T dipoles at P3 and P7 Cryogenic design support for cryo-collimators and 11 T dipoles at P3 and P7

Main components at Point 1 and 5 ?: what about new Q6 and additional Q7+? Inner tripletMatching section Continuous cryostat Continuous cryostat ?? ? ? (& quench buffers) Ground level Shaft Cavern

P1 & P5 layout 1: Matching section cooled with sector cryoplants P1 or P5 S81 or S45 S12 or S56

P1 & P5 layout 2: Matching section cooled with inner triplet cryoplants P1 or P5 S81 or S45 S12 or S56

Comparison of layouts at P1 and P5 AdvantageDrawback Layout 1: MS with sector Corresponds to the CtC baseline (minor modification on the existing QRL, i.e. only new jumper extensions foreseen)… Better sharing of high current circuits within SC links. …but reuse of existing QRL if the new MS layout largely differ from the existing one (operating temperature and/or new equipment (D2, CC, Q4, Q5, Q6? Q7+?…))  could be also expensive and space consuming… …and maybe not feasible! i.e MS will need a new compound transfer line (8-10 MCHF tbc) Layout 2: MS wit IT Optimisation of the distribution and space with respect to the HL-LHC need. Allow the upgrade of “A” boxes during LS2 Complete sectorization of MS + IT allowing mechanical intervention without warm-up of the two adjacent sectors (but interconnection, if any, must be designed accordingly) Increase of the CtC (~1 km of compound transfer line with ~20 service modules)  additional cost (8-10 MCHF tbc) Increase of number of high current circuits in the “X” SC link

Interconnection for partial redundancy Present redundancy baseline w/o interconnection (IB) in between cryoplants ! “Partial” redundancy:- cold standby during technical and Xmas stops - low beam-intensity operation in case of major breakdown on the new cryoplant (full nominal redundancy not possible) - what about redundancy with detector cryogenics ? Cost increase

Interconnection box (IB) Up to 10 cryogenic valves to be integrated in the tunnel (space ?)  Volume in between valves used as controlled volume for safe cryo-consignation  Valve DNs depend on the level of needed redundancy

Space requirement in caverns and shafts Shaft requirement  In addition to the 3 SC links: - 1 compound cryoline (~DN500) - 3 warm recovery lines (~DN ) Cavern requirement: - 1 cold compressor box

Minimum CCB requirement in cavern Depending of the total cooling capacity and operating temperature Single CC trainDouble CC train Best for cavern integration Global or distributed ? (500 W max size for distributed HX !) 500 W HX

Number of cold compressor trains LHC sector Present HL-LHC Requirement (tbc)

Minimum size of cold compressor box (CCB) ~6 m ~1.6 m ~5.5 m + electrical cabinets in protected area for instrumentation, AMB controllers and variable-frequency drives (~0.6 x ~2.7 x ~2.2 m 3 )  Ground level installation of cabinets under study with 150 m of cabling (today: 25 m max)

P4 Layout: new cryogenics for SRF module With interconnection for partial redundancy (Accepted as baseline) P4 S34S45

P4 cryogenic process & flow diagram UCB: K cryoplant (tbc) UX45

P7 Layout: Deported current feed boxes New cooling circuits for SC links and deported current feed boxes New cooling circuits for SC links and deported current feed boxes Extension of the warm recovery lines to the TZ76 Extension of the warm recovery lines to the TZ76 Cryogenic design of new SC links and current feed boxes. Cryogenic design of new SC links and current feed boxes. TZ76 S67 S78

Sector heat loads: local limitation Synchrotron radiation  Synchrotron radiation  Image current  Image current  Beam gas scattering  Beam gas scattering  Resistive heating  Resistive heating 

Sector heat loads: global limitation Load transfer from 1.9 K to K refrigeration Installed (as specified) ~1 W/m per aperture available for e-cloud  ~20 % lower than local limitation (OK !)

Specific cryogenic studies and tests (or what differ from LHC design ?) Cooling circuits for large heat deposition: Cooling circuits for large heat deposition: on 1.9 K cold masses up to 10 W/m  heat extraction from SC cables and quench energy margin  Generic heat flow in magnet cross section on 1.9 K cold masses up to 10 W/m  heat extraction from SC cables and quench energy margin  Generic heat flow in magnet cross section on beam-screens up to W/m (image current effect ?) on beam-screens up to W/m (image current effect ?) Cooling of HTS SC links and current feed boxes Cooling of HTS SC links and current feed boxes Cooling and pressure relief of crab-cavities Cooling and pressure relief of crab-cavities Validation tests on SC link, crab-cavities, magnets, beam screens… Validation tests on SC link, crab-cavities, magnets, beam screens… Reactivation of the Heat Load Working Group Reactivation of the Heat Load Working Group Quench containment and recovery (cold buffering ?) Quench containment and recovery (cold buffering ?) Large-length cable (150 m) for cold-compressor controls and drives Large-length cable (150 m) for cold-compressor controls and drives Large capacity ( W) sub-cooling heat exchangers Large capacity ( W) sub-cooling heat exchangers Larger turndown capacity factor on 1.8 K refrigeration cycle: up to 10? Larger turndown capacity factor on 1.8 K refrigeration cycle: up to 10? From users to cryogenic infrastructure

Schedule : Freeze of heat load requirement P7 P1&P5 ? (type A) P1&P5 (type X & A)

Conclusion Several HL-LHC cryogenic layouts have been presented with alternatives for cooling sectorization and redundancy  additional study needed for final decision Several HL-LHC cryogenic layouts have been presented with alternatives for cooling sectorization and redundancy  additional study needed for final decision Preliminary heat load estimate is defined :  local and global limitation for sector cryogenics are compatible with the proposed HL-LHC beam parameter.  the HLWG to refine and follow the heat load inventory have to be reactivated. Preliminary heat load estimate is defined :  local and global limitation for sector cryogenics are compatible with the proposed HL-LHC beam parameter.  the HLWG to refine and follow the heat load inventory have to be reactivated. Specific cryogenic studies and tests are defined  some of them have already started Specific cryogenic studies and tests are defined  some of them have already started Integration study of new underground equipment must be done to validate:  the possible reuse of part of the existing distribution system (QRL)  the underground space availability for the cold compressor boxes at P1 and P5 Integration study of new underground equipment must be done to validate:  the possible reuse of part of the existing distribution system (QRL)  the underground space availability for the cold compressor boxes at P1 and P5