Lead from the front Texas Nodal 1 Texas Nodal Market Implementation Program Implementation Scenarios September 6, 2006.

Slides:



Advertisements
Similar presentations
June 26, 2008 TAC Texas Nodal Market Implementation: Program Update Jerry Sullivan.
Advertisements

EMS User’s Group 2008 Presented By Curtis Crews of ERCOT and Margaret Goodrich of Project Consultants, LLC Presented to EMS User’s Group Atlanta, GA September.
October 22, 2007 TPTF Meeting Early Delivery Systems Status Update and Forecast Daryl Cote/John Webb/John Hall.
1 Texas Nodal Texas Nodal Program Implementation TPTF June 6, 2006 Agenda.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation Program Scenarios / Trade-Offs September 5, 2006.
Lead from the front Texas Nodal 1 TPTF Update for TAC November 29, 2007 Trip Doggett.
Market Implementation Board Presentation October 1 Texas Nodal Market Implementation ERCOT Board of Directors Meeting Program status.
Lead from the front Texas Nodal 1 Single-Entry Model Milestone Status Report May 1, 2008.
July 9, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan.
1Texas Nodal Texas Nodal Market Trials and Data Verification ROS Meeting By Steve Grendel, ERCOT Thursday, 01/11/2007.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation TPTF Nodal Status Update November 6, 2006.
Market Implementation Board Presentation July – v1.1F 1 Texas Nodal Market Implementation ERCOT Board of Directors Meeting Program.
EDS 2 Early Delivery Systems Review and Request for Approval May 2007 John Webb.
March 20, 2008 TPTF CIM Update Raj Chudgar Program Director for Market Redesign.
Lead from the front Texas Nodal 1 Texas Nodal Load Frequency Control (LFC) EDS 3 Release 6 - Handbook EDS 3 Release 6 MP Planning.
Texas Nodal Timeline Options, TPTF Jul 11, Timeline Options Trip Doggett TPTF
ROS Meeting – 12/06/071Texas Nodal Program - TPTF Update Texas Nodal Transition Plan Task Force ROS Meeting Stacy Bridges, ERCOT Thursday, 12/06/2007.
September 8, 2008 TPTF Nodal Core Projects Updates Nodal Project Managers.
TPTF CIM Health Check Raj Chudgar Program Director for Market Redesign.
Lead from the front Texas Nodal 1 Texas Nodal Critical Path Update TPTF Date xxx.
March 11, 2008 Texas Nodal Market Redesign Program Commercial Operations Subcommittee.
Lead from the front Texas Nodal 1 TPTF Update for TAC March 8, 2007 Trip Doggett.
COMS Nodal Commercial Systems Project Update COPs Meeting May 2007 By Bill Barnes and Justin Rasberry.
January 15, 2008 Monthly Board of Directors Meeting Texas Nodal Market Implementation Program Update Jerry Sullivan.
Lead from the front Texas Nodal 1 Texas Nodal Congestion Revenue Rights (CRR) EDS 3 Release 7 - Overview EDS 3 Phase 2 MP Planning.
Credit Monitoring and Management Status TPTF December 17, 2007.
July 7, 2008 TPTF Texas Nodal Market Implementation: - Program Update - Market Readiness Update Jerry Sullivan.
Lead from the front Texas Nodal 1 Integrated ERCOT Readiness and Transition (IRT) TPTF - November 6 th, 2006.
12/4/2007 ERCOT Public INF MP Identity Management Jeff Floyd Gary Macomber.
September 25, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan.
January 21, 2008 TPTF 168 Hour Test Initial Approach Discussion.
Lead from the front Texas Nodal 1 TPTF Update for TAC February 1, 2007 Trip Doggett.
February 20, 2006 Nodal Architecture Overview Jeyant Tamby 20 Feb 2006.
EDS 2 Early Delivery Systems Release 3 – Workshop August 16, 2007.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation ERCOT Board Of Directors – August 15, 2006 TPTF Meeting August.
Lead from the front Texas Nodal 1 EDW Update to TPTF November 27, 2007 Janet Ply, PhD EIS Nodal EDW Project Manager.
Lead from the front Texas Nodal 1 Texas Nodal EDS 3 Early Delivery System Plan TPTF April 02, 2007.
Nodal Program Update Mike Cleary Sr. VP and Chief Technology Officer.
August 25, 2008 TPTF Nodal Status Report: Integrated Schedule Update Change Control Update Adam Martinez Troy Anderson.
Integrated Release Approach and Update TPTF 11/10/2008 Matt Mereness.
TPTF CIM Health Check Raj Chudgar Program Director for Market Redesign.
Lead from the front Texas Nodal 1 TPTF Update for TAC January 4, 2007 Trip Doggett.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation Program Implementation Scenarios September 6, 2006.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation Program Scenarios / Trade-Offs September 5, 2006.
October 8, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan Program Director, Market Redesign.
September 22, 2008 TPTF Nodal Status Report: Project Status Updates Nodal Project Managers.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation Integration Update October 24, 2006 Daryl Shing, Enterprise.
Market Redesign Update ERCOT Board of Directors Meeting April 18, 2006 Ron Hinsley Chief Information Officer
Lead from the front Texas Nodal 1 Texas Nodal EDS 4 Early Delivery System Plan TPTF May 22 nd, 2007.
August 27, 2007 Executive Committee Meeting Texas Nodal Program Update Jerry Sullivan.
Lead from the front Texas Nodal 1 Reduction of MMS Vendor Effort for TPTF January 8, 2008 Murray Nixon Sai Moorty.
Lead from the front Texas Nodal 1 Integrated ERCOT Readiness and Transition (IRT) TPTF – December 4 th, 2006 ERCOT Qualification.
Lead from the front Texas Nodal 1 Texas Nodal EDS Market Trials Approach Wednesday, November 29, 2006.
April 1, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan.
1 Texas Nodal Texas Nodal Program Implementation TAC July 6, 2006 Agenda.
Retail Workshop ERCOT Nodal Update October 06, 2010.
Lead from the front Texas Nodal 1 Early Delivery System Testing Environments & Planning – Involving Market Participants TPTF May.
Lead from the front Texas Nodal 1 TPTF Update for TAC August 2, 2007 Trip Doggett.
October 2, 2008 TAC Texas Nodal Market Implementation: Program Update Ron Hinsley.
January 3, 2008 TAC Meeting Texas Nodal Program Update Jerry Sullivan.
June 5, 2008 TAC Texas Nodal Market Implementation Program Update Jerry Sullivan.
ROS Meeting – 06/12/081Texas Nodal Program - TPTF Update Texas Nodal Transition Plan Task Force ROS Meeting Stacy Bridges, ERCOT Thursday, 06/12/08.
1 Market Trials Update NATF January 5, 2010.
6/21/2007 TPTF: Baselines 1&2 WP and CI Baselines 1 and 2 White Papers and Change Items Diran Obadina.
1 Single Entry Model (SEM) Go-Live TAC Update May 7, 2009.
Lead from the front Texas Nodal 1 Texas Nodal EDS4 - Approach 11/28/2007.
August 11, 2008 TPTF EDS Sequence and Durations Discussion Daryl Cote.
1 1 Texas Nodal Program UpdateMarch 21, 2008 Nodal SAS70 Audit – Readiness Approach & Timeline March ‘08June ‘08 Sept ‘08 Dec ‘08 Jan ‘09 Define Readiness.
NMMS Nodal Network Mgmt and Monitoring System Update
Texas Nodal Program Current Schedule and Recent Changes
Presentation transcript:

Lead from the front Texas Nodal 1 Texas Nodal Market Implementation Program Implementation Scenarios September 6, 2006

Lead from the front Texas Nodal 2 Scenario #1 – single release (baseline) (Nodal Market live & Zonal Market Shutdown July 2009) EMS Early Delivery Systems MMS CRR MIS NMMS Commercial Systems ERCOT & MP Readiness Q2 2008Q3 2009Q4 2008Q3 2008Q2 2007Q1 2007Q4 2006Q4 2007Q3 2007Q1 2008Q3 2006Q Outage Scheduler EDW “UI in production” Q Qualification Freeze EDS 3 (TXMACS 0.3) SCED; MP SCED Offers EDS 4 TXMACS 0.4) with selected MPs EDS 5 (TXMACS 0.5) MMS FATMMS SAT CRR Design, Build, Pre-FATCRR FATCRR SAT Final MP Interface Specs 3/31 MP Registration complete MIS FATMIS SAT 168 hour market trial FATSAT Naming Convention DB NMMS Build Common model update process NODAL GO LIVE MIS (EMS/MMS/CRR) Design, Build, Pre-FAT EDW FATEDW SAT Statements Layout Script test Credit Monitoring End of Trials MP Nodal RegistrationMP Financial & Operational Qualification EMS SATEMSEMS FAT EMS Requirements, Conceptual Design MIS SAT MIS (SCED) Design, Build, Pre- FAT MIS FAT MMS Design, Build, Pre-FAT MMS Requirements, Conceptual Design OS SATOS BuildOS FAT OS Requirements, Conceptual Design CRR Requirements, Conceptual Design Commercial Systems Design, Build, Pre-FATCS FATCS SAT EDW Requirements, Conceptual Design SCED SATSCED BuildSCED FAT SCED Requirements, Conceptual Design Registration ready MPSCED Offers Business Requirements complete 10/30 Preliminary MP Interface Specs 12/31 CS FATCS SAT EDW FATEDW SATEDW FATEDW SAT CS Requirements, Conceptual Design EDW Design, Build, Pre-FAT MIS FATMIS SAT Begin MP trial participation “Non-binding settlements” Financial Transfer CS FATCS SAT EDS 4 MP SAT TXMACS 1.0 Live operations MIS FATMIS SAT “CRR Auction for Go Live” OTS SAT OTS FAT EDS 3 Data Validation NMMS Conceptual Design Naming Convention information collection Model Data Certification Model Data Remediation Reconciliation Assumptions affecting the critical path The current State Estimator will meet the necessary criteria Current NMMS product will be capable of providing Real Time Models for any Nodal System Vendors selection will be done by Mid-June Vendors will share detailed design documents with other vendors for interface definitions TDSPs will be trained on new NMMS and there will dual entry of models – into the new NMMS and into GENESYS. ERCOT will have enough staff to handle this work To allow for interface definitions, detailed design documents of individual projects can be completed 80 hours after one another. The order of completion will be NMMS – MMS/EMS/SE – CRR/Outage Schedule – Commercial Systems – MIS/EDW To satisfy section 17.3 of the Nodal protocols, ERCOT will deploy COGNOS and SAS to provide PUCT with the ability to generate reports ERCOT would need 6 months of integration testing on applications such as MMS, CRR and NMMS Areva’s EMS will handle CIM models All systems have to conform with the integrated Data Dictionary TPTF will hold review meetings as required for approval of requirements and conceptual design documents

Lead from the front Texas Nodal 3 Scenario #2 – 3 incremental releases & slack removed (Release 2 & Zonal Shutdown July ’08, Release 3 January ’09) EMS Trials & Implementation MMS CRR MIS NMMS Commercial Systems ERCOT & MP Readiness Q2 2008Q3 2009Q4 2008Q3 2008Q2 2007Q1 2007Q4 2006Q4 2007Q1 2008Q3 2006Q Integration EDW Q Qualification Freeze EDS 3 EDS 4 MMS FATITEST CRR Design, Build, Pre-FATCRR FATITEST Final MP Interface Specs 3/31 MP Registration complete 168 hour market trial Real Time Operations GO/NO GO Zonal Shutdown GO/NO GO MIS (EMS/MMS/CRR) Design, Build, Pre-FAT EDW FATITEST Statements Layout Script test End of Trials MP Nodal Registration MP Financial & Operational Qualification ITESTEMSEMS FAT EMS Requirements, Conceptual Design ITEST MIS (SCED) Design, Build, Pre- FAT MIS FAT MMS Design, Build, Pre-FAT MMS Requirements, Conceptual Design ITEST OS Build FAT OS Requirements, Conceptual Design CRR Requirements, Conceptual Design Commercial Systems Design, Build, Pre-FATCS FATITEST EDW Requirements, Conceptual Design ITESTSCED BuildSCED FAT SCED Requirements, Conceptual Design Registration ready MPSCED Offers Business Requirements complete 10/30 Preliminary MP Interface Specs 12/31 CS Requirements, Conceptual Design EDW Design, Build, Pre-FAT MIS FATITEST Begin MP trial participation EDS 4 MP SAT OTS ITEST OTS FAT EDS 3 Data Validation Planning UI FAT ITEST Naming Convention DB Common model update process NMMS Conceptual Design Naming Convention information collection Model Data Certification Model Data Remediation Reconciliation NMMS Build Outage Scheduler EDS 1/2 BuildFATITEST Requirements, Conceptual Design ITESTOS FAT Forward Markets GO/NO GO Single Entry Model GO LIVE Q Operations UI

Lead from the front Texas Nodal 4 Scenario #3 – Release 2 & 3 combined & slack removed (Nodal Market live & Zonal Market Shutdown January 2009) EMS Early Delivery Systems MMS CRR MIS NMMS Commercial Systems ERCOT & MP Readiness Q2 2008Q3 2009Q4 2008Q3 2008Q2 2007Q1 2007Q4 2006Q4 2007Q3 2007Q1 2008Q3 2006Q Outage Scheduler EDW Q EDS 3 (TXMACS 0.3) SCED; MP SCED Offers EDS 4 TXMACS 0.4) with selected MPs MMS FATMMS SAT CRR Design, Build, Pre-FATCRR FATCRR SAT Final MP Interface Specs 3/31 NODAL GO LIVE MIS (EMS/MMS/CRR) Design, Build, Pre-FAT EDW FATEDW SAT Statements Layout Script test EMS SATEMSEMS FAT EMS Requirements, Conceptual Design MIS SAT MIS (SCED) Design, Build, Pre- FAT MIS FAT MMS Design, Build, Pre-FAT MMS Requirements, Conceptual Design OS SATOS BuildOS FAT OS Requirements, Conceptual Design CRR Requirements, Conceptual Design Commercial Systems Design, Build, Pre-FATCS FATCS SAT EDW Requirements, Conceptual Design SCED SATSCED BuildSCED FAT SCED Requirements, Conceptual Design Registration ready Business Requirements complete 10/30 Preliminary MP Interface Specs 12/31 CS Requirements, Conceptual Design EDW Design, Build, Pre-FAT MIS FATMIS SAT EDS 4 MP SAT TXMACS 1.0 Live operations OTS SAT OTS FAT EDS 3 Data Validation Qualification Freeze MP Registration complete 168 hour market trial End of Trials MP Nodal Registration MP Financial & Operational Qualification MPSCED Offers Begin MP trial participation Planning UI FAT ITEST Naming Convention DB Common model update process NMMS Conceptual Design Naming Convention information collection Model Data Certification Model Data Remediation Reconciliation NMMS Build Operations UI EDS 1/2 Single Entry Model GO LIVE

Lead from the front Texas Nodal 5 Scenario #4a – 3 incremental releases, timed for seasonality (Release 2 & Zonal Shutdown October ’08, Release 3 February ’09) EMS Trials & Implementation MMS CRR MIS NMMS Commercial Systems ERCOT & MP Readiness Q2 2008Q3 2009Q4 2008Q3 2008Q2 2007Q1 2007Q4 2006Q4 2007Q1 2008Q3 2006Q Integration EDW Q EDS 3 MMS FATITEST CRR Design, Build, Pre-FATCRR FATITEST Final MP Interface Specs 3/31 MP Registration complete 168 hour market trial Real Time Operations GO/NO GO Zonal Shutdown GO/NO GO MIS (EMS/MMS/CRR) Design, Build, Pre-FAT EDW FATITEST Statements Layout Script test End of Trials MP Nodal Registration & Qualification sequence ITESTEMSEMS FAT EMS Requirements, Conceptual Design ITEST MIS (SCED) Design, Build, Pre- FAT MIS FAT MMS Design, Build, Pre-FAT MMS Requirements, Conceptual Design ITEST OS Build FAT OS Requirements, Conceptual Design CRR Requirements, Conceptual Design Commercial Systems Design, Build, Pre-FATCS FATITEST EDW Requirements, Conceptual Design ITESTSCED BuildSCED FAT SCED Requirements, Conceptual Design Registration ready MPSCED Offers Business Requirements complete 10/30 Preliminary MP Interface Specs 12/31 CS Requirements, Conceptual Design EDW Design, Build, Pre-FAT MIS FATITEST Begin MP trial participation EDS 4 EDS 4 MP SAT OTS ITEST OTS FAT EDS 3 Data Validation Planning UI FAT ITEST Naming Convention DB Common model update process NMMS Conceptual Design Naming Convention information collection Model Data Certification Model Data Remediation Reconciliation NMMS Build Outage Scheduler EDS 1/2 BuildFATITEST Requirements, Conceptual Design ITESTOS FAT Forward Markets GO/NO GO Single Entry Model GO LIVE Q Operations UI

Lead from the front Texas Nodal /01/08 Scenario #4b – 3 incremental releases, timed after seasonal 2008 peak (Release 2 & Zonal Shutdown October ’08, Release 3 December 1, 2008) EMS Trials & Implementation MMS CRR MIS NMMS Commercial Systems ERCOT & MP Readiness Q2 2008Q3 2009Q4 2008Q3 2008Q2 2007Q1 2007Q4 2006Q4 2007Q1 2008Q3 2006Q Integration EDW Q EDS 3 MMS FATITEST CRR Design, Build, Pre-FATCRR FATITEST Final MP Interface Specs 3/31 MP Registration complete 168 hour market trial Real Time Operations GO/NO GO Zonal Shutdown GO/NO GO MIS (EMS/MMS/CRR) Design, Build, Pre-FAT EDW FATITEST Statements Layout Script test End of Trials MP Nodal Registration & Qualification sequence ITESTEMSEMS FAT EMS Requirements, Conceptual Design ITEST MIS (SCED) Design, Build, Pre- FAT MIS FAT MMS Design, Build, Pre-FAT MMS Requirements, Conceptual Design ITEST OS Build FAT OS Requirements, Conceptual Design CRR Requirements, Conceptual Design Commercial Systems Design, Build, Pre-FATCS FATITEST EDW Requirements, Conceptual Design ITESTSCED BuildSCED FAT SCED Requirements, Conceptual Design Registration ready MPSCED Offers Business Requirements complete 10/30 Preliminary MP Interface Specs 12/31 CS Requirements, Conceptual Design EDW Design, Build, Pre-FAT MIS FATITEST Begin MP trial participation EDS 4 EDS 4 MP SAT OTS ITEST OTS FAT EDS 3 Data Validation Planning UI FAT ITEST Naming Convention DB Common model update process NMMS Conceptual Design Naming Convention information collection Model Data Certification Model Data Remediation Reconciliation NMMS Build Outage Scheduler EDS 1/2 BuildFATITEST Requirements, Conceptual Design ITESTOS FAT Forward Markets GO/NO GO Single Entry Model GO LIVE Q Operations UI

Lead from the front Texas Nodal 7 Scenario Summary DAM/REAL-TIME/RUC IMPLEMENTATION & ZONAL SHUTDOWN JULY 1, 2009 –Scenario #1 – single release (baseline) (Nodal Market live & Zonal Market Shutdown July 2009) REAL-TIME/RUC IMPLEMENTATION & ZONAL SHUTDOWN JULY 1, 2008 FOLLOWED BY DAM IMPLEMENTATION JANUARY 1, 2009 –Scenario #2 – 3 incremental releases & slack removed (Release 2 & Zonal Shutdown July ’08, Release 3 January ’09) DAM/REAL-TIME/RUC IMPLEMENTATION & ZONAL SHUTDOWN JAN 1, 2009 –Scenario #3 – Release 2 & 3 combined & slack removed (Nodal Market live & Zonal Market Shutdown January 2009) REAL-TIME/RUC IMPLEMENTATION & ZONAL SHUTDOWN OCTOBER 1, 2008 FOLLOWED BY DAM IMPLEMENTATION FEB 1, 2009 –Scenario #4a – 3 incremental releases, timed for seasonality (Release 2 & Zonal Shutdown October ’08, Release 3 February ’09) REAL-TIME/RUC IMPLEMENTATION & ZONAL SHUTDOWN OCTOBER 1, 2008 FOLLOWED BY DAM IMPLEMENTATION DEC 1, 2008 –Scenario #4b – 3 incremental releases, timed after seasonal 2008 peak (Release 2 & Zonal Shutdown October ’08, Release 3 December 1, 2008)