Lead from the front Texas Nodal 1 Single-Entry Model Milestone Status Report May 1, 2008.

Similar presentations


Presentation on theme: "Lead from the front Texas Nodal 1 Single-Entry Model Milestone Status Report May 1, 2008."— Presentation transcript:

1 Lead from the front Texas Nodal http://nodal.ercot.com 1 Single-Entry Model Milestone Status Report May 1, 2008

2 Lead from the front Texas Nodal http://nodal.ercot.com 2 ERCOT Anti-Trust Admonition ERCOT strictly prohibits Market Participants and their employees who are participating in ERCOT activities from using their participation in ERCOT activities as a forum for engaging in practices or communications that violate the antitrust laws. The ERCOT Board has approved guidelines for members of ERCOT Committees, Subcommittees and Working Groups to be reviewed and followed by each Market Participant attending ERCOT meetings. If you have not received a copy of these Guidelines, copies are available at the Client Relations desk. Please remember your ongoing obligation to comply with all applicable laws, including the antitrust laws.

3 Lead from the front Texas Nodal http://nodal.ercot.com 3 Agenda –Single Entry Go Live definition and criteria –Single Entry Model applicable protocols and Section 21 governance –NMMS tool deployment benefits –ERCOT NMMS current status –Scorecard –Next Steps –Q&A

4 Lead from the front Texas Nodal http://nodal.ercot.com 4 3 The focus of this status report is on the following area…. For Single Entry model Go Live we are focusing on NMMS the tool, NOMCR capability, and the EMS CIM importer 1234

5 Lead from the front Texas Nodal http://nodal.ercot.com 5 What is Single Entry Model Go Live? The ERCOT NMMS tool is deployed to production. TSPs will use the ERCOT NOMCR process to submit network model changes to ERCOT. TSPs will no longer submit Service Requests for zonal network model changes (unless agreed to with ERCOT Network Modeling Group). ERCOT will enter NOMCR-submitted changes from TSPs into zonal Genesys modeling system (ERCOT dual entry). QSEs w/resources will continue to submit RARFs; ERCOT will submit NOMCRs on their behalf. ERCOT will generate and maintain the NMMS ERCOT CIM model.

6 Lead from the front Texas Nodal http://nodal.ercot.com 6 Single Entry Model is Not… Confirming that all nodal systems (EMS, MMS, OS, etc) are interpreting CIM data correctly and results are consistent –This will be an iterative process performed after Single Entry Model Go Live and before the 168-hour test. Does NOT enable TSPs to use the ERCOT planning model change requests –Planned as a future ERCOT NMMS release, coordinated with TSPs

7 Lead from the front Texas Nodal http://nodal.ercot.com 7 Moving forward with Section 21 as governance… Protocol 21.12.3Notice to Market Participants of Effective Date for Nodal Protocol Provisions and Retirement of Zonal Protocol Provision No part of the nodal market design may start operation until all the Market Readiness Criteria for that part of the nodal market design have been met. Certification that all Market Readiness Criteria have been met must be made at least by each of the following: the Transition Plan Task Force (TPTF), TAC, ERCOT Staff and the ERCOT Board. Upon such certification, ERCOT shall issue two Notices alerting Market Participants to the effective date of Nodal Protocol sections and the retirement of Zonal Protocol sections, as applicable. ERCOT shall issue the first Notice no less than thirty (30) days prior to the effective date or retirement date, as applicable, and the second Notice no less than ten (10) days prior to the effective date or retirement date, as applicable. The Notice shall include: (1)The Nodal Protocol Sections to become effective and (2)The Zonal Protocol Sections to be retired, if any.

8 Lead from the front Texas Nodal http://nodal.ercot.com 8 Single Entry Model Go Live Entrance Criteria  Complete and Consistent Nodal Model –Ability to import NMMS ERCOT CIM and successfully execute EMS applications –Database/application result comparison between zonal network model and nodal network model  NMMS Market Trials Completed  NMMS Sev 1 and Sev 2 Defects Resolved  NMMS Certification Approval –Internal & External Staff Approval Transition Plan Task Force (TPTF) TAC ERCOT Staff ERCOT Board –Issue Market Notices (30 day, 10 day)

9 Lead from the front Texas Nodal http://nodal.ercot.com 9 ERCOT’s plan to move forward… Based on the Section 21, ERCOT is not ready to move forward with the related Nodal Protocol The Nodal protocols associated with Single Entry Model Go Live are: –3.10 Network Operations Modeling and Telemetry –3.8 Special Considerations for Split Generation Meters (NOMCRs) –3.7 Resource Parameters (NOMCRs) –3.5.2 Hub Definitions (NOMCRs) –3.3.2.1 Information to Be Provided to ERCOT (NOMCRs) ERCOT is planning to move towards using the tool, and then initiating the certification approval process –NMMS tool deployment for June (assuming issues are corrected)

10 Lead from the front Texas Nodal http://nodal.ercot.com 10 What this means to you…. ERCOT is not planning to put any Nodal Protocols Live on June 2 nd ERCOT will only start enforcing the Nodal Protocols after Certification votes as per Section 21 Once ERCOT Nodal Protocols are Live –TSPs and QSE w/resources will need to start following the Nodal timelines for the Network Model changes –ERCOT will start posting the Network Model and approved changes –Realization of all the benefits listed earlier Logistically, it means that we are in “production” with our first Nodal solution

11 Lead from the front Texas Nodal http://nodal.ercot.com 11 Benefits to TSPS & QSEs Establishes the NMMS single-entry process to submit changes to the nodal market several months prior to Nodal December 1 st Go Live Enables TSPs to validate internal processes and procedures prior to Nodal December 1 st Go Live Provides TSPs with the opportunity to establish consistency between internal models and the ERCOT nodal model Provides TSPs and QSEs with visibility of the nodal model and the associated changes

12 Lead from the front Texas Nodal http://nodal.ercot.com 12 ERCOT Current Status – NMMS Product Defect Resolution Summary of Open Issues –ERCOT NMMS completed FAT for NMMS 3 on April 30th, 2008. –Of the Sev 1 and Sev 2 defects documented to date, all but 2 are expected to be resolved with the April 29th NMMS Patch Performance issues expected to be tested on May 1 st, and if successful the defect will be closed TNA / SAS 70 defect expected to be resolved with June patch, and not critical for Single Entry Model Go Live From ERCOT Quality Center

13 Lead from the front Texas Nodal http://nodal.ercot.com 13 ERCOT Current Status – NMMS Integration NMMS Initial Load From EMS in CIM/XML MPs (NOMCR, PMCR, SAMR) – CIM/XML, RAWD, IDEV, PRJ, etc. ERCOT (NOMCR, PMCR, SAMR) – CIM/XML, IDEV, RAWD, PRJ, etc. Generation data – Registration Group in CIM XML Outages – Outage Records – MMS,EMS, OTS & OE – Network, SCADA, & Gen Model + ratings, contingency, settlement points, SPS/RAP/MAP, etc. CIM XML MIS Web Site – Full Model + Incremental changes – CIM/XML OS - List of Equip + topology to 2 nd Tier XML CRR – Bus-Branch Model + Settlement Points, oContingency, o Outages, Ratings – RAWD SPS/RAP/MA P, etc. - Word Doc Planning – Bus-Branch Model – RAWD SPS/RAP/M AP, etc. Word Doc LodeStar, Data Aggregation & Settlements – substation data, EPS, ESID, Settlement Points, Model Data – CIM XML -> XML ICCP – Measurement Data – CIM XML May be converted to CSV after Export MP Notifications – Email messages Legend: Green=Complete

14 Lead from the front Texas Nodal http://nodal.ercot.com 14 ERCOT Current Status – NMMS Integration A number of NMMS Interfaces, both input and output, are complete, subject to validation testing –Capability to provide Model to EMS/MMS –Capability to produce full, incremental, CIM/XML files for MIS posting –Capability to provide the equipment list to OS –Capability to provide a Settlements and Billing Profile –Capability to provide Planning PSS/E models Interfaces In Progress –Generation Registration data (RARF) – in progress –Outages back to NMMS for CRR/Planning – in progress –ICCP – may be converted to CSV after Export for ICCP application population –MP Notifications – Email messages, in progress –Capability to create a augmented PSS/E file for CRR, in progress

15 Lead from the front Texas Nodal http://nodal.ercot.com 15 ERCOT Current Status – NMMS Business Processes Business Processes have been defined for –Generate, Post, and Distribute Models and Files –Conduct NOMCR Validation –Respond to Model Changes and Interim Updates Documentation of all 3 Procedures is on track for a June 1st delivery Process Diagrams documented –State Diagram - Market Trials NMMS EDS2 Training Exercises –Model and manage the power system data –Test connectivity with new market participant –Conduct NOMCR validation –Generate, post and distribute models and files –Respond to model changes & interim updates –Conduct Level 2 validation –Conduct Level 3-5 validation

16 Lead from the front Texas Nodal http://nodal.ercot.com 16 ERCOT Current Status – NMMS Business Processes State Diagram - Market Trials NMMS EDS2 Training Exercises

17 Lead from the front Texas Nodal http://nodal.ercot.com 17 ERCOT Current Status – NMMS Business Processes Level 3 Validation

18 Lead from the front Texas Nodal http://nodal.ercot.com 18 ERCOT Current Status – NMMS Business Processes Level 3 Validation

19 Lead from the front Texas Nodal http://nodal.ercot.com 19 ERCOT Current Status – NMMS Market Trials Number of TSP Companies Number of Participants EDS Training days @ ERCOT EDS Testing days @TSP Site 228323 EDS2 Release 4 Market Trials involved TSP training on the NMMS system. Completion of this training enabled the TSPs to review the model, make changes as needed and complete model validation as required by the Nodal Transition Plan. Scripts included: –Generate, Post, and Distribute Models and Files –Change Request Submissions –Status Changes –Additional Features –Downloading Change Files Updates to the Market Trial scripts were driven by feedback by participants. This training is scheduled to complete on May 20th.

20 Lead from the front Texas Nodal http://nodal.ercot.com 20 ERCOT Current Status – NMMS Training Training TypeNumber of Participants PassedCompletedIncompleteFailed Instructor Led21410910401 Web-Based19213727262 The Network Model Management course is an 8-hour one-day course covering the operation of the ERCOT Network Model Management System (NMMS) and the associated processes. Topics include the processes, procedures and activities that provide the necessary safeguards in modeling the ERCOT system. To date, the instructor led course has been delivered to 214 attendees. The next course is scheduled for May 21. The market share status of training is “Yellow” based on the fact that QSE’s with Resources and TSPs completing the course.

21 Lead from the front Texas Nodal http://nodal.ercot.com 21 ERCOT Current Status – NMMS Staffing The NMMS project team consists largely of ERCOT “home team” staff (only 1 consultant) which are involved in development, testing, and training. Therefore this is the same team that will be the business owners of Single Entry Go Live, future CIM testing, and other activities in preparation of the Nodal Market December 1 st Go Live. EMMS Production Support has been engaged in set up of the HW/SW and product releases. Business has hired or has outstanding offers for all open positions IT is working to fill any open position.

22 Lead from the front Texas Nodal http://nodal.ercot.com 22 ERCOT Current Status – NMMS Artifacts Work Products/Documents:Status Business Requirements SpecificationComplete CharterComplete Use Case Model SurveyComplete Supplementary SpecificationsComplete Use Case SpecificationComplete Technical ArchitectureComplete Conceptual System DesignComplete  Software Architecture DocComplete  Data ModelComplete  Data Migration SpecificationComplete Architectural Proof of ConceptComplete User Interface PrototypeComplete Standard Interfaces DocumentPlanned May 2008 Work Products/Documents:Status Migration Control DocumentCompleted with each release Code Review ChecklistComplete to date Unit Test and LogPlanned April 2008 Test PlanPlanned May 2008 Test CaseIn ReqPro Test ScriptQuality Center System Monitoring DocumentPlanned April 2008 Operational GuideProvided by Siemens Maintenance GuideProvided by Siemens User GuideProvided by Siemens Training PlanComplete Training MaterialComplete Transition PlanComplete to date Key project documents are either complete or on track to complete in a timely manner

23 Lead from the front Texas Nodal http://nodal.ercot.com 23 ERCOT Current Status – Data Dictionary – The Data Dictionary is distributed via email to all vendors and MPs that are interested. – The current Data Dictionary version is 1.11 – Additional versions are expected, based on the data requirements of the CIM importers. – The Go Live plan allows for subsequent versions, and the implemented version for Single Entry Model will be posted for MPs

24 Lead from the front Texas Nodal http://nodal.ercot.com 24 Outstanding Issues – NMMS Performance ERCOT with Siemens identified a SEV1 performance issue with the NMMS product –With the new NMMS security model (through Citrix) we are only able to get 4 concurrent users on at the same time What has ERCOT and Siemens done…. –ERCOT has reproduced the issue for Siemens –Siemens has been investigating the issue on the product –ERCOT discovered a Citrix patch that applied to the specific performance situation –ERCOT applied the patch and has successfully tested with 12 users (limit of current team) –ERCOT has set up a large performance test on May 1 st, and depending on the results will determine next steps

25 Lead from the front Texas Nodal http://nodal.ercot.com 25 Outstanding Issues – EMS Importer Current status –EMS importer Pre-FAT is in progress at ERCOT –Addressing Defects (from Pre-FAT starting 4/14) and missing data Currently projected to complete Pre-FAT by 5/30 (plan and schedule are being finalized)

26 Lead from the front Texas Nodal http://nodal.ercot.com 26 SCADA Dynamic Ratings ICCP Network Generation ERCOT CIM Importer Status 4/30 CIM File Importer CIM Based Data Repository Model Workspace Netmom Exporter SCADAmom Exporter Genmom Exporter DynRatings Exporter OAGmom Exporter RASmom Exporter CTGSmom Exporter Graphic Modeler User Interface Complete With minor issues SPRs Not Tested Netmom DB CTGSmom DB Network Model SCADA Model Generation Model Dynamic Limits Model OAG Model RAS Model CTGS Model Retesting SCADAmom DB Genmom DB DynRatings DB OAGmom DB RASmom DB NMMS CIM Importer Tool Validation Apps Legend

27 Lead from the front Texas Nodal http://nodal.ercot.com 27 Scorecard Nodal Model Consistency EMS Importer populates Nodal EMS CIM Schema Frozen Market Trials / Training Defect Resolution Business Processes Protocols/Traceability Artifacts Overall Assessment & Recommendation Go Live Scorecard Background Data Market Trials / Training EDS2 Release 4 TSP training Defects Resolution (Apr 28 patch) ERCOT Business Proc Traceability (PMO/Project) =GNMMS TrendTrend This week Project Importer / CIM Model Freeze Nodal Model Validation / Data Dictionary

28 Lead from the front Texas Nodal http://nodal.ercot.com 28 Next Steps Red/Yellow Items: ERCOT is planning to work with AREVA and the EMS team on the CIM importer schedule and associated schema and data issues –Schedule will drive delivery date of Single Entry Model Go Live Yellow Item: ERCOT will continue to work with Siemens on additional functionality and any new defects Yellow Item: ERCOT is requesting feedback on how to improve participant attendance in market training ERCOT will continue to build the production environment and operation procedures to be ready when the overall assessment supports moving forward –HW set up on redundant sites for application and citrix servers –SW set up for replication –Help desk / Openview monitoring set up –Operation procedures being written –NMMS sandbox available for TSP testing TSPs will continue to “practice” using the NMMS in the sandbox environment. Based on the outcome of today’s meeting, ERCOT will send out a market notice stating that we will NOT move forward with Single Entry Model Go Live

29 Lead from the front Texas Nodal http://nodal.ercot.com 29 Q&A / Open Forum


Download ppt "Lead from the front Texas Nodal 1 Single-Entry Model Milestone Status Report May 1, 2008."