VILLAGE OF PATCH, NM, FEASIBILITY STUDY Village of Patch Case Study Seattle Environmen tal Planning Class June, 2009 US Army Corps of Engineers Albuquerque.

Slides:



Advertisements
Similar presentations
US Army Corps of Engineers BUILDING STRONG and Taking Care of People! Ecosystem Restoration Along the Los Angeles River: Creativity within Concrete Dan.
Advertisements

FDR1 - 1 Flood Risk management History/Mission/Policies.
Chattahoochee River Restoration Aquatic Ecosystem Restoration City Mills Dam Eagle and Phenix Dam.
John H. Kerr Dam and Reservoir John H. Kerr Dam and Reservoir U.S. Army Corps of Engineers Wilmington District.
Watershed Dams in Georgia 1. –357 Total –195 High Hazard (NRCS) –NRCS constructed – owned by local sponsors –Most built between 1950s-1970s for flood.
HATCH, NM, Background Information Village of Hatch Case Study.
Carson City Freeway Paul M. Frost, P.E. Principal Hydraulic Engineer Nevada Department of Transportation Mark E. Forest, P.E. Executive Vice-President.
South Side Red River Bridge Corridor Study Phase III Preliminary Geotechnical Study Phase IV New Alignment Alternatives Evaluation.
1 FEMA Flood Insurance Rate Map Update FEMA Public Meeting October 22, 2009.
CHARACTERISTICS OF RUNOFF
US Army Corps of Engineers BUILDING STRONG ® Skiatook Lake Drought Issues and Management.
OKLAHOMA STATE UNIVERSITY Biosystems and Agricultural Engineering Department Hydrology 101 OKLAHOMA STATE UNIVERSITY Biosystems and Agricultural Engineering.
Rivanna Water & Sewer Authority Community Water Supply Mitigation Plan Public Meeting November 2, 2006.
Northeast Corridor Greenway Acquisition – Mitigation Feasibility Study Results City Council Workshop June 24, 2014.
Welcome Rob Rash CEO/Chief Engineer St
Watershed and its divide What’s the situation at points A and B in terms of: a. gradient b. stream velocity c. erosive power? Headwaters.
Kansas City Industrial Council Hydrology and Hydraulics
Overview of Watershed Systems
One Team Destined For Greatness US Army Corps of Engineers BUILDING STRONG ® Operations Division Mark Yuska Chief, Operations Division.
THE MISSISSIPPI RIVER. General facts: Third largest drainage basin in the World The Mississippi drains 1/3 of USA and a small part of Canada. Second longest.
Year 7 Revision May MAPSKILLS 2.8 Ordnance Survey maps.
Comprehensive Basinwide Protection Recommendations 13 Primary Principals: 1.Serve as framework moving forward 2.Establish acceptable levels of protection.
US Army Corps of Engineers BUILDING STRONG ® Kansas Citys, Missouri and Kansas Flood Risk Management Project Presentation to Kansas City Industrial Council.
 Prepared for  City of Palm Coast, Florida  June 24, 2014 Drummond Property Acquisition in Connection With The Land Donation of 70 Laramie Drive From.
Upper Brushy Creek Water Control & Improvement District
Henning Roedel Civil and Environmental Engineering Department Stanford University November 25, 2008.
Exeter 8/12/00.
Rush River Assessment Project Hydrologic Flow Study Sibley County SWCD Presentation to the Minnesota River Research Forum March 10, 2005.
Why Should New Mexico Dam Owners Care about Climate Change and Extreme Events Dagmar Llewellyn, Reclamation Albuquerque Area Office Presentation to the.
Flooding New Orleans, Aug Flooding –Varies with intensity and amount of rainfall –Perhaps the most universally experienced natural hazard Flood.
Engineering History and 2008 Operation of the Bonnet Carré Spillway: A Controlled Levee Crevasse on the Lower Mississippi River Christopher G. Brantley,
Hydraulic and Hydrologic Considerations in Planning Course FLOOD RISK MANAGEMENT Chuck Shadie Mississippi Valley Division.
Chapter 33 Dam Construction. Objectives After reading the chapter and reviewing the materials presented the students will be able to: Give reasons why.
Surface Water Chapter 9. Water Cycle Also the hydrologic cycle Driving force is the sun Review: condensation, precipitation, transpiration, evaporation,
200+ Years of Global Dam Development Each point on the globe represents one of 6,000+ dams built from Dams impact the hydrological cycle and.
Peabody Coal Lower Basin Pipeline Engineering Appraisal Study Bureau of Reclamation September 18, 2002.
Riverside County Flood Control and Water Conservation District Murrieta Creek Flood Control, Environmental Restoration and Recreation Project June 2006.
BASIN and RIVER SYSTEMS Divide Dam at Lake TravisDEM of Trinity River.
Rivanna Water & Sewer Authority Community Water Supply Mitigation Plan Public Meeting November 2, 2006.
Roseau River Flood Damage Reduction Project Roseau, Minnesota.
Otter Creek Watershed Meeting January 19, 2008 Mike Dreischmeier Agricultural Engineer Natural Resources Conservation Service.
Surface Water Supplies Joe Zulovich Extension Agricultural Engineer Commercial Agriculture Program.
US Army Corps of Engineers BUILDING STRONG ® Boise River Feasibility Study Ellen Berggren, PMP Outreach Coordinator/ Project Manager Idaho Governor’s Roadless.
Population - 44,301 18% - Aged 65+ Household Median Income- $29,530 Jan.-March 2004 unemployment 14 % Demographics.
Establishing the Scientific Basis for Ecosystem Management On the Upper Mississippi River Dr. Ken Lubinski, USGS Upper Midwest Environmental Sciences Center.
1 Lake Ballinger and McAleer Creek Watershed Strategic Action Plan Forum Briefing #2 January 27, 2009.
Sediment Management in Prado Basin and Lower Santa Ana River Greg Woodside, P.G., C.Hg Executive Director of Planning & Natural Resources September 20,
A Sediment Budget for Two Reaches of Alameda Creek (1900s through 2006) Paul Bigelow, Sarah Pearce, Lester McKee, and Alicia Gilbreath.
FLOOD CONTROL. AMAFCA The Albuquerque Metropolitan Arroyo Flood Control Authority (AMAFCA) was created in 1963 by the New Mexico Legislature with specific.
STREAM STABILITY STUDY FOR PIPELINES IN HIGH CONSEQUENCE AREAS By: Larry Blair, PE Eastern Sandoval County Arroyo Flood Control Authority (ESCAFCA) Sandoval.
Public Meeting April 2, 2015 Albany Park Stormwater Diversion Tunnel.
Rio Grande Rectification Reach FLO-2D Model Development Presentation to: New Mexico – Texas Water Commission and Paso del Norte Watershed Council Project.
FLO-2D Model Development Below Caballo Dam to Ft. Quitman Prepared by: U.S. Army Corps of Engineers Albuquerque District and Mussetter Engineering, Inc.
Ruttinger & Sons Engineering Designed by: Taylor Kasperick Jacob Wilson Loren Ruttinger Presented by: Loren Ruttinger.
 Beginning in the late 1980’s significant loss of forest cover and channelization in the area of Block 72, lead to increased total and peak flows being.
Reclamation and Hoover Dam It’s All About The Water.
Preliminary Engineering Analysis and Design Foxcroft Colony and Mosby Woods Condominiums Prepared for: City Council Work Session November 3, 2015.
US Army Corps of Engineers BUILDING STRONG ® Miles City, Montana Section 205 Gwyn M. Jarrett - Project Manager Omaha District April 27, 2016.
Watersheds and River Basins
Regional to Engineering Scale HUC8 HUC12 Catchment Engineering Hydrology Engineering Hydraulics Personal – a flooded home.
City Council March 4, Introduction The UCRA recommends the development of a storm water storage basin just to the east of FM 1223, south of Avenue.
Savannah River Projects
Cristina Nelson, Term Project, CEE 6440, Fall 2007
Why do people try to manage rivers?.
Babcock Basin-Design Phase
flooding and housing buyouts in onion creek
Ch. 1 Review Game.
Ch. 1 Review Game.
Sacramento Environmental Commission January 2019.
Presentation transcript:

VILLAGE OF PATCH, NM, FEASIBILITY STUDY Village of Patch Case Study Seattle Environmen tal Planning Class June, 2009 US Army Corps of Engineers Albuquerque District 1 HO #s 2 & 2a Ch 1 Module 2 Patch,

Study Authority Authority “ The Secretary of the Army is hereby authorized directed to cause surveys for flood control and allied purposes, including channel and major drainage improvements to be made under the direction of the Chief of Engineers, in drainage areas of the United States and its territorial possessions, which include the localities specifically named in this section” … Patch, NM 2

VILLAGE OF PATCH, NM, FEASIBILITY STUDY US Army Corps of Engineers Albuquerque District The study is located in Patch, NM. The purpose of the feasibility study is to determine Federal interest and optimize a flood damage reduction/ecosystem restoration plan for the city of Patch. Structures and roadways have been impacted by flows from the surrounding mountains, significantly flooding the community twice in the last 15 years. Flooding originates from two sources- Spring Canyon and Placitas Arroyo. Initial investigations determined that there is a likely Federal interest in constructing flood control projects in the area, the most probable alternatives being a small dam at Spring Canyon. Repeated flooding limits fishery populations. Regional Setting 3

Drainage Area VILLAGE OF PATCH, NM, FEASIBILITY STUDY US Army Corps of Engineers Albuquerque District 4 Patch, New Mexico

Floodplains VILLAGE OF PATCH, NM, FEASIBILITY STUDY US Army Corps of Engineers Albuquerque District 5 P atch

Flood History: The Village of Patch experienced significant Flood events in 1988, 2002 and FEMA and Corps’ analyses determined Spring Canyon is a flood threat to the Village of Hatch. The entire Village of Patch lies within a 100-year Floodplain VILLAGE OF PATCH, NM, FEASIBILITY STUDY US Army Corps of Engineers Albuquerque District 6

Flood Potential: Spring Canyon channel capacity is 1,300 CFX (100- year flow is-1% chance event-estimated at 2,600 CFS) Estimated average annualized flood damages of $10.1 million from Spring Canyon VILLAGE OF PATCH, NM, FEASIBILITY STUDY US Army Corps of Engineers Albuquerque District 7

8

Existing and Likely Future Without-Project Conditions Physical Setting 17.2 square mile watershed draining from the south flowing north into the Rio Grande An upstream detention structure controls 15.4 square miles of the basin Elevation in the drainage drops from 6,000 ft to 4,030 ft Flooding events in 1988, 1992 and 2006 left three feet of water in the street VILLAGE OF PATCH, NM, FEASIBILITY STUDY US Army Corps of Engineers Albuquerque District 9

Existing and Likely Future Without-Project Conditions Physical Setting (continued) Once flows enter the village there is no clear drainage pathway into the Rio Grande; floodwaters remain in place until evaporated. The Village storm drainage system is sized for a 5-year event. Sediment renders the system largely inoperable during larger events VILLAGE OF PATCH, NM, FEASIBILITY STUDY US Army Corps of Engineers Albuquerque District 10

Existing and Likely Future Without-Project Conditions Social and Economic Conditions 2004 population of 10, single residential structures within the 1% event floodplain 187 commercial structures within the 1% event floodplain 127 public structures within the 1% event floodplain 10 apartment within the 1% event floodplain VILLAGE OF PATCH, NM, FEASIBILITY STUDY US Army Corps of Engineers Albuquerque District 11

Existing and Likely Future Without-Project Conditions Social and Economic Conditions (continued) Median income for a household: $21,200 Many seasonal inhabitants “Chile capitol of the world” 172 homes with flood insurance VILLAGE OF PATCH, NM, FEASIBILITY STUDY US Army Corps of Engineers Albuquerque District 12

More Information Non-damaging Channel Capacity 10,300 cubic feet per second (cfs) 100-year flow 20,600 cfs Flood Damages Estimated average annualized flood damages $10.1 Mil Federal Disaster Area in 2006 VILLAGE OF PATCH, NM, FEASIBILITY STUDY US Army Corps of Engineers Albuquerque District 13

More Information Biological Communities Southern cottonwood- willow riparian forest occurs in Spring Creek Watershed. Salt Cedar dominates Placitas Arroyo. The forest provides canopy cover needed for sensitive nesting birds. VILLAGE OF PATCH, NM, FEASIBILITY STUDY US Army Corps of Engineers Albuquerque District 14

More Information Other Environmental Issues 10 lower-income apartment complex occurs in close proximity to the channel confluence of Spring Creek & Placitas Arroyo. New Mexico's Air Quality reviews imply that the high ozone levels in the northwest and southern parts of the state are part of a regional problem. VILLAGE OF PATCH, NM, FEASIBILITY STUDY US Army Corps of Engineers Albuquerque District 15

VILLAGE OF PATCH, NM, FEASIBILITY STUDY CULTURAL RESOURCES –During a site visit, black-on-white pottery fragments, burnt plant remains and long bones were observed eroding out of the river banks some 10 feet below the current floodplain. –Another 2 feet below, a hard clay band was observed in the river bank profile in Placitas Arroyo. 16

Plans Studied in Detail No Action Plan Non-Structural (Flood Warning) Channel Improvements Flood Detention oUpper Basin Structure oLower Basin Structure VILLAGE OF PATCH, NM, FEASIBILITY STUDY US Army Corps of Engineers Albuquerque District 17

Project Alternatives No Action Plan Non-Structural (flood warning) Non-Structural (raising/flood walls) Non-Structural (buyouts/relocation) Channel Improvements Flood Detention oUpper Basin Structure oLower Basin Structure VILLAGE OF PATCH, NM, FEASIBILITY STUDY US Army Corps of Engineers Albuquerque District 18

Impact Comparison of Alternative Plans Resource AreaNo ActionNon Structural NED DamChannel Improvements Land Use FarmlandNo Change to the Existing Condition Some Change to the Existing Condition Minimal impact to agricultural land use due to location of structure. High; Project located along agricultural lands. TransportationExisting ConditionMinor ImpactTemporary during Construction High; numerous road crossings and reroutes. NoiseExisting Condition Temporary Air QualityExisting Condition Temporary Water QualityExisting ConditionImprovedTemporary Settling BasinExisting Condition Hydrologic changeHydrologic Change Vegetation/WildlifeExisting ConditionImprovedMinor ImpactHigh Cultural ResourcesExisting Condition Minor Impact Visual ResourcesExisting ConditionHighMinor ImpactHigh 19

Recommended Plan Locally Preferred Plan 100-yr (1% Event) Dam in Lower Basin Features of the Locally Preferred Plan include Earth fill Dam approximately 14,000 ft. in length Concrete spillway 200 ft. in length Height of approximately 20 ft. Outlet Conduit 300 Acre-Foot Sediment pool 151 Acre-Foot Water Storage pool VILLAGE OF PATCH, NM, FEASIBILITY STUDY US Army Corps of Engineers Albuquerque District 20

Patch 21