Organization Date Alaskan Way Viaduct & Seawall Replacement Program 4 th Quarter 2009 Progress Report Meeting December 9, 2009.

Slides:



Advertisements
Similar presentations
Replacement of the Queens Approach Bronx-Whitestone Bridge
Advertisements

TRB BRT Workshop July 22, 2008 ECTP Project Oversight Grantee Perspective.
I-4 Ultimate with Lanes Project Central Florida 1 May 21, 2013.
Orange County Transportation Authority Measure M2 M2020 Update and Select Project Highlights Orange County Business Council Infrastructure Committee December.
Congressional District Projects New CD-2 SH 392 Interchange at I-25: — Bridge replacement and widening, will also improve on/off ramps and frontage roads.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION South Cascade Drive/Miller Road (Formerly Route 219)/ Cattaraugus Creek Design-Build Project (PIN ,
Alternative Project Delivery Mechanisms The J. K. Spruce Experience Katherine Yates Assistant General Counsel.
Alternative Project Delivery
UPCOMING MTA CAPITAL CONSTRUCTION SOLICITATIONS
1 Salt Lake City Gateway Area Railroad Consolidation Project Grant G. Schultz, Ph.D., P.E., PTOE Assistant Professor Brigham Young University CE En 361.
New York State Department of Transportation
New York State Department of Transportation
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Route 110 over Route 27 Design-Build Project (PIN , D900027) Town of Babylon, Suffolk County Request.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Interstate 81 Bridges over Route 80 Design-Build Project (PIN , D900023) Town of Tully, Onondaga County.
New York State Department of Transportation
Public Works Contracting Marsha Reilly Office of Program Research House of Representatives recommended.
Page 1 MINISTRY OF TRANSPORTATION Cyrville Road Bridge Replacement at Highway 417 (Ottawa Queensway) Detail Design Study Group Work Project
Broadway Street Viaduct Improvement, Pre-Load Testing and Geotech Report Workshop Consultant Presentation Iowa DOT 2 nd April 2007.
Wyoming Infrastructure Authority Developing Electric Infrastructure for the Future of the West Energy Gateway Update Presented by Darrell T. Gerrard Vice.
Project Briefing Metropolitan Washington Council of Governments Transportation Policy Board Project Briefing Metropolitan Washington Council of Governments.
From Planning to Pouring: The Evolution of Safe Routes to School Julie Walcoff, Ohio DOT, Columbus, OH Alex Smith, Columbus Public Health, Columbus, OH.
I Larry Heil, FHWA October 15, 2003 Environmental Streamlining.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
Regional Transportation Investments: Alaskan Way Viaduct / Seawall Port of Seattle Commission Meeting March 28, 2006 Item No. xx Supp. Meeting.
TH 2 – Wilton Bridge Replacement Design-Build Project S.P March 5, 2009 Todd Vonasek, P.E. Mn/DOT Project Manager PROJECT INFORMATIONAL MEETING.
Arizona ACC Biennial Transmission Assessment Navajo Transmission Project Update May 22, 2008 Presentation by Ben Hoisington Project Administrator, DPA.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Region 9 Design-Build Project (PIN , D900020) Broome, Delaware,
1 Tower Road Project Update. 2 The Project Team requests the Alachua County Commission: Authorize staff to: Proceed with re-evaluating four (4) key issues.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Regions 2 & 9 Design-Build Project (PIN , D900022) Herkimer,
Planning and Community Development Department Housing Element City Council February 03, 2014.
Washington’s Water Use Efficiency Rule May Require Increased Coordination for Many Utilities Dan Sander, P.E. Senior Engineer.
Silver Line Phase 1 – Status Report Status Overall Phase 1 Construction – 99% complete All Station at 98% complete except Wiehle – Reston East at 99% complete.
METROPOLITAN TRANSPORTATION COMMISSION Key Steps to Delivering Project 1.Lead agency submits final project scope, budget and schedule to MTC 2.MTC.
Regional Transportation Investments: Alaskan Way Viaduct / Seawall Port of Seattle Commission Policy and Staff Briefing March 14, 2006 Item No. xx Supp.
Texas Department of Transportation Corpus Christi District Harbor Bridge Project U.S. 181 (Harbor Bridge)/SH 286 (Crosstown Expressway) Citizens Advisory.
Safe & Sound Bridge Improvement Program. Purpose of Meeting Introduction of Team Today’s discussion  History of Safe & Sound  DBFM to MDBB/DB split.
Regional Transportation Committee (RTC) 10-Year Project Milestone Policy Transportation and Trinity River Project Committee October 26, 2015.
Northeast Corridor Greenway Acquisition Project – Design and Permitting Status Update City Council Workshop August 25, 2015.
D.d. delivers district department of transportation d.d. delivers FAISAL HAMEED RONALDO T. NICHOLSON. P.E. Innovative Project Delivery Processes Innovative.
Regional Transportation Investments: Alaskan Way Viaduct / Seawall Port of Seattle Commission Meeting November 8, 2005?? Item No. xx Supp. Meeting Date:
Toll Bridge Seismic Retrofit Program Project Schedule and Budgets.
JOHNSON STREET BRIDGE PROJECT COUNCIL WORKSHOP MAY 21, 2009.
August 19, 2015 Port Bienville Rail EIS Scoping Meeting Presented by: Rhea Vincent Mike McGuire.
Texas Department of Transportation Corpus Christi District U.S. 181 (Harbor Bridge) Environmental Documentation and Schematic Development Citizens’ Advisory.
Parks & Recreation Service Delivery Model Review Progress Report #1 City of Pitt Meadows Council January 19,
1 © 2013 Protiviti Inc. All Rights Reserved. This document has been prepared for use by OOCEA’s management, audit committee, and board of directors. This.
AB 32 Update December 6, Outline Cap and Trade Program 2013 Update to Scoping Plan Looking ahead to
Washington Street Boat Landing Pergola Restoration Design-Build Project Design-Build RFQ – Pre-Submittal Meeting Jeff Lundstrom, SDOT Project Manager February.
Planning Commission Study Session: Preferred Plan July 23, 2015.
1 EASTERN MUNICIPAL WATER DISTRICT Temecula Valley Recycled Water Pipeline Joe Mouawad Sr. Director of Engineering September 2, 2015.
Wastewater Treatment Plant No. 2 Construction Contract City Council Workshop February 9, 2016.
Waterdown Road Corridor Class Environmental Assessment (Phase 3 & 4) Community Services Committee May 9, 2012.
December 17,  MnDOT signed a highway easment in 1960 with US Steel  The TH 53 is over a ore deposit with shallow strippings, high iron and low.
The purpose of the US 53 project is to address the termination of the 1960 easement agreement that affects the current highway location in order to continue.
Iron Range Tourism Bureau April 25, 2013 Hwy 53 Update.
2009 Sales Tax Extension Project Status Update. 2 Background Sales Tax was extended via August 26, 2008 referendum. Sales Tax was extended for an additional.
Technical Issues Design Status Due Diligence Materials Tony DeVito, Project Director Jan. 28, 2016 I-70 East Project.
Big Cypress Basin Capital Project Update Jeffrey Kivett, P.E., Director Operations, Engineering and Construction Division Jeffrey Kivett, P.E., Director.
County of Fairfax, Virginia Department of Transportation Update on Transportation Activities in Fairfax County Transportation Roundtable Dulles Area Transportation.
Alternative Alignments Public Meeting
Measure M2 Performance Assessment
Value Engineering Study and Risk Assessment
Center City Connector 101.
Manual on Accommodating Utilities in Pierce County Rights-of-Way
Bureau of engineering City of Los Angeles.
AX7665D82 Areawide Total Maximum Daily Load (TMDL) Design-Build
Green Line Extension Project
I Street Bridge Replacement Project
Brieana Reed-Harmel, Broadband Project Manager
Presentation transcript:

Organization Date Alaskan Way Viaduct & Seawall Replacement Program 4 th Quarter 2009 Progress Report Meeting December 9, 2009

Presentation Topics Program overview. S. Massachusetts to Union Electrical Line Relocation. S. Holgate to S. King Street Viaduct Replacement. Central Waterfront Replacement.  EIS.  Alignment.  RFP.

Program Overview Governor and Mayor signed a Memorandum of Agreement endorsing the bored tunnel in October. Electrical Line Relocation Project to be substantially complete in early December. Holgate-to-King design modifications: estimated $100 million in savings. Two SR 99 ITS contracts advertised in October; bids opened on one.

Program Overview Central Waterfront bored tunnel alternative:  CEVP + VE workshops results in new alignment option.  EIS schedule impacted by new alignment; requires aggressive approach to maintain schedule.  SOQ’s received from four teams; evaluations in progress. Estimate-at-Completion: recent CEVP and estimate results -  Bored Tunnel Alternative = $2,000 million.  Holgate-to-King =$ 443 million.  Other Moving Forward = $ 365 million.  TOTAL STATE =$2,808 million. Current Legislated Budget is $2.4 billion. Need $400 million in Toll Revenue Bond proceeds needed to deliver State scope.

Program Overview Schedule highlights:  Holgate-to-King:  New conformed bid set with re-design in February  Bid opening on March 24,  Bored Tunnel Alternative:  RFP draft complete: February  ROD in Spring 2010.

Electrical Line Relocations Recent Activities:  Transmission Circuit #1 was cut and distribution was turned over to SCL for splicing.  Transmission Circuit #2 testing/energization and Royal Brougham Way asphalt restoration was completed.  Demolition of old oil contained cable system from viaduct has been completed.  Distribution lines are being removed.  Facility has been turned back to SCL. WSDOT providing support to SCL to repair an oil leak vicinity University / Western.  Forecast to be substantially completed in early December.

Electrical Line Relocations Demolition of Existing Electrical Cables under Viaduct Emergency Oil Leak Location & Repair

Holgate-to-King Viaduct Replacement Recent Activities:  Stage 1 (Construction)  New bike and pedestrian path was opened to the public.  Completed 26kV duct bank from Station 2+25 to Station  Began contract work north of Royal Brougham Way  Stage 2 (Design).  UPRR and BNSF Whatcom Lead vacation agreements and the BNSF Railroad Construction & Maintenance agreement were finalized.  Contract advertised on October 26, 2009.

Holgate-to-King Viaduct Replacement Recent Activities:  Stage 2 (Continued)  November VE studies resulted in design change recommendations that would:  Remove retained cut undercrossing and associated bridges.  Replace undercrossing with an elevated structure that will for Port traffic to bypass the railroad crossing (a new Stage 3 contract).  Provide for detour through WOSCA, replacing the west side transition structure connection to the viaduct  Above design revisions result in EA re-evaluation to be completed before March 24, 2010 bid opening date.

Holgate-to-King Viaduct Replacement Challenges & Opportunities:  Reaching agreement on Railroad pre-emption at Atlantic Street with City and BNSF.  Completing Stage 2 design changes and not delay bid opening past March  Recent design changes result in estimated $100 million savings and reduced construction duration by an estimated six months.

S. Holgate to S. King Viaduct Replacement Previous Design Alaskan Way S./East Marginal Way S. connector

S. Holgate to S. King Viaduct Replacement Current Proposal

Holgate-to-King Viaduct Replacement 26kV Electrical Duct Bank between Ring Vaults 1 and 2 Setting Overhead Poles at Port of Seattle Terminal #46

Central Waterfront / Bored Tunnel Alternative EIS Recent Activities:  Held cooperating agency EIS review kickoff meetings with the Port of Seattle and King County.  Completed the first and second rounds of co-lead agency reviews of several discipline reports.  Developing a revised SDEIS schedule given recent changes to north and south portals. Upcoming Activities:  Continue development and co-lead review of SDEIS summary chapters, outline, and selected appendices.  In January, receive and utilize a revised EIS design snapshot.  Target for Record of Decision is Spring 2011.

Central Waterfront / Bored Tunnel Alternative EIS Challenges & Opportunities:  Meeting the aggressive EIS schedule relies heavily on quick reviews and issue resolution, close coordination with co-lead and cooperating agencies, and aggressive 106 and ESA consultations. Many items are on the critical path.

Central Waterfront / Bored Tunnel Alternative RFP Recent Activities:  Latest contracting strategy calls for tunnel bore to be design-build; all other packages will be design-bid-build.  Geotechnical investigation program will result in a Geotechnical Baseline Report. Key to risk management and will accompany the tunnel bore RFP.  Bored Tunnel Alternative draft RFP is in review, to include reviews conducted by the City of Seattle.  Issued a RFQ to which four teams have submitted SOQ’s

Central Waterfront / Bored Tunnel Alternative RFP Upcoming Activities:  Evaluate the four SOQ’s received in December; develop a short- list.  RFP schedule:  Draft RFP complete: February  Final RFP complete and issued: June  Proposals due to WSDOT: October  Award of the design-build contract: January 2011.

Central Waterfront / Bored Tunnel Alternative RFP Challenges & Opportunities:  Developing a final RFP for a design-build contract that will remain attractive to proposers.  Balance risk between WSDOT and proposers in a way that is in the best interest of the Department.

Central Waterfront / Bored Tunnel Alternative Alignment Recent Activities:  CEVP and VE workshops held to maximize efficiencies and reduce costs.  Selected a new alignment option (see diagram next page).  Initiating utility investigations along the new alignment option and addressing right-of-way and building settlement impacts.  New alignment in the north removes the need for construction of the detour for SR 99 and the temporary structure on Harrison Street over SR 99.  Developed south end Preliminary Construction Staging concepts, and updated identified tie-back, staging and acquisition areas.

Central Waterfront / Bored Tunnel Alternative Alignment

Upcoming Activities:  Conduct additional geotechnical investigations along the new alignment option.  Continue with utility relocations; determine right-of-way needs; assess building settlement risk and mitigation measures.  Document the new alignment option as the baseline against which to manage project delivery. Challenges & Opportunities: Complete the design snapshot reflecting the new alignment option so as not to impact the EIS and RFP schedules. Deliver the overall bored tunnel alternative to an aggressive schedule that opens to traffic in 2015.