1 Progress On The Design And Manufacture Of The New Stator Geoff Barber Imperial College.

Slides:



Advertisements
Similar presentations
MICE Magnetic Investigation of T2 MICE/ISIS Target Meeting 17 th September 2010 P J Smith – University of Sheffield.
Advertisements

MICE MICE Target Mechanism Paul Smith University of Sheffield 8 th June 2010 (Based upon talk given by Chris Booth at CM26)
E2 Motors and Motor Starting (Modified)
The MICE Target Lara Howlett University of Sheffield.
MICE TARGET HARDWARE C. Booth, P. Hodgson, R. Nicholson, P. J. Smith, Dept. of Physics & Astronomy University of Sheffield, England. 1 - The MICE Experiment.
Status of the LARP Phase II Secondary Collimator Prototype 30 September 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US.
Progress of the BEPCII Injection System Kang Wen.
MICE target stator: measurements & modelling Ben Shepherd MICE target workshop 13 May 2011.
Development of new Mice Target Stator. (or show and tell) Rutherford Lab 13 th December 2011.
Biot-Savart Law The Field Produced by a Straight Wire.
MICE Target Report Chris Booth (for target team) Sheffield 7 th May 2009.
MICE Target Schedule Chris Booth Sheffield 12 th June 2006.
Introduction to NSF SPIRIT Workshop 2006 DC ELECTRIC MOTORS.
G.Barber Tracker Update, Berkeley 10 Feb Tracker Progress Contents:- Station Space Frame Patch Panel / Vacuum Seal Light Guide Map Position of Degrader/Support.
Background to the current problem 1. As a result of the high stresses in the bobbin due to the magnet load, the bobbin end plate needs to be increased.
TARGET WORKSHOP – SHEFFIELD HALLAM UNIVERSITY Monday 2 March 2009 The ISIS – MICE interface Eddie McCarron Contents 1.Target alignment with ISIS beam centre.
Stator Plan & Schedule Chris Booth 2 nd March stators to construct for mid-April. One complete coil assembly recovered from ISIS drive. Coils recoverable.
Target: K. Long, 21Dec2009. Schedule for T2 re-instatement: T2#2: – Next steps: Non-DLC bearings: – Continuing delay in material delivery! » Vespel delivery.
Target: K. Long, 16Nov2009. Schedule for T2 re-instatement: T2#2: – Next steps: Non-DLC bearings: – Delay in material delivery: » Torlon delivery expected.
Current carrying wires 1820 Hans Christian Oersted Hans Christian Ørsted.
Target: K. Long, 16Nov2009. Schedule for T2 re-instatement: T2#2: – Next steps: Non-DLC bearings: – Continuing delay in material delivery! » Vespel and.
G.Barber 28 Oct Construction/Refurbishment Of The Tracker Prototype Contents:- Welcome Back Plans Layout Things to be addressed New Schematic.
G.Barber Mice Target Stator Field Mapping March Mice Target Stator Field Mapping G Barber, E Longhi, C MacWaters, P Smith, J Tarrant & Many others.
Status of the LARP Phase II Secondary Collimator Prototype 14 October 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC.
The printed circuit board (PCB) design
DC GENERATOR CHAPTER-9.
DC Motor Control Project Group A ALEXANDER M FUNK LAM D NGUYEN JAKEISHA D THOMPSON PAULETTE J VERNON ERIC G ZAISER 12/03/01.
EET 412 Electrical Machine Design Dina Maizana kukum.edu.my.
MICE Target Mechanical Design l Contents »Status of modelling and drawing »Work being undertaken at RAL on shaft and bearing prototypes »Procedure for.
Chapter 20 Induced Voltages and Inductance. Faraday’s Experiment – Set Up A current can be produced by a changing magnetic field First shown in an experiment.
Chapter 6 DC Machines EET103/4.
STFC Technology undulator manufacture and measurement James Rochford On behalf of the Helical collaboration.
ALICE Photo-Injector Ceramic Vacuum Joint Collaboration Daresbury Laboratory has pioneered the use of ‘bulk resistive’ ceramic for the high voltage insulator.
Induced Voltage and Inductance
Drilling a Double Cosine-Theta Coil Hunter Blanton, Spencer L. Kirn, Christopher Crawford University of Kentucky Abstract: A double cosine theta coil is.
1 Motors and Generators ©Dr. B. C. Paul More Fun with Flux Mechanically Rotated Shaft Slip Rings Wires with brush contacts to slip rings Electromagnetic.
G. Barber Sci-Fi Tracker Progress Ral 28 Oct Progress On The Design Of The Full Tracker Contents:- Recap of New Station Layout Version 2.5 Version.
Chapter 22 Electromagnetic Induction Magnetic Fields Produced by Currents The direction of the magnetic field due to a current-carrying wire can.
MICE Target Mechanical Design l Status of Target ref. Schedule »Drawings –Drawing list created (see next slide) includes inventory –Drawings being released.
Generators and Motors. Lightning Review Last lecture: 1.Induced voltages and induction Induced EMF Induced EMF Faraday’s law Faraday’s law Motional EMF.
Electric Machine Introduction
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July Mechanical Update for Tracker workshop Contents:- New Station Layout Light Guide.
A Presentation On Construction Of Turbo Generator
PASI OsC meeting 12th July 2012
G.Barber Mice Tracker Mechanical Progress Tracker Mechanical Progress Contents:- Station Space Frame Station Layout Light Guide Map Connectors Patch.
Main features of PETS tank J. Calero, D. Carrillo, J.L. Gutiérrez, E. Rodríguez, F. Toral CERN, 17/10/2007 (I will review the present status of the PETS.
INDUCTION MOTOR.
Chris Booth & Paul Smith Sheffield 16 th August 2007 MICE Target Installation.
Fundamentals of DC Electric Machinery
Engineering Design Process Selecting an idea – design and build Steps 3 and 4.
Internal Guide : Batch No : 4 Mrs.Punyavathi Madam
24 September 2012 Immanuel Gfall (HEPHY Vienna) SVD Status of Mechanics PXD-SVD Meeting Göttingen.
Chris Booth Sheffield 29th March 2006
Stator Plan & Schedule Chris Booth 2nd March 2009
Electric Motors and Generators
Single Phase Induction
MICE Target Mechanical Design
Chapter 6: DC & AC Machine
MICE Target Report Video Conference 29/11/07
Electric Machine Introduction
AC and DC motors.
Services Layout – Update
INDUCTION MOTOR.
Electrical Machine-I EE 2107 Dr. Md. Sherajul Islam
Induction Motor. Induction motor Main parts are Stator Rotor.
10-Nov Nov-18 converted to Mechanical Energy DC Motor Describe how a d.c. motor works: A current-carrying coil in a magnetic field experiences.
28-Feb Feb-19 converted to Mechanical Energy DC Motor Describe how a d.c. motor works: A current-carrying coil in a magnetic field experiences.
Electric Machine Design Course
Presentation transcript:

1 Progress On The Design And Manufacture Of The New Stator Geoff Barber Imperial College

Quick Background 2 Why are we developing a new Stator? When it was agreed to put a Mice target into ISIS one of the stipulations was that a second target was built and run ‘offline’ so that any potential threats to ISIS would be found before problems arose. As it happened the target in ISIS performed very well whilst the offline target had problems with wear to its bearings. The target was stripped down and inspected and it was discovered that the DLC was badly worn. The problem was tackled in 2 ways: One was to improve the materials used in the bearings and to rebuild using new materials The other was to try and discover what factors if any were adding to the wear in the bearings. The bearing material was changed to DLC on Vespel and after an ongoing development the bearings perform well.

Quick Background cont. 3 One of the spare units was then put through ‘inspection’. It was decided to Map the magnetic field of the stator coils. Initially this was carried out in the first instance by Emily Longhi of Diamond. She found that the Mechanical (bearing) axis and the Magnetic axis were not aligned. Unfortunately this was not quantified and due to the pressure of work from Diamond Emily was unable to continue with the work. Enter Ben Shepherd from Daresbury, Ben quantified the magnetic offset and it also turned out that it was not linear. To improve the performance of future targets a redesign of the coils was undertaken, the idea was to incorporate improvements to the magnetic axis alignment, cooling and overall performance. The following is where we are.....

Bobbin with Wire Slits 4 The design has the 24 coils wound onto a common ‘bobbin’ and this will hopefully address the misalignment problem. The design fits into the original body and flange (with 2 additional slots for cooling pipes). To help improve the performance the bore was reduced to decrease the gap between the inner bore of the coils and the permanent magnet. The number of turns on the coils has also been increased. This has been modelled by Ben to ensure we were not adding turns ‘beyond a useful radius’. It is now complete and out to manufacture. (AC Precision and Oxford Physics workshop)

Cooling Segment 5 The cooling was revisited and a new cooling jacket designed. This will hopefully make contact with the top outer radius of the coils. The flow of coolant has also been greatly increased. It is hoped that this will aid performance improvement as the cooler the coils run the less resistance and so more power can be fed in. The cooling jacket segments are being manufactured at Imperial College and will be vacuum brazed the tested.

Bobbin with Cooling Jacket Fitted 6

Power Distribution 7 The Power distribution to the 3 phases now takes place internally and is done using bus bars. These were to consist of heavy duty printed circuit boards fixed over the gap between the cooling jacket segments, however if the tails are left longer and soldered to each other as well as the track this will negate the need for a ‘high weight’ board. The tails from every third coil is soldered as shown above. The strange layout of the copper on the board is to reverse the polarity of each coil in a given phase.

QA 8 As the Bobbin-Cooling Jacket-Power distribution assembly are to be potted (more later) it is essential that there is a rigorous QA in place. This has not been fully developed yet but must include:- Testing for shorts between the winding and the bobbin body, this will need to be done at each coil to avoid risk to subsequently wound coils Testing for shorts in a coil i.e. winding to winding, a technique will need to be developed for this possibly using precise resistance measurement in the wire. Again this needs to be done at each coil. Good solder joints on the bus bars Test for shorts between coils and the cooling jacket when fitted There will be many more before the potting can be confidently undertaken and any suggestions will be welcome.

Assembly Fitted Into Potting Jig 9 Once the assembly has passed all the QA requirements it is to be potted. A potting jig has been designed and manufactured from PTFE

Stator Assembly (shown Minus Flange) 10 Once the assembly is potted and passed further QA it is to be installed into a modified version of the original body, this has 2 extra slots to accommodate the cooling pipes and welded into position. The completed assembly is then taken to Daresbury to be field mapped by Ben as the final QA.

Future Plans 11 The Bobbin bodies that we have had manufactured have stress relieved during the machining process and this has ‘dished’ the flanges. We have further ideas for reducing this effect that we would like to pursue. We can still use these bodies to investigate the production methods further. It is planned to wind a number if coils onto one of the bobbins and then to field map the unit. This could be either every 3 rd position (8 coils) or every other position (12 coils). This will give us valuable data as to the uniformity we can expect in the magnetic axis position from this production method. It will also act as a test piece for the assembly processes that will need to be carried out.