PRODUCTION AND OPERATIONS MANAGEMENT
Advertisements

 Projects are usually infrequent or one- time.  No two projects are the same.  Projects are usually fairly long.  Several months to many years  Involve.
3 - 1 Course Title: Production and Operations Management Course Code: MGT 362 Course Book: Operations Management 10 th Edition. By Jay Heizer & Barry Render.
2 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Project Management 2.
© 2004 by Prentice Hall, Inc., Upper Saddle River, N.J Operations Management Project Management Chapter 3 - Heizer.
© 2006 Prentice Hall, Inc.3 – 1 Operations Management Chapter 3 – Project Management Chapter 3 – Project Management © 2006 Prentice Hall, Inc. PowerPoint.
1 1 Slide © 2009 South-Western, a part of Cengage Learning Slides by John Loucks St. Edward’s University.
Project Development Scheduling and Probability of Completion.
Chapter 3 (Continued) Outline Recap CPM (continued)  Assign time estimates to each activity  Compute the longest time path through the network.
The Nature of Project Management zCharacteristics of Projects: purpose, life cycle, interdependencies, uniqueness, and conflict. zProject Management Process:
Project Management Chapter 13
Project Management Project management is a systemized approach to: ◦ defining, ◦ organizing ◦ planning ◦ monitoring ◦ controlling projects.
Managing Projects. Project Management Questions zWhat activities are required to complete a project and in what sequence? zWhen should each activity be.
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edward’s University.
Projects: Critical Paths Dr. Ron Lembke Operations Management.
© 2007 Pearson Education Project Management Chapter 3.
TECHNIQUES FOR PLANNING & MANAGING PROJECTS.
Project Scheduling Professor Stephen Lawrence Leeds School of Business University of Colorado Boulder, CO
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Project Management OPIM 310-Lecture.
Chapter 16 – Project Management
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 6 Project Management To Accompany.
© 2000 by Prentice-Hall Inc Russell/Taylor Oper Mgt 3/e Chapter 6 Project Management.
2 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Project Management Chapter 2.
Project Scheduling Professor Stephen Lawrence Graduate School of Business Administration University of Colorado Boulder, CO
Analyzing Cost-Time Trade-Offs There are always cost-time trade-offs in project management. – You can completing a project early by hiring more workers.
의사결정론의 개요 중앙대학교 경영대학 박해철. The Classical Areas of Management Finance Marketing Organizational Behavior/Personnel Management Accounting Management Information.
MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. W6 6.2 Operation Management Operation Management Managing Projects Techniques.
Project Management 1.
© 2007 Pearson Education Project Management Chapter 3.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Project Management Chapter 2
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Planning.
© 2004 by Prentice Hall, Inc., Upper Saddle River, N.J Network Planning Methods Example CPM : Saint Paul’s Hospital Network Planning Methods.
Chapter 6. Terminology AOA and AON diagrams Determining Project Duration, Critical Path Special.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. KR: Chapter.
Project Scheduling A. A. Elimam FinishStart. Project Scheduling Need to plan and control large/time consuming projects.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Fifth Edition © 1999 Addison Wesley Longman. All rights reserved. 時間管理補.
Managing Project Processes Managing Project Processes.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Activity.
Network Planning Methods Example PERT & CPM
LM733-PRODUCTION OPERATIONS MANAGEMENT
Lecture 09 Project Management ISE Dept.-IU Office: Room 508.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 17 Project Management Part.
Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1999 PROJECT MANAGEMENT 18-1 Project Management.
1 1 Project Scheduling PERT/CPM Networks. 2 2 Originated by H.L.Gantt in 1918 GANTT CHART Advantages - Gantt charts are quite commonly used. They provide.
1 1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 6 Project Management To Accompany.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Project Planning and Budgeting Recall the four stages Project Definition and Conceptualization Project Planning and Budgeting Project Execution and Control.
© 2005 Prentice Hall, Inc. Managing Projects Dr. Mohammad Hamsal.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Planning.
Project Management – Part 1. Overview What is a project? Project management techniques Activity lists Network diagrams Critical path analysis Gant charts.
© 2007 Pearson Education Project Management. © 2007 Pearson Education Bechtel Group, INC.  Bechtel is a $16.3 billion-a-year construction contractor.
Operations and Project Management Session 3 Extra Some Additional Details on CPM and PERT.
Project Management Chapter 8.
Project Management Chapter Topics
Hospital Establishment
Projects: Critical Paths
Developing a Project Plan
Project Planning and Budgeting
Probabilistic Time Estimates
תזמון פרויקטים.
Project Scheduling: Lagging, Crashing and Activity Networks
Örnek-2Örnek-2 2 FinishFinish StartStart CG B 10 D 35 H J E 24 I 15 A F K ABCDEFGHIJKABCDEFGHIJK — — A B B A C D A E,G,H F,I,J Immediate.
Chapter 16 – Project Management
Learning Curve Analysis
Planning and Managing Projects
Managing Risk Chapter 7.
Presentation transcript:

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Chapter 4 - Managing Project Processes

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Activity Relationships Activity Relationship AOAAON Figure 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Activity Relationships Activity Relationship S precedes T, which precedes U. AOAAON 12 S 3 T 4 U STU Figure 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Activity Relationships Activity Relationship S and T must be completed before U can be started. AOAAON S T U T S 4 U Figure 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Activity Relationships Activity Relationship T and U cannot begin until S has been completed. AOAAON T U S T U 2 S Figure 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Activity Relationships Activity Relationship U and V cannot begin until both S and T have been completed. AOAAON U V S T 3 S T U V Figure 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Activity Relationships Activity Relationship U cannot begin until both S and T have been completed; V cannot begin until T has been completed. AOAAON S T U V 13 Dummy SU TV Figure 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Activity Relationships Activity Relationship T and U cannot begin until S has been completed; V cannot begin until both T and U have been completed. AOAAON ST 5 V U Dummy STV U Figure 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff. BSelect site and do site survey. CSelect equipment. DPrepare final construction plans and layout. EBring utilities to the site. FInterview applicants and fill positions in nursing, support staff, maintenance, and security. GPurchase and take delivery of equipment. HConstruct the hospital. IDevelop an information system. JInstall the equipment. KTrain nurses and support staff. Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop an information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J AON Network Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital AON Network Start A Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital AON Network Start A B Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital AON Network Start A B C Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital AON Network Start A B C D Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital AON Network Start A B C D E Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital AON Network Start A B C D E F Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital AON Network Start A B C D E F G Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital AON Network Start A B C D E F G H Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital AON Network Start A B C D E F G H I Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital AON Network Start A B C D E F G H I J Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital AON Network Start A B C D E F G H I J K Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital AON Network FinishStart A B C D E F G H I J K Figure 4.2 Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J AOA Network Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital AOA Network A Start 1 2 Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital AOA Network A B Start Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital AOA Network A B C D Start Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital AOA Network F A B C D H E G I Start Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital AOA Network F A B C D H E G J I Start Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J AOA Network F A B C D H E G J I Dummy Start Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital AOA Network F A B C D H E G K J I Finish 9 Dummy Start Figure 4.3 Example 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J Completion Time

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9 Figure 4.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9 Path Expected Time (wks) A-F-K28 A-I-K33 A-C-G-J-K67 B-D-H-J-K69 B-E-J-K43

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9 Path Expected Time (wks) A-F-K28 A-I-K33 A-C-G-J-K67 B-D-H-J-K69 B-E-J-K43

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Immediate ActivityDescriptionPredecessor(s) ASelect administrative and medical staff.— BSelect site and do site survey.— CSelect equipment.A DPrepare final construction plans and layout.B EBring utilities to the site.B FInterview applicants and fill positions in nursing, support staff, maintenance, and security.A GPurchase and take delivery of equipment.C HConstruct the hospital.D IDevelop and information system.A JInstall the equipment.E,G,H KTrain nurses and support staff.F,I,J Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9 Path Expected Time (wks) A-F-K28 A-I-K33 A-C-G-J-K67 B-D-H-J-K69 B-E-J-K43

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Figure 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Earliest Start and Earliest Finish Times A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 I 15 F 10 Example 4.2 Finish Start

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Earliest Start and Earliest Finish Times A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 0 I 15 F 10 Earliest start time Example 4.2 Finish Start

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F 10 Earliest Start and Earliest Finish Times Earliest start time Earliest finish time Example 4.2 Finish Start

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Earliest Start and Earliest Finish Times Example 4.2 Finish Start

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Earliest Start and Earliest Finish Times Example 4.2 Finish Start

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Earliest Start and Earliest Finish Times Example 4.2 Finish Start

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Earliest Start and Earliest Finish Times Example 4.2 Finish Start

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Earliest Start and Earliest Finish Times Example 4.2 Finish Start

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Earliest Start and Earliest Finish Times Example 4.2 Finish Start

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Earliest Start and Earliest Finish Times

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Latest Start and Latest Finish Times Example 4.3 Finish Start

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Latest Start and Latest Finish Times A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Latest finish time Example 4.3 Finish Start

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Latest Start and Latest Finish Times A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Latest start time Latest finish time Example 4.3 Finish Start

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Latest Start and Latest Finish Times Example 4.3 Finish Start

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Latest Start and Latest Finish Times Example 4.3 Finish Start

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Latest Start and Latest Finish Times Example 4.3 Finish Start

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Latest Start and Latest Finish Times

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Gantt charts

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Figure 4.8 Gantt Charts

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Activity Slack Analysis Example 4.4 Finish Start

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Activity Slack Analysis Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Activity Slack Example 4.4 Finish

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Activity Slack Analysis Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Activity Slack Slack = LS – ES or Slack = LF – EF Example 4.4 Finish

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Activity Slack Analysis Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Activity Slack Slack K = 63 – 63 or Slack K = 69 – 69 Example 4.4 Finish

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Activity Slack Analysis Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Activity Slack Slack K = 0 or Slack K = 0 Example 4.4 Finish

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Activity Slack Analysis Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Example 4.4 Finish

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Activity Slack Analysis Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Node DurationESLS Slack Example 4.4 Finish

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Activity Slack Analysis Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E I 15 F Node DurationESLS Slack A12022 B9000 C D10990 E F G H I J K Example 4.4 Finish

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital C 10 G 35 E 24 I 15 F B9B9 0 9 D H J4J K6K Critical Path Node DurationESLS Slack A12022 B9000 C D10990 E F G H I J K Example 4.4 Finish

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital C 10 G 35 E 24 I 15 F B9B9 0 9 D H J4J K6K Critical Path A Example 4.4 Finish Start

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Figure 4.9 Activity Slack

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital 8000 — 7000 — 6000 — 5000 — 4000 — 3000 — 0 — Direct cost (dollars) |||||| Time (weeks) Figure 4.10 Cost-Time Relationships in Cost Analysis

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital 8000 — 7000 — 6000 — 5000 — 4000 — 3000 — 0 — Direct cost (dollars) Crash cost (CC) Normal cost (NC) |||||| Time (weeks) (Crash time)(Normal time) Figure 4.10 Cost-Time Relationships in Cost Analysis

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital 8000 — 7000 — 6000 — 5000 — 4000 — 3000 — 0 — Direct cost (dollars) Crash cost (CC) Linear cost assumption Normal cost (NC) |||||| Time (weeks) (Crash time)(Normal time) Figure 4.10 Cost-Time Relationships in Cost Analysis

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital 8000 — 7000 — 6000 — 5000 — 4000 — 3000 — 0 — Direct cost (dollars) 5200 Crash cost (CC) Linear cost assumption Normal cost (NC) Estimated costs for a 2-week reduction, from 10 weeks to 8 weeks |||||| Time (weeks) (Crash time)(Normal time) Figure 4.10 Cost-Time Relationships in Cost Analysis

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Maximum NormalNormalCrashCrashTimeCost of TimeCostTimeCostReductionCrashing per Activity(NT)(NC)(CT)(CC)(wk)Week A12$ 12,00011$ 13,0001$ 1,000 B950,000764,00027,000 C104,00057, D1016,000820,00022,000 E24120, ,000108,000 F1010,000616,00041,500 G35500, ,000103,000 H401,200,000351,260,000512,000 I1540, ,50052,500 J410,000113,00021,000 K630,000534,00014,000 Totals$1,992,000$2,209,000 Table 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Minimum-Cost Schedule A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Minimum-Cost Schedule Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity J by 3 $1,000/week Minimum-Cost Schedule Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity J by 3 $1,000/week 3($28,000) – 3($1,000) = $81,000 Minimum-Cost Schedule Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 66 weeks Crash Activity J by 3 $1,000/week 3($28,000) – 3($1,000) = $81,000 $2,624,000 – $81,000 = $2,543,000 Minimum-Cost Schedule Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,543,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 66 weeks Crash Activity J by 3 $1,000/week 3($28,000) – 3($1,000) = $81,000 $2,624,000 – $81,000 = $2,543,000 Minimum-Cost Schedule Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Minimum Cost Schedule A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,543,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity J by 3 $1,000/week 3($28,000) – 3($1,000) = $81,000 $2,624,000 – $81,000 = $2,543,000 FinishStart A 12 B9B9 C 10 D 10 E 24 F 10 G 35 H 40 I 15 J1J1 K6K6

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Minimum Cost Schedule A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,543,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity J by 3 $1,000/week 3($28,000) – 3($1,000) = $81,000 $2,624,000 – $81,000 = $2,543,000 FinishStart A 12 B9B9 C 10 D 10 E 24 F 10 G 35 H 40 I 15 J11J111 K6K6

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,543,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 66 weeks Crash Activity D by 2 $2,000/week Minimum-Cost Schedule Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,543,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 66 weeks Crash Activity D by 2 $2,000/week $28,000 + $8,000 – 2($2,000) = $32,000 $2,543,000 – $32,000 = $2,511,000 Minimum-Cost Schedule Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,511,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 64 weeks Crash Activity D by 2 $2,000/week $28,000 + $8,000 – 2($2,000) = $32,000 $2,543,000 – $32,000 = $2,511,000 Minimum-Cost Schedule Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Minimum Cost Schedule A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,511,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity D by 2 $2,000/week $28,000 + $8,000 – 2($2,000) = $32,000 $2,543,000 – $32,000 = $2,511,000 FinishStart A 12 B9B9 C 10 D 10 E 24 F 10 G 35 H 40 I 15 J11J111 K6K6

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Minimum Cost Schedule A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,511,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity D by 2 $2,000/week $28,000 + $8,000 – 2($2,000) = $32,000 $2,543,000 – $32,000 = $2,511,000 FinishStart A 12 B9B9 C 10 D88D888 E 24 F 10 G 35 H 40 I 15 J11J111 K6K6

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,511,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Paths B-D-H-J-K and A-C-G-J-K: 64 weeks Crash Activity K by 1 $4,000/week Minimum-Cost Schedule Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,511,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Paths B-D-H-J-K and A-C-G-J-K: 64 weeks Crash Activity K by 1 $4,000/week $8,000 – $4,000 = $4,000 $2,511,000 – $4,000 = $2,507,000 Minimum-Cost Schedule Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,507,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Paths B-D-H-J-K and A-C-G-J-K: 63 weeks Crash Activity K by 1 $4,000/week $8,000 – $4,000 = $4,000 $2,511,000 – $4,000 = $2,507,000 Minimum-Cost Schedule Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Minimum Cost Schedule A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,511,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity D by 2 $2,000/week $28,000 + $8,000 – 2($2,000) = $32,000 $2,543,000 – $32,000 = $2,511,000 FinishStart A 12 B9B9 C 10 D88D888 E 24 F 10 G 35 H 40 I 15 J11J111 K6K6

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Minimum Cost Schedule A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,511,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity D by 2 $2,000/week $28,000 + $8,000 – 2($2,000) = $32,000 $2,543,000 – $32,000 = $2,511,000 FinishStart A 12 B9B9 C 10 D88D888 E 24 F 10 G 35 H 40 I 15 J11J111 K55K555

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Critical Paths B-D-H-J-K and A-C-G-J-K: 63 weeks Crash Activities B and C by 2 $7,000/week and $600/week A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,507,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Minimum-Cost Schedule Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Critical Paths B-D-H-J-K and A-C-G-J-K: 63 weeks Crash Activities B and C by 2 $7,000/week and $600/week A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,507,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 2($8,000) – 2($7,600) = $800 $2,507,000 – $800 = $2,506,200 Minimum-Cost Schedule Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Critical Paths B-D-H-J-K and A-C-G-J-K: 61 weeks Crash Activities B and C by 2 $7,000/week and $600/week A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,506,200 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 2($8,000) – 2($7,600) = $800 $2,507,000 – $800 = $2,506,200 Minimum-Cost Schedule Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Minimum Cost Schedule A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,511,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity D by 2 $2,000/week $28,000 + $8,000 – 2($2,000) = $32,000 $2,543,000 – $32,000 = $2,511,000 FinishStart A 12 B9B9 C 10 D88D888 E 24 F 10 G 35 H 40 I 15 J11J111 K55K555

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Minimum Cost Schedule A-I-K:33 weeksB-D-H-J-K:69 weeks A-F-K:28 weeksB-E-J-K:43 weeks A-C-G-J-K:67 weeks Total cost = $2,624,000 $2,511,000 Indirect costs = $8,000/week Penalty cost = $20,000/week after week 65 Critical Path B-D-H-J-K: 69 weeks Crash Activity D by 2 $2,000/week $28,000 + $8,000 – 2($2,000) = $32,000 $2,543,000 – $32,000 = $2,511,000 FinishStart A 12 B77B777 C88C888 D88D888 E 24 F 10 G 35 H 40 I 15 J11J111 K55K555

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Coors Field

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Probabilistic Time Estimates

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Probabilistic Time Estimates Time Probability Figure 4.11

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Probabilistic Time Estimates Figure 4.11 (a) Mean mab Time Probability

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Probabilistic Time Estimates Figure 4.11 (b) Mean abm 33 33 Area under curve between a and b is 99.74% Time Probability

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital AF I CG Finish D E HBJ K Start Probabilistic Time Estimates Example 4.6

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Activity B Most OptimisticLikelyPessimistic (a)(m)(b) 7815 Probabilistic Time Estimates AF I CG Finish D E HBJ K Start Example 4.6

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Activity B Most OptimisticLikelyPessimistic (a)(m)(b) 7815 Probabilistic Time Estimates t e = = 9 weeks 7 + 4(8) AF I CG Finish D E HBJ K Start Example 4.6

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Activity B Most OptimisticLikelyPessimistic (a)(m)(b) 7815 Probabilistic Time Estimates t e = = 9 weeks 7 + 4(8)  2 = = 1.78 ( ) AF I CG Finish D E HBJ K Start Example 4.6

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Example 4.6 St. Adolf’s Hospital OptimisticLikelyPessimisticExpectedVariance Activity(a)(m)(b)Time (t e )(  2 ) Time Estimates (wk)Activity Statistics

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Example 4.6 St. Adolf’s Hospital OptimisticLikelyPessimisticExpectedVariance Activity(a)(m)(b)Time (t e )(  2 ) Time Estimates (wk)Activity Statistics A B C D E F G H I J K

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Probabilities Critical Path = B - D - H - J - K T = 72 days T E = 69 days Example 4.7

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital  2 =  (variances of activities) z = T –T E  2 Probabilities Critical Path = B - D - H - J - K T = 72 days T E = 69 days Example 4.7

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital  2 =  (variances of activities) z = T – T E  2  2 = = Probabilities Critical Path = B - D - H - J - K T = 72 days T E = 69 days Example 4.7

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital  2 =  (variances of activities) z = T – T E  2  2 = = z = 72 – Probabilities Critical Path = B - D - H - J - K T = 72 days T E = 69 days Example 4.7

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital  2 =  (variances of activities) z = T – T E  2  2 = = z = = – Probabilities Critical Path = B - D - H - J - K T = 72 days T E = 69 days Example 4.7

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital  2 =  (variances of activities) z = T – T E  2  2 = = z = = – Probabilities Critical Path = B - D - H - J - K T = 72 days T E = 69 days From Appendix 2 P z =.8078 .81 Example 4.7

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital  2 =  (variances of activities) z = T - T E  2  2 = = z = = Probabilities Critical Path = B - D - H - J - K T = 72 days T E = 69 days Project duration (weeks) 6972 Probability of meeting the schedule is Length of critical path Normal distribution: Mean = 69 weeks;  = 3.45 weeks Probability of exceeding 72 weeks is Figure 4.12 Example 4.7

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital  2 =  (variances of activities) z = T – T E  2  2 = = z = = – Probabilities Path = A - C - G - J - K T = 72 days T E = 67 days From Appendix 2 P z =.8980 .90 Example 4.7

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital AF I CG Finish D E HBJ K Start

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital ActivityDurationEarliest StartLatest StartSlack C101614–2 G352624–2 J46159–2 K66563–2 D10109–1 H402019–1 E I F Table 4.2

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Project Life Cycle

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Project Life Cycle StartFinish Resource requirements Time

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Project Life Cycle Definition and organization PlanningExecutionClose out StartFinish Resource requirements Time Figure 4.13

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Solved Problem 1 Finish Start A4A4 B7B7 C5C5 D6D6 E3E3 F 11 G4G4 H3H3 Figure 4.14

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Solved Problem 2 Finish Start A B C D E F G Figure 4.15(a)

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Solved Problem 2 Figure 4.15(b) Finish Start F A B C D E F G Dummy

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Solved Problem 2 Finish Start Figure 4.16 A D E G C F B

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Solved Problem 2 Finish Start Figure 4.16 A D E G C F B Start 1 ESEF LSLF A