Definition of Firm Energy and Interruptible Transmission Two Issues Causing Problems for Business in the Western Interconnection.

Slides:



Advertisements
Similar presentations
Parallel Flow Visualization and Flowgate Allocations Equity Concerns of Non-Market Transmission Owners Equity Concerns of Non-Market Transmission Owners.
Advertisements

© 2004 Dominion Dominion Proposal January 24, 2005.
CRITF Update ISAS Vegas January 11, Action Items -Work on items that need tag identification under both existing MORC and ORSTF proposal -Define.
Energy Day Timing Issues and Operational Concerns Pipeline Segment Wholesale Gas Quadrant North American Energy Standards Board Business Practices Subcommittee.
1 Intra-Day Nominations through a Posted Point of Restriction Kathryn Burch Project Manager – Standards and Regulatory Compliance Spectra Energy Transmission.
NAESB Coordinate Interchange Version 1 Standard Revision 1, Draft 5 August, 2005.
NAESB Coordinate Interchange
WECC Board of Directors April 21-23, 2004 Seattle, Washington WECC Procedure for Reporting of System Events Disturbance Reports Rod Maslowski OC Vice Chairperson.
NAESB Coordinate Interchange Standard, Version 1 / 0
NERC TPL Standard Issues TSS Meeting #146 Seattle, WA August 15-17, 2007 Chifong Thomas.
Operating Reserves --- Again A Discussion Primer
© 2009 The Williams Companies, Inc. All rights reserved. ______________ WECC November 12, 2012.
Load Responsibility in the NWPP Footprint
WECC BAL-STD-002 Workshop February 6, 2008
Western Electricity Coordinating Council Market Interface Committee Report to the WECC Board of Directors December 6-7, 2007 Robert D. Schwermann MIC Chair.
Interchange Authority Recommendations Board of Directors Meeting December 7, 2007.
BAL-002-WECC-1 Contingency Reserves
Interchange Scheduling and Accounting Subcommittee Update October 2008 Gary Nolan ISAS Vice-Chair.
Intra Hour Tagging/Oasis During System Contingencies The transmission tagging process was initially developed to solve an after the fact accounting issue.
Presented to the WECC MIC June 15, 2007
Gas-Electric Coordination Update JGC Meeting August 23-24, 2012.
FERC Order minute Scheduling.
Standard Market Design (SMD) in New England Federal Energy Regulation Commission Conference on Standard Market Design January 22, 2002 David LaPlante Vice.
Winter 2013/2014 Reliability Solution Including LNG MWHs N. Jonathan Peress Conservation Law Foundation Greg Lander Skipping Stone NEPOOL Markets & Reliability.
Al McBride MANAGER, AREA TRANSMISSION PLANNING Existing Import Interfaces: Transmission Transfer Capabilities and The Calculation of Tie Benefits DECEMBER.
Gloria Godson VP, Federal Regulatory Policy Reliability Pricing Model Part 2.
Duke Energy Ohio Standby Rates Jim Ziolkowski, P.E., Rates Manager September 13,
WELCOME Western Area Power Administration1. Where did the journey begin? Western Area Power Administration2.
Susan Covino Senior Consultant, Emerging Markets March 31, 2015
Andy Meyers Interchange Scheduling and Accounting Subcommittee Chair Discussion Item: Use of Emergency eTags January 2015 Salt Lake City, UT.
Pricing the Components of Electric Service in Illinois Scott A. Struck, CPA Financial Analysis Division Public Utilities Bureau Illinois Commerce Commission.
Demand Response in MISO Markets NASUCA Panel on DR November 12, 2012.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 1 Network Operating Committee (NOC) June 12 th, 2014.
© 2013 McNees Wallace & Nurick LLC October 17, 2013 Robert A. Weishaar, Jr. ON SITE ENERGY – INTERPLAY WITH PJM DEMAND RESPONSE PROGRAMS Harrisburg, PA.
11 Why BPA Transmission Customers Aggregate Reservations Feb. 20, 2013.
NERC Congestion Management Congestion Management Option 3 Vendor Meeting Julie Pierce – NERC IDCWG Chair.
Welcome New York Independent System Operator. (Pre-NYISO) Regulated Market Physical contracts Regulated industry Cost Based System Two Party Deals Bundled.
Spinning Reserve from Load Transmission Reliability Peer Review January, 2004 John D. Kueck Brendan J. Kirby.
Reserves Issue For years there has been disagreement over reserves issues and what constitutes firm power. We’ve been able to function as a market, despite.
WECC Market Interface Committee Update WSPP Spring 2008 Meeting April 8, 2008 Robert D. Schwermann MIC Chair.
2013 Calendar Year Customer Survey Results
POWER SYSTEM PLANNING CHARTER AND PROCESSES Presentation to TAC 10/09/2003 KENNETH A. DONOHOO, P.E. Manager of System Planning Transmission Services
OASIS Insights & Observations Transmission Customer Forum September 21-22, 2006 Jim Viikinsalo September 21-22, 2006 Jim Viikinsalo.
Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.
OSC Meeting April 27, Transmission Cost Allocation Overview.
Joe Polidoro, Sr. Engineer PJM Interconnection, LLC Grid of the Future: Integrating Load Response into the Markets.
Bulk Power Transmission System
Reserves…Where are we??? Service Schedule C Service Schedule C C-3.10 Seller shall be responsible for ensuring that Service Schedule C transactions are.
PJM©2013www.pjm.com Economic DR participation in energy market ERCOT April 14, 2014 Pete Langbein.
PJM© Demand Response in PJM 2009 NASUCA Mid-Year Meeting June 30, 2009 Boston, MA Panel: Price Responsive Demand – A Long-Term Bargain.
Kathy Anderson Idaho Power
IWWG Annual Conference Wind Management at MISO July 22, 2011.
1 WSPP EC SLIDES FOR AGENDA ITEMS 3 AND 4 WSPP SERVICE SCHEDULE C WSPP Service Schedule C includes a provision allowing interruption “to meet Seller’s.
Distributed Generation Registration June 30, 2008.
Programs/Products that ERCOT Does Not Presently Offer ERCOT Demand Side Working Group New DR Product Options Subgroup Jay Zarnikau Frontier Associates.
WSPP Webinar Proposed Service Schedules Operating Reserve Service (D) Intra-Hour Supplemental Power (E) February 4, 2010.
Role Of ERC in the WESM To enforce the rules and regulations governing the operations of the WESM and monitors the activities of the Market Operator and.
Market Implications and Considerations for Enhanced Scheduling Flexibility: Facts Observations Problems Solutions February 2016 Greg Lander– President.
Explanation of Revised Draft Reserves Schedule, Service Schedule D Contact: Arnie Podgorsky Mike Thompson Wright & Talisman PC
©2003 PJM 1 Presentation to: Maryland Public Service Commission May 16, 2003.
Wind Management at MISO
WEQ OASIS Subcommittee
The New Texas Wholesale/Retail Market
Regional Transmission Organizations
Gas-Electric Coordination Can New Services Bridge the Divide?
Review of After-the-Fact (ATF) Tagging Criteria Scheduler’s Meeting May 24, 2016 Raymond will ask the audience what their expectations are in regard to.
Summer Peak Energy Pricing in New England: The ISO-NE Response
Review of After-the-Fact (ATF) Tagging Criteria Scheduler’s Meeting May 24, 2016 Raymond will ask the audience what their expectations are in regard to.
Two-Tier Firm Curtailment Overview
NERC Congestion Management
Presentation transcript:

Definition of Firm Energy and Interruptible Transmission Two Issues Causing Problems for Business in the Western Interconnection

Who is Carrying Reserves? When a Firm Transaction is made, must the Sending Control Area carry Reserves on the Transaction? When a Firm Transaction is made, must the Sending Control Area carry Reserves on the Transaction? –Is this a requirement? –How would the seller carry the reserves? –Is it reasonable to require the seller to carry reserves? –Is this needed for reliable system operations?

Is This a Requirement? Can an entity sell firm energy without reserve? Yes, it is a business transaction. Can an entity sell firm energy without reserve? Yes, it is a business transaction. Is this a reliability issue? Is this a reliability issue? –No. The entities involved need to know who is carrying reserves. Is it more reliable for the purchaser to carry its own reserves instead of the seller? YES! Is it more reliable for the purchaser to carry its own reserves instead of the seller? YES! –The purchaser has no right to call upon reserves held by the seller unless they are in the same RSG. –There is no transmission path for the delivery of reserves held by the seller of hourly or daily transactions nor has there been any evaluation to ensure reliable delivery.

How does the Seller Carry the Reserves? If a seller is MSSC, there is no change in reserves required by WECC rules. If a seller is MSSC, there is no change in reserves required by WECC rules. If the seller is Load Driven, there is a change in reserve required by WECC rules. If the seller is Load Driven, there is a change in reserve required by WECC rules.

Can a Firm Sale Result in a Reduction of Reserves Carried in the WECC? Yes. A firm sale can result in a combined decrease in reserves carried by two control areas if the sending control area is MSSC and the receiving control area has a load driven reserve requirement. Yes. A firm sale can result in a combined decrease in reserves carried by two control areas if the sending control area is MSSC and the receiving control area has a load driven reserve requirement.

Load Responsibility, Why Do We Have It? If the MSSC is correctly determined, there should be no reliability issues associated with doing away with the Load Responsibility section of MORC. If the MSSC is correctly determined, there should be no reliability issues associated with doing away with the Load Responsibility section of MORC. The reserve obligation is not affected based on commerce in any other NERC region. The reserve obligation is not affected based on commerce in any other NERC region.

Should the Seller Carry Reserves on Firm Energy Sales? If the seller holds the reserve and the buyer has a DCS event, no reserves will be provided by the seller. If the seller holds the reserve and the buyer has a DCS event, no reserves will be provided by the seller. –No transmission path is reserved for delivery –The buyer has no right to call for activation if the seller is in a different RSG –No evaluation has been made to determine if reserves can be delivered from seller to buyer without concern. Example - Reserves held in PJM will not be very useful for San Diego Gas and Electric. Example - Reserves held in PJM will not be very useful for San Diego Gas and Electric.

Is a Definition of Firm Energy Needed for Reliable Operation of the System? If the reserves for the WECC were determined based only on MSSC, there would be no issue. If the reserves for the WECC were determined based only on MSSC, there would be no issue. Load Responsibility used with no change in required reserves due to transactions would also solve the issue. Load Responsibility used with no change in required reserves due to transactions would also solve the issue. As done today, the Reliability Coordinator can not even determine where reserves will be held. As done today, the Reliability Coordinator can not even determine where reserves will be held. Answer – No! Answer – No!

Does This Mean That We Have a Reliability Issue? The issue of reserves associated with wholesale sales has never been identified as a contributor to a significant WECC event. The issue of reserves associated with wholesale sales has never been identified as a contributor to a significant WECC event. The real reliability issue is the constantly changing reserve requirements. The real reliability issue is the constantly changing reserve requirements. Defining an energy product should be a business practice, not a reliability issue. Defining an energy product should be a business practice, not a reliability issue.

Interruptible Transmission What is it, exactly??

Interruptible Transmission FERC tariff does not have a service schedule called interruptible transmission. FERC tariff does not have a service schedule called interruptible transmission. Non-Firm transmission is defined in the tariff but it is not interruptible for any reason. Firm transmission can also be curtailed under the tariff. Non-Firm transmission is defined in the tariff but it is not interruptible for any reason. Firm transmission can also be curtailed under the tariff. Under WECC Unscheduled Flow Mitigation Procedure, all transactions are subject to curtailed, so claiming only Non- Firm is interruptible seems questionable. Under WECC Unscheduled Flow Mitigation Procedure, all transactions are subject to curtailed, so claiming only Non- Firm is interruptible seems questionable.

Questions for the Group Is an overloaded transmission line a reliability issue? Is an overloaded transmission line a reliability issue? Is an overscheduled transmission line a reliability issue? Is an overscheduled transmission line a reliability issue? Once past the scheduling deadline, can transmission service be interrupted for economic reasons? Once past the scheduling deadline, can transmission service be interrupted for economic reasons?

13.8Scheduling of Firm Point-To-Point Transmission Service: Schedules for the Transmission Customer's Firm Point-To-Point Transmission Service must be submitted to the Transmission Provider no later than 1:00 p.m. (Pacific Time) of the Working Day prior to commencement of such service. Schedules submitted after 1:00 p.m. (Pacific Time) will be accommodated, if practicable. Hour-to-hour schedules of any capacity and energy that are to be delivered must be stated in increments of whole megawatts per hour. A Transmission Customer within the Transmission Provider's service area with multiple requests for Transmission Service at a Point of Receipt, each of which is under 1,000 kW per hour, may consolidate its service requests at a common point of receipt into units of whole megawatts per hour for scheduling and billing purposes. Scheduling changes will be permitted up to thirty (30) minutes before the start of the next clock hour provided that the Delivering Party and Receiving Party also agree to the schedule modification.

Summary of Tariff Section 13.8 Schedules must be submitted prior to XXXX the day ahead. Schedules must be submitted prior to XXXX the day ahead. Schedules submitted after XXXX will be accommodated if practicable. Schedules submitted after XXXX will be accommodated if practicable. Schedule changes will be permitted up 30 (20) minutes prior to the operating hour. Schedule changes will be permitted up 30 (20) minutes prior to the operating hour.

14.7Curtailment or Interruption of Service: The Transmission Provider reserves the right to Curtail, in whole or in part, Non-Firm Point-To-Point Transmission Service provided under the Tariff for reliability reasons when an Electrical Emergency or other unforeseen condition threatens to impair or degrade the reliability of its Transmission System. The Transmission Provider reserves the right to Interrupt, in whole or in part, Non- Firm Point-To-Point Transmission Service provided under the Tariff for economic reasons in order to accommodate (1) a request for Firm Transmission Service, (2) a request for Non- Firm Point-To-Point Transmission Service of greater duration, or (3) a request for Non-Firm Point-To-Point Transmission Service of equal duration with a higher price. The Transmission Provider also will discontinue or reduce service to the Transmission Customer to the extent that deliveries for transmission are discontinued or reduced at the Point(s) of Receipt. Where required, Curtailments or Interruptions will be made on a non-discriminatory basis to the transaction(s) that effectively relieve the constraint, however, Non-Firm Point-To-Point Transmission Service shall be subordinate to Firm Transmission Service. If multiple transactions require Curtailment or Interruption, to the extent practicable and consistent with Good Utility Practice, Curtailments or Interruptions will be made to transactions of the shortest term (e.g., hourly non-firm transactions will be Curtailed or Interrupted before daily non-firm transactions and daily non-firm transactions will be Curtailed or Interrupted before weekly non-firm transactions). Non-Firm Point-To-Point Transmission Service over secondary Point(s) of Receipt and Point(s) of Delivery will have a lower priority than any Non-Firm Point-To-Point Transmission Service under the Tariff. The Transmission Provider will provide advance notice of Curtailment or Interruption where such notice can be provided consistent with Good Utility Practice.

Summary of Tariff Section 14.7 Economic Interruptions may occur for Economic Interruptions may occur for –Firm Requests –Longer Duration Non-Firm Requests –Higher Priced Non-Firm Requests At least some Transmission Providers have a fourth reason: transmission service for Network Customers from non-designated resources At least some Transmission Providers have a fourth reason: transmission service for Network Customers from non-designated resources Can any of these be done during the operating hour? After the scheduling deadline? Can any of these be done during the operating hour? After the scheduling deadline?

Curtail Versus Interrupt Is a curtailment the same as an interruption? Is a curtailment the same as an interruption? Under current WECC rules, interruptible effectively means: a product which by contract is interruptible at the supplying systems discretion. Under current WECC rules, interruptible effectively means: a product which by contract is interruptible at the supplying systems discretion. Curtailability is defined in the WECC Definitions to mean an interruption caused by a reduction in capability. Curtailability is defined in the WECC Definitions to mean an interruption caused by a reduction in capability. FERC tariff says curtailment is for reliability reasons. FERC tariff says curtailment is for reliability reasons. Under these definitions, Non-Firm Transmission is clearly not interruptible during the operating hour, but is curtailable. Under these definitions, Non-Firm Transmission is clearly not interruptible during the operating hour, but is curtailable.

Financial Impacts Historically PSCO uses approximately 200 MWs of non-firm transmission for imports. No new Firm Transmission is available through WAPA nor is any likely to be built through the Rocky Mountains. Historically PSCO uses approximately 200 MWs of non-firm transmission for imports. No new Firm Transmission is available through WAPA nor is any likely to be built through the Rocky Mountains. Cost of generation to replace this would be $65/kW/year or $13 million per year. Cost of generation to replace this would be $65/kW/year or $13 million per year. Additionally, PSCo may need to have generation available to cover loss of generator at all times, or approximately 500 MWs of gas turbines, to meet reserve requirements. Additionally, PSCo may need to have generation available to cover loss of generator at all times, or approximately 500 MWs of gas turbines, to meet reserve requirements. Should PSCo curtail Retail Load to meet reserves under these conditions? Should PSCo curtail Retail Load to meet reserves under these conditions?

What Does It All Mean? The current MORCWG proposal before you creates a product that does not exist under the FERC tariff. The current MORCWG proposal before you creates a product that does not exist under the FERC tariff. The MORCWG proposal, if adopted, will cause confusion, and likely significant legal problems for WECC members. The MORCWG proposal, if adopted, will cause confusion, and likely significant legal problems for WECC members. There has not been an evaluation of the impacts of this proposal as required by the WECC Boards guidelines. There has not been an evaluation of the impacts of this proposal as required by the WECC Boards guidelines.

Conclusion PSCo asks that CMOPS either PSCo asks that CMOPS either 1.Send the MORCWG proposal back to the MORCWG to address the issues raised here. 2.Modify the MORCWG proposal to address the issues raised here. 3.Delay any movement on the MORCWG proposal until the WECC reserve requirements undergo a complete review and are adjusted to work with todays electric markets