Closing Out a Federal Aid Construction Project Missouri Local Programs How to Close-Out a Federal Aid Construction Project.

Slides:



Advertisements
Similar presentations
Got Federal-aid? Then you must have all the required contract provisions.
Advertisements

Construction Contract Administration LPA/ODOT
LPA Projects LPA projects Alum Creek Bike Trail $3,200,000 Parsons/Livingston $14,500,000 Riversouth Phase $9,900,000 Lane Avenue $1,700,000 Arcadia.
USDA - RURAL DEVELOPMENT
Change Order Missouri Local Programs How to Complete a Change Order & Get it Approved.
Requirements for Federal Aid Project Contracts Kenneth Spear, Contracts & Estimates Engineer.
Reimbursement Procedures for Title I Charter Schools School Year Department of Federal and State Programs.
INDOT Contractor Prequalification.
LPA Annual Update FFY Roles and Responsibilities 2010 Recap 2011 Changes Areas of Concern MoDOT Project Bid Reviews National Review Team LPA Manual.
With the Genesee County Road Commission By Fred Peivandi, P.E. And Ken Johnson, P.E. Local Road Funding.
Step by Step Process. Checklist and Form Instructions A checklist is provided on the website to help applicants track their progress in completing the.
State Aid (SALT) prepares the Federal Agreements and the Amendments for  Force Account (FA)  Right of Way (ROW)  Preliminary Engineering (PE)  Construction.
Grant Management Webinar Presenters – Karla Freeman – Beth Romero – Chris Epoca.
Community Facility Loans/Grants Architect Flow Chart Owner has need for project. RD Area Office is contacted. RD visits project site and discusses project.
Reimbursements for Local Programs Taylor Rossetti Local Government Coordinator Local Programs Team Sara Janes Local Programs Coordinator.
Circular A-110 Everything You Didn’t Want to Know.
ISLAMIC UNIVERSITY OF GAZA FACULTY OF ENGINEERING CIVIL ENGINEERING DEPARTMENT Defects Liability [Construction Contract Administration] Chapter 11.
Local Agency Program General Information 1. Local Agency Program (LAP) is a re- imbursement program 2. Each Invoice to FDOT should only include one.
Doing Business with Department of Enterprise Services for General Contractors and Subcontractors June 19, 2013.
Reimbursement Procedures for Title I Charter Schools School Year Department of Federal and State Programs.
State Auditor’s Office Change Order Pricing Practices Performance Audit of Eight Local Governments Puyallup City Council February 7, 2012 Chris Cortines,
Construction: Legal Issues. Legal Issues In the Bidding Process Timing of various activities has legal implications. During the bidding process: –A bid.
NOV-3733-SL-9715 Carbones KOM - May 10-11, 2010 – Toulouse, France 1 KICK-OFF MEETING May 10-11, 2010.
DCP 14 Request for Final Payment. Front Page Bottom of Sheet Do not submit an incomplete packet Ledger questions to John Fox ( ) DCP 14 questions.
Procedural Requirements For Force Account Work on Federal and State Projects 2015 ACCA Conference Orange Beach, Alabama.
1 INTERREG IIIB “ATLANTIC AREA” Main points of community regulation 438/2001 financial management and control systems EUROPEAN COMMISSION SPAIN.
Remarks will print on the completed form Generate Quantity Book Entry Generate Pay Quantity.
Project Diary Missouri Local Programs How to Develop and Use the Daily Diary and Payment Diary for LPA Inspectors.
Mn/DOT AUDIT COUNTY HIGHWAY ACCOUNTANTS SINGLE AUDIT DISCUSSION.
Completing the State Aid Payment Request (SAPR). Tips Each spring check on the State Aid Finance web page for the current version of the State Aid Pay.
Kenneth D. Fenton P.S. Clark County Engineer’s Office.
Anna Bergmark Region 7 Local Program Local Program ARRA Training: ARRA Reporting Requirements.
Mock State Aid Project County Highway Accountant’s Conference 2015.
Chapter 30 Final Inspection, Contract Closing, and Project Transfer.
Genesee County Road Commission Fred Peivandi, P.E. County Highway Engineer MTPA July 15, 2011 TIP Project Administration.
Close-out Documentation  DISTRICT WIDE REQUIREMENT – The District has implemented the requirement of the “Blue Folder” for final LAP documentation. This.
MARCH 9, 2006 Boating Safety and Enforcement Grant Program Regulations Stakeholder Workshop Proposed Conceptual Regulations Department of Boating and Waterways.
City of Chicago Comptroller’s Office Voucher Audit and Tracking Unit (Revised 04/06/09) Common Problems with Delegate Agency Invoices.
* The address used when the guarantor request to have statements, collection letters and guarantor/patient ledgers sent to someplace other than the permanent.
PROJECT PHASES ACT Objective To provide an understanding of the design & construction process and the roles of the different participants in this.
Project Closeout Module #14 Prepared by Dr. Randy R. Rapp July 2005.
Consultant Selection Missouri Local Programs How to Evaluate Consultant Proposals, Complete the Rating Sheets & Make a Selection.
Preparing a Right of Way Request for Acquisition Authority Missouri Local Programs How to request right of way acquisition authority for obligation of.
Trivia Certification Program Trivia Mark Foster ODOT Region 1 Liaison and Federal Aid Specialist March 12, 2010.
Request For Qualifications (RFQ) Missouri Local Programs How to Complete the RFQ & Get it Advertised.
Preparing a Right of Way Clearance Certification Request Missouri Local Programs How to complete right of way clearance certification-No new property rights.
Request for Proposals Notification When to use?. When to use….. Federal funds to be used as reimbursement for PE, R/W, CE. 100% local funds for PE and/or.
OTC Pres Project Del P5 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Jeff Gower, State Construction.
Arkansas Department of Emergency Management Arkansas’ Homeland Security & Preparedness Agency Sandy Recovery Improvement Act of 2013 Public Assistance.
April 29, 2014 WELCOME!. Tips & Tricks Interface & View.
MnDOT AUDIT 2016 COUNTY HIGHWAY ACCOUNTANTS CONFERENCE ANNUAL FEDERAL CITY COUNTY AUDIT DISCUSSION.
PREPARING FOR A FISCAL AUDIT OF THE DYS SUBSIDY GRANT PRESENTED BY: GREG STEPHENS ADMINISTRATOR OFFICE OF AUDITS AND FISCAL COMPLIANCE.
Disadvantaged Business Enterprise (DBE) Each Submitter’s Responsibility for Outreach Efforts.
PROJECT CLOSEOUT MODULE 11. Objectives Establish procedures for effective/smooth project close-out As-built plans Project payment Certifications Report.
Document control MODULE 4.
Construction Oversight
FHWA Funding, Monitoring & Reporting
County Highway Accountant’s Conference 2015
Administration of a FIDIC Contract - Financial Management
State Aid Construction
Washington Metropolitan Area Transit Authority (WMATA)
Preparing a Right of Way Clearance Certification Request
Force Accounts.
Delegated Contract Process for Federal Construction Contracts
Management Verifications & Sampling Methods
Common Errors - FCRB Payment Requests
Mark Robinson FINANCE DIVISION SUPPORT
State Aid Construction
Mark Robinson FINANCE DIVISION SUPPORT
Diversity management system (DMS)
Presentation transcript:

Closing Out a Federal Aid Construction Project Missouri Local Programs How to Close-Out a Federal Aid Construction Project

Documentation Required for LPA Project Closeout  1. Semi-final/Final inspection letter  2. LPA Final acceptance letter  3. Testing Results certification  4. Contractor DBE Certification & LPA Recommendation  5. Final Invoice  6. Final Detailed estimate of quantities  7. Contractors Affidavit Regarding Settle of Claims  8. Final Change Order  9. Affidavit (Compliance with Prevailing Wage)

1. Semi-final/Final Inspection Letter  -All projects are required to have a semi final inspection. If any needed corrections to the project are found, a final inspection is then required after all corrections have been addressed.  -Those required to attend semi-final inspection; LPA Representative, contractor, engineer of record, MoDOT.  -The Final Inspection Letter shall state those in attendance, the date inspection took place, and any corrections needed.

2. LPA Final Acceptance letter  -The LPA must submit a final acceptance letter on LPA letterhead stating that they accept all work completed by the contractor.  -The letter must also include the number of working days in the contract and the number of working/calendar days it took to complete the project. If it was a completion date contract, list the contractual date and the completion date. If liquidated damages were incurred, they must be listed.

3. Testing Results Certification -The engineer of record shall supply a letter certifying the results of the test for acceptance of materials. See EPG Figure XX for example letter. -The certification statements that must be included in this letter can be found in EPG of the LPA manual. Number 3 lists all three required statements ( a., b. & c.). (link)

4. DBE Contractor Certification & LPA Recommendation  Contractor Certification –The contractor is to fill out the Contractor Certification Form (EPG Fig X). This form must list final DBE participation showing all work performed and dollar amount paid to each DBE used on contract.  LPA Recommendation of DBE Performance –The LPA must supply on LPA letterhead a recommendation to MoDOT as to the fulfillment of the DBE requirements. –If DBE goals were not met, the LPA must supply documentation as to why. –MoDOT makes the final determination of DBE fulfillment

5. Final Invoice  The appropriate copies of the final invoice shall be included with the close out documentation.  The final invoice will not be reimbursed if all closeout documentation and certifications have not been received by MoDOT within 30 days of final inspection.

6. Final Detailed Estimate of Quantities  A final detailed estimate of quantities must show the final adjusted contract amount. This estimate will include any overruns or underruns of pay items encountered over the length of the contract.  Typically the detailed estimate is supplied by the contractor to the LPA for pay request.

7. Contractors Affidavit Regarding Settle of Claims  The Contractors Affidavit Regarding Settle of Claims (Figure ) shall be filled out and executed by the contractor and supplied to the LPA.

8. Final Change Order  A copy of the final change order is required to close out a project (if applicable).  If all change orders have been approved and there is no final change order needed, a copy of previous change orders must be supplied.

9. Affidavit (Compliance with Prevailing Wage)  The Affidavit (Compliance with Prevailing Wage), (Figure ) shall be filled out and executed by the contractor and supplied to the LPA.

Final Acceptance by MoDOT  After items 1-9 have been supplied to MoDOT, they will be reviewed for correctness, extra funds will be obligated for change orders and final reimbursements to the LPA will be approved and issued.  A final acceptance report will be generated by MoDOT and sent to the LPA. This report closes the project and no additional funds can be obligated or reimbursed.