Copyright © 2009 T.L. Martin & Associates Inc. Chapter 5 Advanced Techniques of CPM Deception and Mystery.

Slides:



Advertisements
Similar presentations
Construction Delays & CPM Schedules
Advertisements

Chapter 6 Practical Methods to Reveal CPM Covert Activities
Administering Lump Sum P/T Contracts via a Cost Loaded Schedule
CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension.
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 4 Standard CPM Smoke and Mirror Tricks (Manipulations)
DISTRICT FIVE CONSTRUCTION CONTRACT ADMINISTRATION UPDATE TRAINING Submission of Working Schedule Specification SP A.
CP Chapter 4 Schedule Planning.
Scheduling Resources and Costs CHAPTER EIGHT Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Defining activities – Activity list containing activity name, identifier, attributes, and brief description Sequencing activities – determining the dependencies.
Project Management 6e..
Chapter 14 Schedule Risk Management Dr. Ayham Jaaron Second Semester 2010/2011.
Systems Analysis and Design 9th Edition
Systems Analysis and Design 8 th Edition Chapter 3 Managing Systems Projects.
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
Project Control Techniques
PROJECT TIME CONTROL. PROJECT SCHEDULING REFERENCES PRIMARY REFERENCE IN THIS PRESENTATION IS Operations Management, Ed 6, Heizer & Render, Prentice Hall,
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 2 Key CPM Scheduling Terms.
Project Cost Management Estimation Budget Cost Control
Systems Analysis and Design 8th Edition
Introduction -Discussed preparation of the overall plan for the project - as well as its implementation. -The control system quantitatively measures actual.
Reviewing & Analyzing Schedule
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
1 ®  Overview Benefits of a Good Construction Schedule Baseline Schedule Development Schedule Updating and Maintenance Managing Project Changes USACE.
XII- COST CONTROL, MONITORING & ACCOUNTING
Construction Scheduling and Estimating.  Someone gets an IDEA  The IDEA inspires a PLAN to be created  The PLAN is used to build the SCHEDULE  The.
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 3 Requirements of a realistic CPM schedule.
Toolkit 4.
Construction: Legal Issues. Legal Issues In the Bidding Process Timing of various activities has legal implications. During the bidding process: –A bid.
Amin Salari, CCM, PMP, LEED AP – Lundgren Management
CONTROLLING TIME. ”Remember that time is money” Benjamin Franklin 1748.
McDONOUGH BOLYARD PECK CONSTRUCTION ENGINEERING SUCCESSFUL STRATEGIES FOR SCHEDULING PROJECTS TO FINISH ON TIME Presented by Christopher J. Payne, PE,
Scheduling Resources and Costs CHAPTER EIGHT PowerPoint Presentation by Charlie Cook Copyright © 2014 McGraw-Hill Education. All Rights Reserved.
Planning and Scheduling. Project Planning –Selecting Construction Methods and sequence of work –Must complete planning before doing scheduling –Steps.
Quick Recap.
Risk Assignment in The Delivery of a Project  RISK! –Construction projects have lot of it –Contractors manage it –Owners pay for it.
Lecture 7. Review of Lecture 6 Project Scheduling: The process of defining project activities, determining their sequence, estimating their duration Scheduling.
Managing Project Resources. Project Resources Human Resources Project stakeholders: – Customers – Project team members – Support staff Systems analyst.
Chapter 15 Construction Scheduling. Objectives After reading the chapter and reviewing the materials presented the students will be able to: Identify.
Scheduling Resources and Costs CHAPTER EIGHT Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
T.L. Martin & Associates Copyright © 2008 Chapter 1 Fundamentals of Scheduling T.L. Martin & Associates, Inc Office Park Drive Gaithersburg, Maryland.
LECTURE 4 FORMULATION & PRESENTATION OF MONETARY CLAIMS  Recovery of Loss / Expenses / Damages  Notice of intention to claim  Particular and further.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
Scheduling Resources and Cost
Copyright © 2003 Primavera Systems, Inc Primavera User Conference Schedule Bingo presented by Mike Stone w/Professional Project Management Services.
Introducing Project Management Update December 2011.
Copyright 2003 Lynn Frock & Company. All Rights Reserved. 1 Five Ways to Build a Microsoft Project Schedule Lynn Frock, PMP Phone
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
1 Float Ownership in Construction Project Khalid Al-Gahtani.
Problems, Methods and Tools of Advanced Constrained Scheduling Session 9 Shane Archibald Archibald Associates & Spider Project (USA) “PMI” is a registered.
Improved Project Control Through CPM Scheduling What Owners, PM’s and CM’s Need to Know t H E T I B U R O N T I B U R O N G R O U P, L L C G R O U P, L.
Project Time Management Ashima Wadhwa. Schedule Development – Determining start and finish dates for project activities – Without realistic dates, project.
Scheduling. Putting the activities in chronological order –Chicken or the egg Allows the PM to determine the time required to complete a project.
CLAIMS MANAGEMENT. PRESENTATION OUTLINE INTRODUCTION TYPICAL CLAIMS AGAINST OWNER TYPICAL CLAIMS AGAINST CONTRACTOR CRITICAL PATH METHODS UTILIZATION.
Scheduling CTC-370. Value Engineering Provides alternatives to the proposed design –Save Owner $$ –Must be as good or better than original design –Must.
University of Calgary Continuing Education Construction Contract Law and Documents Week 12 Changes Delays Claims Contract Documentation.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
SOFTWARE PROJECT MANAGEMENT
Managing Schedule Slack/Float PMI Scheduling Forum January 6, 2015 January 6, 2015 Presented by: Ric Albani, PMP, PMI-SP, PMI-RMP, MCTS.
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
BSBPMG503A Manage Project Time Manage Project Time Project Time Processes Part 2 Diploma of Project Management Qualification Code BSB51507 Unit Code.
Project Time Management Based on PMBOK 5 th Edition Abdelrahman Sheta, PMP,ITIL 1PMP - Project Time Managementfacebook.com/Sheta.Page.
SCHEDULE MANAGEMENT MODULE 8. Required by Specification City/Caltrans Level 1 schedule – simple Less than $1 million, less than 100 working days Advanced.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
Establishing and Managing a Schedule Baseline
Project Management -- Scheduling Resources and Costs
ENGINEERING MANAGEMENT (GE 404)
CHAPTER 6 PROJECT TIME MANAGEMENT
How to perform Time Impact Analysis / Window Analysis in Primavera P6
CHAPTER 6 PROJECT TIME MANAGEMENT
Presentation transcript:

Copyright © 2009 T.L. Martin & Associates Inc. Chapter 5 Advanced Techniques of CPM Deception and Mystery

Copyright © 2009 T.L. Martin & Associates Inc. A. The baseline schedule

Copyright © 2009 T.L. Martin & Associates Inc. The baseline schedule Should represent a contractor’s realistic strategy for constructing the project and meeting all contract requirements. It is to include all work activities, linked together based: –primarily on physical relationships –secondarily by contractor preference Work activity durations are based on: –work quantities, –Resources, and –reasonable production rates. A contractor’s estimated “means and methods” of its bid should be similar to the baseline schedule.

Copyright © 2009 T.L. Martin & Associates Inc. The baseline schedule An accurate baseline schedule is an extremely useful tool. It is the basis for many important decisions: –owner, contractor and subcontractor commitments, –Financial and cash-flow requirements –personnel, material and equipment

Copyright © 2009 T.L. Martin & Associates Inc. The baseline schedule Specialty subcontractors should develop an activity list with estimated work quantities, key resources and anticipated productions. The owner should also provide the general contractor anticipated work lists for which it assumes responsibility with appropriate durations. The general contractor then takes this information and develops a proposed as planned project CPM schedule. This proposed schedule should first be reviewed by specialty contractors. The contractor’s finalized baseline schedule should then be reviewed and approved by the owner and/or its representatives.

Copyright © 2009 T.L. Martin & Associates Inc. The baseline schedule The baseline CPM schedule has significance since it may be used to prove delay to project completion. Contractors use it as a basis to claim damages due to alleged owner interference, delays and/or directed acceleration. Owners uses it to help defend against such claims. (A baseline schedule may include some very deceptive tricks.)

Copyright © 2009 T.L. Martin & Associates Inc. The baseline schedule Tricks and Traps A contractor under-resources the baseline schedule. –Stop an owner from rightfully complaining that the project is being delayed due to contractor failure to resource the job correctly. –The under-resourced scheduled may also set up an owner for an acceleration claim, with damages computed as the difference between the baseline and what was actually expended.

Copyright © 2009 T.L. Martin & Associates Inc. The baseline schedule Tricks and Traps Another favorite trick is to improperly prolong some work and cause follow-on activities to be crowded into an unrealistic performance periods. This often creates many critical activity paths during the crowded period, with high risk of completion delay. –The owner and contractor incorectly will not view problems early-on as detrimental to overall project performance.

Copyright © 2009 T.L. Martin & Associates Inc. The baseline schedule Tricks and Traps Improperly prolonging some work and causing follow- on activities to be crowded into an unrealistic performance period often backfires. The Owner takes advantage of available float in early work –Delays to foundations, –Late owner furnished equipment and/or materials, –Late designs for follow-on work, –Will not appear critical, resulting in no entitlement to additional time for contractor performance.

Copyright © 2009 T.L. Martin & Associates Inc. The baseline schedule Tricks and Traps A contractor may attempt to create many critical paths through a project’s CPM network. This however becomes a double-edged sword if the contractor causes a delay along one of the critical paths. The more probable result with multiple critical paths is concurrent delay. Both owner and contractor problems delay critical path work, which generally results in a non-compensable time extension for the contractor. Thus, an unrealistically crowded period in a CPM schedule harms both the contractor and the owner.

Copyright © 2009 T.L. Martin & Associates Inc. Key Issues to Watch Out for in the Schedule Development Process Inadequate number of activities and missing work activities Excessive activity durations The use of vague logic and missing logic ties for key relationships The use of manpower restraints and preferential logic conditions which cause critical or near-critical paths Excessive number or unreasonable constraints Failure to include “ordinary” weather days Typical problems encountered in the Baseline Network

Copyright © 2009 T.L. Martin & Associates Inc. Key Issues to Watch Out for in the Schedule Development Process Control and abuse of float Owner durations for various approvals Front-end cost loading Deferring major features of work toward the end of the project and not taking advantage of the opportunities that exist

Copyright © 2009 T.L. Martin & Associates Inc. B. Updating the project schedule

Copyright © 2009 T.L. Martin & Associates Inc. Updating Update - The process of incorporating actual event documentation into the baseline schedule or current approved schedule to forecast how the actual progress of the work compares to the plan Should be required with every pay requisition or at least monthly

Copyright © 2009 T.L. Martin & Associates Inc. Update Why Update a Schedule –Document and record actual progress –Determine status of the job relative to completion or interim milestones –Establish an accurate benchmark for payment- “earned value” –To provide current activity start and finish dates

Copyright © 2009 T.L. Martin & Associates Inc. The Data Date DATA DATE - The first working day after the reporting period Generally at the end of the month to coincide with billing cycles

Copyright © 2009 T.L. Martin & Associates Inc. Goals of a Schedule Update To limit surprises To preserve an accurate record of progress Accurately determine reasonable payment Forecast project completion or key project milestones Calculate the impact of progress (or lack there of) in the previous period

Copyright © 2009 T.L. Martin & Associates Inc. The Schedule Update Process Contractor develops a pencil copy Must accurately reflect both: –Value of work in place based on actual quantities installed –Required time to complete remaining work. Allow review of activity percent complete and resource percent complete.

Copyright © 2009 T.L. Martin & Associates Inc. The Schedule Update Process A key area of trickery involves revisions to logic or lack there of, during the update. Major revisions to activity sequences with impacts to critical work and/or causing previously non-critical work to become critical, require special review and understanding. Owner responsible changes should be added to the CPM schedule during the updating process, based on agreed to fragnets. The insertion of added or changed work into the CPM during the updating process should be done based on quantities of work, realistic resources and associated production rates.

Copyright © 2009 T.L. Martin & Associates Inc. The Schedule Update Process KEY ITEMS TO REVIEW (for Trickery) Calculation Setting –Retained Logic vs. Progress Override vs. Actual Dates

Copyright © 2009 T.L. Martin & Associates Inc. The Schedule Update Process KEY ITEMS TO REVIEW (for Trickery) Calculation Setting Impact. –Retained Logic vs. Progress Override vs. Actual Dates –Start to Start Lag Calculations

Copyright © 2009 T.L. Martin & Associates Inc. Start to Start Lag Calculations As Planned Based on Actual StartBased on Early Start (of Remaining Duration)

Copyright © 2009 T.L. Martin & Associates Inc. The Schedule Update Process KEY ITEMS TO CHECK (for Trickery) Calculation Setting Impact. –Retained Logic vs. Progress Override vs. Actual Dates –Start to Start Lag Calculations –Contiguous vs. Interruptible durations

Copyright © 2009 T.L. Martin & Associates Inc. Contiguous vs. Interruptible Durations

Copyright © 2009 T.L. Martin & Associates Inc. The Schedule Update Process KEY ITEMS TO CHECK (for Trickery) Calculation Setting Impact. –Retained Logic vs. Progress Override vs. Actual Dates –Start to Start Lag Calculations –Contiguous vs. Interruptible durations –Start vs. Finish vs. Most Critical Total Float Calculations

Copyright © 2009 T.L. Martin & Associates Inc. The Schedule Update Process KET ITEMS TO CHECK (for Trickery) Calculation Setting Impact Verify dates are not leveled or limited Review Out-of-Sequence work

Copyright © 2009 T.L. Martin & Associates Inc. Out of Sequence Progress

Copyright © 2009 T.L. Martin & Associates Inc. C. Manipulation of delay

Copyright © 2009 T.L. Martin & Associates Inc. Manipulation of delay The insertion of owner responsible issues into a CPM schedule can result in misleading criticality. This will occur if the added or changed work is put into the plan based on preference, rather than physical dependency. Key resource constraints should be reviewed by both the contractor and the owner.

Copyright © 2009 T.L. Martin & Associates Inc. Manipulation of delay The insertion of added and changed work is subject to all of the tricks noted above including: –imposed constraints on activities, –selected schedule calculation method, –resource leveling, –activity relationship exploitation, and –creating impractical periods of multiple critical paths

Copyright © 2009 T.L. Martin & Associates Inc. D. Concurrency and other imaginings

Copyright © 2009 T.L. Martin & Associates Inc. Concurrency and other imaginings If a delay is encountered, during the updating process it must be determined if it has an impact to the overall project completion or to the completion of a contractual milestone date. If the delay has no affect on milestone or overall project completion, than the delay did not cause any damage or loss to either the contractor or the owner. This occurs as the delay simply reduced the float time along an activity path.

Copyright © 2009 T.L. Martin & Associates Inc. Concurrency and other imaginings The analysis and proof of liability, causation and damage becomes very complex when multiple delay issues are encountered. With each update, typically there are a number of activities that are not progressed as planned. The reasons for the lack of progress are many and varied and may simply result in logic revisions adjusting for contractor preferred sequences of work. Other issues affecting activity performance may not be as simply resolved.

Copyright © 2009 T.L. Martin & Associates Inc. Concurrency and other imaginings Sometimes a single activity may experience multiple causes of delay. For example, during one update period, the façade of the building may be delayed due to the crane being diverted for installation of added rooftop units, an owner responsible change, And also due to concrete structure errors preventing façade placement until concrete rework is performed, a contractor responsible delay. The question then becomes, did the contractor’s structure errors or the owner’s change delay the critical façade or a combination of both?

Copyright © 2009 T.L. Martin & Associates Inc. Concurrency and other imaginings The arguments are straightforward; The contractor argues that the structural repairs would have been completed much sooner but for the owner’s change diverting the crane. Simply, why hurry up to only wait for the crane to be freed from the changed work. The owner argues that the changed work was performed while the crane was unoccupied, awaiting contractor structural repairs, thus the contractor was not delayed by the change.

Copyright © 2009 T.L. Martin & Associates Inc. Concurrency and other imaginings If the delay period can be reasonably apportioned between the various causes of delay, damages are generally apportioned as well. If the delay cannot be apportioned, than generally the contractor is given a non- compensable time extension.

Copyright © 2009 T.L. Martin & Associates Inc. Concurrency and other imaginings Multiple delays may occur to different activities along the same activity chain or among different activity chains at the same time or at different times. For example, the installation of underground utilities is delayed by poor performance of a subcontractor that then delayed critical foundation work. The owner delays steel fabrication due to late changes to the structural drawings.

Copyright © 2009 T.L. Martin & Associates Inc. Concurrency and other imaginings Even though the underground delay occurs first, the contractor can argue that the drawing changes will critically delay steel fabrication and delivery, thus the foundation work can slip until the steel is ready for delivery. The owner will argue that since the underground utilities delayed the foundations, it can use that delay period to revise the steel requirements.

Copyright © 2009 T.L. Martin & Associates Inc. Concurrency and other imaginings If the contractor argues the “why hurry up to wait” theory, generally it must: –demonstrate that it could have completed on time but for owner caused delay –and/or the Owner responsible delay was an overriding significant delay affecting related work rendering the then current schedule meaningless. (John Driggs Co., ENG BCA Nos. 4926, 5061, 5081, 87-2 BCA ¶ 19,833 at 100,388.)

Copyright © 2009 T.L. Martin & Associates Inc. Concurrency and other imaginings If multiple concurrent delays occur, the party claiming damages must provide a reasonable basis for apportioning delay between the parties. If the concurrent delays can not be segregated, then nether party can recover monetary damages from the other and an excusable but non-compensable time extension is granted to the contractor.

Copyright © 2009 T.L. Martin & Associates Inc. Concurrency and other imaginings The resource loaded CPM schedule, becomes an important tool as various delays are apportioned between the parties. Various tricks can play apart as well including: –imposed constraints on activities, –selected schedule calculation method, –resource leveling, –activity relationship exploitation, and –creating impractical periods of multiple critical paths.

Copyright © 2009 T.L. Martin & Associates Inc. Please continue with Chapter 6 Practical Methods to Reveal CPM Covert Activities