Presentation is loading. Please wait.

Presentation is loading. Please wait.

Reviewing & Analyzing Schedule

Similar presentations


Presentation on theme: "Reviewing & Analyzing Schedule"— Presentation transcript:

1 Reviewing & Analyzing Schedule
CTC-415

2 Reviewing the Schedule
Is Schedule complete Are Activity Duration Reasonable Are Activity Relationships Complete Are Activity Relationships Valid Is Project Calendar Correct Is Schedule Duration within Contract Time Are Contractual Milestones Met

3 Analyzing the Schedule
Is Critical Path Reasonable Are there Multiple Critical paths What Activities are Near Critical How does Work Flow Are there Conflicts Among Concurrent Activities Is there an Excessive amount of Work at any Time

4 Updating Schedule Frequency Depends on Complexity Unexpected events
More complex -> more updates Unexpected events Update after event to determine new completion date Helps team evaluate strategies to mitigate impacts When specified By contract documents

5 Updating Schedule How Gather Activity Status Info
Update Date – when the info is gathered Activity status Actual start date – meaningful work begins % complete Work in place -> work in place/planned work quantity Time expended -> time expended/ planned duration (only good for time dependent activities like concrete curing) Cost Incurred - >cost incurred/planned cost (depends on actual resource productivity being constant and resource costs not varying) Resource used -> Resource Used/Planned resource amount

6 Updating Schedule How Activity status Gathering Data
Remaining duration – Remaining Work quantity/Anticipated Productivity Actual finish date – all completed activities Provides data for future jobs Gathering Data Direct observation, Update meetings, field reports, turnaround reports, photos and videotape

7 Modify and Revise Schedule
Revise network logic Change duration to meet contracted completion Reflect changes in planned means and methods for completing activity Shift activity to better time (summer for concrete)

8 Modify and Revise Schedule
Revise Activity Durations Planned quantity of work has changed Amount of resources has changed Productivity is either higher or lower than planned Add & Delete Activities Scope of work changed Activities divided into smaller activities

9 Review and Analyze Schedule
Make sure new schedule does not contain errors Implement updated schedule

10 Analyzing Schedule Status
What is the basis for evaluating schedule status? Usually the original schedule is the baseline What is planned completion date Is updated schedule completion date same as baseline If not – why not (is there an error)

11 Analyzing Schedule Status
Has the critical path shifted? If so – why Are CP activities really “critical” Has the float changed on any activities? Has weather become a factor for any activity Are there trends worth watching Any changes since last update?

12 Out of Sequence Work Why? Preserve Schedule Logic Keep crews busy
Preparatory work starts early Gives crew a chance to test means and methods Preserve Schedule Logic Shorten successor activity caused by out of sequence work Keep all other logic intact

13 Value Engineering Provides alternatives to the proposed design
Save Owner $$ Must be as good or better than original design Must save enough $$ so that contractor can recover his cost of doing VE Usually comes from contractor’s or engineer’s previous experience

14 Value Engineering Can save $$ either due to savings in time or materials Ex: Composite Wall and roofs Material cost per sf is higher than regular roof Labor cost is lower Requires a crane

15 Value Engineering Ex: Replace infiltrators with Eljen In drains
System size is reduced to 50% Also reduces amount of sand, clay, topsoil Reduces dozer time and installation time In-drain costs about 2x infiltrator


Download ppt "Reviewing & Analyzing Schedule"

Similar presentations


Ads by Google