1 05/14/2009 PHENIX WEEKLY PLANNING 5/14/2009 Don Lynch.

Slides:



Advertisements
Similar presentations
1 4/9/2009 PHENIX WEEKLY PLANNING 4/9/2009 Don Lynch.
Advertisements

1 6/25/2009 PHENIX WEEKLY PLANNING 6/25/2009 Don Lynch.
1 4/30/2009 PHENIX WEEKLY PLANNING 4/30/2009 Don Lynch.
2/2/20121 PHENIX WEEKLY PLANNING 2/2/2012 Don Lynch.
1 3/19/2009 PHENIX WEEKLY PLANNING 3/19/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/15/2007 Don Lynch. 2/15/207 Weekly Planning Meeting 2 Remaining Schedule StartComplete Cosmic Ray Run (Run 6.9)In Progress All.
2/9/20121 PHENIX WEEKLY PLANNING 2/9/2012 Don Lynch.
PHENIX WEEKLY PLANNING 5/17/2007 Don Lynch. 5/17/2007 Weekly Planning Meeting 2.
1 7/02/2009 PHENIX WEEKLY PLANNING 7/2/2009 Don Lynch No Meeting this week due to July 4 th holidays. Slides have been updated. Next planning meeting will.
1 3/12/2009 PHENIX WEEKLY PLANNING 3/12/2009 Don Lynch.
1 2/12/2009 PHENIX WEEKLY PLANNING 2/12/2009 Don Lynch.
1 1/22/2009 PHENIX WEEKLY PLANNING 1/22/2009 Don Lynch.
1 1/13/2011 PHENIX WEEKLY PLANNING 1/13/2011 Don Lynch No Meeting Today Due to snow shortened work week, today’s planning meeting has been cancelled. Slides.
1/5/20121 PHENIX WEEKLY PLANNING 1/5/2012 Don Lynch.
8/9/20121 PHENIX WEEKLY PLANNING 8/9/2012 Don Lynch.
1 3/5/2009 PHENIX WEEKLY PLANNING 3/05/2009 Don Lynch.
PHENIX WEEKLY PLANNING 4/10/2008 Don Lynch. 04/10/08 Shutdown ’08 Schedule Purge Flammable Gas, Magnet & DAQ TestsDone Remove lock-out & open shield wallDone.
1 4/2/2009 PHENIX WEEKLY PLANNING 4/2/2009 Don Lynch.
PHENIX WEEKLY PLANNING 3/8/2007 Don Lynch. 3/8/207 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Continues…. All Up Commissioning In Progress.
12/29/20121 PHENIX WEEKLY PLANNING 12/29/2011 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
1 2/26/2009 PHENIX WEEKLY PLANNING 2/26/2009 Don Lynch.
1 4/16/2009 PHENIX WEEKLY PLANNING 4/16/2009 Don Lynch.
PHENIX WEEKLY PLANNING 3/6/2008 Don Lynch. 3/6/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Technical Support /1/08 PHENIX WEEKLY PLANNING 5/1/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/27/2008 Don Lynch. 3/27/2008 Weekly Planning Meeting2 Shutdown ’08 Schedule CM Crane ReviewMar Purge Flammable Gas, Magnet.
5/1/ PHENIX WEEKLY PLANNING May 1, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 2/2/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 3/22/2007 Don Lynch. 3/22/2007 Weekly Planning Meeting 2 Schedule Re-Start 5 man shifts 3/20/07 Beam: blue ring 3/8/07, in yellow.
PHENIX WEEKLY PLANNING 1/10/2008 Don Lynch. 1/10/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going1/18 Gas.
1 7/23/2009 PHENIX WEEKLY PLANNING 7/23/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/9/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 9/14/06 Don Lynch. 9/14/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown '065/1/200612/8/2006.
PHENIX WEEKLY PLANNING 12/6/2007 Don Lynch. 12/6/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn GoingOn Going.
PHENIX WEEKLY PLANNING 3/23/06 Don Lynch. MPC Electronics MPC rack installed without cards. Cards to be installed As available and as access time is available.
1 05/07/2009 PHENIX WEEKLY PLANNING 5/07/2009 Don Lynch.
1 3/10/2011 PHENIX WEEKLY PLANNING 3/10/2011 Don Lynch.
PHENIX WEEKLY PLANNING 10/4/2007 Don Lynch. 10/4/2007 Weekly Planning Meeting 2007 PHENIX Shutdown October 2007: Finish MPC South Installation, replace.
PHENIX WEEKLY PLANNING 12/7/06 Don Lynch. 12/7/06 Weekly Planning Meeting 2.
1 12/30/2010 PHENIX WEEKLY PLANNING 12/30/2010 Don Lynch.
3/20/ PHENIX WEEKLY PLANNING March 20, 2014 Don Lynch.
1/26/20121 PHENIX WEEKLY PLANNING 1/26/2012 Don Lynch.
1 10/15/2009 PHENIX WEEKLY PLANNING 10/15/2009 Don Lynch.
1 05/21/2009 PHENIX WEEKLY PLANNING 5/21/2009 Don Lynch.
5/12/11 1 PHENIX WEEKLY PLANNING 5/12/2011 Don Lynch.
PHENIX WEEKLY PLANNING 3/15/2007 Don Lynch. 3/15/2007 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Done All Up Commissioning On Going Re-Start.
PHENIX WEEKLY PLANNING 3/02/06 Don Lynch. BLM Test.
Technical Support /15/08 PHENIX WEEKLY PLANNING 5/15/2008 Don Lynch.
5/24/20121 PHENIX WEEKLY PLANNING 5/24/2012 Don Lynch.
Technical Support /18/08 PHENIX WEEKLY PLANNING 12/30/2008 Don Lynch.
PHENIX WEEKLY PLANNING 5/7/2007 Don Lynch (Thursday is Monday this week)
1 12/17/2009 PHENIX WEEKLY PLANNING 12/31/2009 Don Lynch.
PHENIX WEEKLY PLANNING 1/31/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going Switch.
1 12/17/2009 PHENIX WEEKLY PLANNING 12/17/2009 Don Lynch.
1 5/19/2011 PHENIX WEEKLY PLANNING 5/19/2011 Don Lynch.
5/30/20131 PHENIX WEEKLY PLANNING 5/30/2013 Don Lynch.
1 1/29/2009 PHENIX WEEKLY PLANNING 1/29/2009 Don Lynch.
1 7/16/2009 PHENIX WEEKLY PLANNING 7/16/2009 Don Lynch.
3/7/20131 PHENIX WEEKLY PLANNING 3/7/2013 Don Lynch.
Technical Support /16/08 PHENIX WEEKLY PLANNING 10/16/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/1/2007 Don Lynch March: in like a lion Out like a lamb.
1 6/4/2009 PHENIX WEEKLY PLANNING 6/4/2009 Don Lynch.
1 7/9/2009 PHENIX WEEKLY PLANNING 7/9/2009 Don Lynch.
PHENIX WEEKLY PLANNING 6/8/06 Don Lynch. 6/8/2006 Weekly Planning Meeting 2 This Week Rec’d TOF West Access: move HBD to Dead Turtle Position Sec’y of.
1 8/20/2009 PHENIX WEEKLY PLANNING 8/20/2009 Don Lynch.
1 11/25/2010 PHENIX WEEKLY PLANNING 11/25/2010 Don Lynch.
2/20/ PHENIX WEEKLY PLANNING Feb. 20, 2014 Don Lynch.
1 2/19/2009 PHENIX WEEKLY PLANNING 2/19/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 2/14/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
1 2/4/2010 PHENIX WEEKLY PLANNING 2/4/2010 Don Lynch.
Presentation transcript:

1 05/14/2009 PHENIX WEEKLY PLANNING 5/14/2009 Don Lynch

2 05/14/2009 RPC Installation Crane Measurements RPC Installation Support measurements MuTrigger FEE South Cable Tray planning RPC3 N gap interferences planning HBD Troubleshooting Other Work? Next Maintenance Access Day – May 27 Anyone wishing to access the Tunnel either north or south of the IR should inform the RC at least 2 days ahead of time to coordinate with C-A-D. If you require technician assistance inform me as well. Yesterday’s Maintenance Access Day

3 05/14/2009 Upper Support Brackets needed here. Brackets to have up-down and east west adjustments And here

4 05/14/2009 Need to design and fabricate easier access (steps and platform) for work above MuID steel. StepsPlatform

5 05/14/2009 Shutdown ’09 Major tasks (expect 5 month shutdown): EOR party June 26/2009 shutdown Begins June 28 End run, remove wall, MuID collars down, EC to AH (3 weeks) RPC Factory Operations (in progress and continuing beyond Shutdown ’09) RPC Station 3 North (entire shutdown) Install Station 1 South scaffolding (1 week) Install Station 2/3 scaffolding (2 weeks) Install stations 1, 2 and 3 south MuTrigger FEE’s (12 weeks) MuTr decapacitations: station 3 south (3 weeks) PC1 East repair (4 weeks) Mechanical/Electrical Plumbing installation of (4) new DCM racks Add Ar Dewar and expand gas pad to add storage (12 weeks) Prep for future upgrades/existing equipment maintenance & Repair (as necessary) Shutdown ’09

6 05/14/2009 Shutdown Prep Now to June 28 TaskComplete By RPC Installation design parts & ToolsMay 15 RPC Electronics Rack PrepJune 20 RPC Installation parts and Tools FabricationJune 28 MuTrigger FEE Parts and Tools orderingJune 28 MuTrigger FEE Cable Management planJune 15 RPC3 N Cable and Piping relocation PlanJune 15 RPC Factory Tools complete and commissioned June 28

7 05/14/2009 End of Run, Start of Shutdown TaskCompletion Date End of Run Party6/26 End of Run 96/28 Flammable Gas Purge6/30 Open Wall and Disassemble7/2 MuID Collar Removal7/8 Move MMS South7/10 Test RMC Higher comm speed on EC before disconnecting7/15 Disconnect EC and move to AH7/17 Move MuID Collars to AH7/20 Install IR floor plates, rolling cart & manlift in IR7/22 Reconnect EC for shutdown mode7/24 Remove East/West vertical & Upper Bias MMS lampshades 7/24

8 05/14/2009 RPC Factory Operations Gap and Module assembly and testing in-progress (continues through shutdown) Gap and Module Storage with humidity control Nearly complete (need to get permanent elec., 2 nd humidity controller & covers for last 3 storage racks) Tilting transport Table Nearly complete Burn in test stand (Bike rack section) In Progress Burn-in test stand gas system and controls 5/29 (ready for 1 st half octant) Assembly of half-octants for station 3 north 6/1-9/1

9 05/14/2009 RPC Factory

10 05/14/2009 RPC Factory Burn In Test Station For Octant and Half Octant Burn-in Tests Assembly to begin soon

11 05/14/2009 RPC3 North Installation Schedule TaskCompletion Date Installation Concept FinalizedApr. 24 Half-Octant Brackets, Connecting Blocks, under detector translating support designApr. 30 Installation Fixturing and Tooling DesignMay 15 Redesign crystal palace/IR Gas BarrierMay 29 End of Run 9 June 28 Fixturing/Tooling, Brackets/Block/support FabricationJune 30 Move Shielding/Remove Crystal PalaceJune 29-July31 Move cable trays and piping in gap 5June 29-July 31 Simulated (practice) installation with new fixturing/ toolingJuly 13-July 31 Install, level & survey support structure Aug. 3 - Aug 14 Half Octant Testing and Assembly Complete Aug. 17- Sep. 18 (1 st half Octant ready by Aug.17, 16 th by Sep.18) Mechanical Install Align & survey RPC3 N Aug 17 – Sep. 30 Install 3 elect. Racks, all cables & gas systemOct. 1 – Oct. 30 Commissioning Nov. 1 – Nov. 30 Install new crystal palace/IR Gas Barrier & ShieldingNov. 1 – Nov. 30 Start Run 10Dec. 1

12 05/14/2009 After the base support structures have been installed, Install the unistrut guide rails at the pedestal and at beam height levels and +/- ~ 6 ft from beam height on east and west tunnel walls as shown. These rails will be used to prevent pitch rotation (about the horizontal axis perpendicular to the beamline [X-axis]). In addition there will be 4 sets of adjustable brackets above the MuID Steel adjacent to gap 5 and corresponding to the upper bracket ears on Half-octants HO_8 east and HO_8 west. Above gap 5 steel beam height & +/- 6 ft from Beam height Along top of pedestal Note: This view looks thru MuID Steel which has been made transparent for this representation beam height & +/- 6 ft from Beam height

13 05/14/2009 After HO1 west is installed, the clamp shown is used to keep the HO stable in the vertical configuration. Clamp is idealized actual clamp will have adjustments to align the pitch angle. Note: These views look thru MuID Steel which has been made transparent for this representation Clamp Unistrut low profile rail

14 05/14/2009 View angle reversed for clarity Long Column attached to vertical unistrut guide rail here HO_3 attached to vertical unistrut guide rail here Vertical and horizontal unistrut guide rails attached by double ended rollers here

15 05/14/2009 Half Octant West #4 View looking thru MuID steel plates which have been made transparent. After HO_4 is positioned onto HO_3, inner angled connector at inner 3-4 joint is bolted, inner straight connector has been unbolted from lifting fixture and remains in place to accept HO_5. At outer face lower brackets have been locked into angled bracket at outer 3-4 joint and straight bracket remains in place to accept HO_5. West sliding base is slid west 60” and clamp is attached to the outer face of HO_4 and positioned to slide in the mid plane unistrut channel. After the clamp is attached slide the base back to the 0 position Sliding clamp

16 05/14/2009 Half Octant West #4 View looking thru MuID steel plates which have been made transparent. After HO_4 is positioned onto HO_3, inner angled connector at inner 3-4 joint is bolted, inner straight connector has been unbolted from lifting fixture and remains in place to accept HO_5. At outer face lower brackets have been locked into angled bracket at outer 3-4 joint and straight bracket remains in place to accept HO_5. West sliding base is slid west 60” and outer mounting bracket is attached to vertical unistrut guide After the bracket is attached, slide the base back to the 0 position Sliding clamp

17 05/14/2009 Half Octant West #8

18 05/14/2009 Half Octant West #7

19 05/14/2009 Half Octants HO_1 East through HO_4 East are installed similarly to their wester counterparts.

20 05/14/2009 HO_8 East and HO_7 East are installed similarly to their western counterparts.

21 05/14/2009 MuTrigger FEE South TaskCompletion Date Install Station 1 South Scaffold (carpenters) 7/31 Install Station 1 cable management 8/14 Install station 2/3 scaffolding (Techs) 8/14 Install station 1 FEE’s & Electronics 8/28 Install station 2 & 3 cable mngment 8/28 Station 1 plumbing 9/11 Install station 2/3 FEE’s & electronics 9/25 Station 2/3 plumbing 10/9

22 05/14/2009 MMS scaffolding Designed for MuTr installation. Approved in 2000 for use. Stress analysis done for worst case. Current design has minor modifications. Concept approved at C-A Design Review Met with Donna Dowling to discuss Bargaining Unit negotiations

23 05/14/2009 MuTr Decapacitations Task Completion Date Station 2/3 Decaps8/14-8/28 Testing/verification9/4

24 05/14/2009 PC1 East Repair TaskCompletion Date Design Repair support fixtureDone Review and approvalDone Fabrication7/1 (order placed) Install support fixture8/14 Remove cables and plumbing 8/28 Roll out DC/PC19/4 Replace failed PC19/11 Roll DC/PC1 in9/18 Restore cables and plumbing 9/25 Test/commissioning10/2

25 05/14/2009 PC1 East Repair Fixturing Design Repairs to be performed during ’09 Shutdown New Column Supports Under railway extensions New Railway extensions will allow DC to be pulled out ~ 3 feet more Access to PC1 is adequate to remove and replace module Quote Rec’d from CS

26 05/14/2009 Gas Pad Expansion, New Argon Dewar TaskCompletion Date Proposal Done Review and Approval5/1 Design6/1 Site Preparation7/1 Install Empties racks8/1 Install Ar Dewar9/1 Test and Commission10/1 (Rough guess actual schedule TBD)

27 05/14/ ’20’ New storage pad for empty gas cylinders, 20’x 20’, 9” min thick. reinforced concrete New Argon Dewar Pad, 16’ x 20’, 12” minimum thickness, reinforced concrete. New Argon Dewar Met with Dave Phillips to walk thru the plan

28 05/14/2009 New DCM Rack Plumbing (Not Scheduled Yet) 4 new DCM racks need cooling water plumbing

29 05/14/2009 Other Work Upgrades Support: New Beampipe sections (non-Be) (Sent Drawings to Mike Mapes) New Beampipe supports FOCAL prototype design support VTX fabrication tooling design VTX installation design FVTX design/eng’g support Summer Sunday Prep TBD Existing Detector Maint & Repairs Maintenance & Overhead Tasks Rack Room Reorganization C-A-D AC, Water System, Electrical system work which may impact shutdown schedule:Tasks, schedules, priorities TBD

30 05/14/2009 Roof leaks in utility bathroom at northwest corner behind tech offices and over door between rack room and assembly hall. Heat wrap tape for trailer bathroom toilet drains to prevent freeze/clogging in winter. Improved Rack Room AC performance (This item has been addressed time and again but unsatisfactorily. Currently the AC fails periodically and is repaired only to fail again. On-condition maintenance is not adequate…an engineered solution is needed.) Icy conditions at mixing house north stairs 2009 Building Maintenance Issues

31 05/14/2009 Safety, Security, etc. PHENIX Safety Goals for this years shutdown: 1. Injuries - (First Aid) Injuries - (Reportable) Injuries - (DART) Near misses Injuries avoided due to good planning - All Safety is everyone’s responsibility. We plan so we stay safe.

32 05/14/2009 Where To Find PHENIX Engineering Info Links for the weekly planning meeting slides, archives of past meeting slides,long term planning, pictures, videos and other technical info can be found on the PHENIX Engineering web site: Its going to be a busy summer, so get on board with your work requests now.