1 PRR 776 in the Context of the ERCOT Market Design Eric S. Schubert Regulatory Affairs Advisor BP Energy Company.

Slides:



Advertisements
Similar presentations
Achieving Price-Responsive Demand in New England Henry Yoshimura Director, Demand Resource Strategy ISO New England National Town Meeting on Demand Response.
Advertisements

EMIG Electricity Market Investment Group Presentation to the Ontario Energy Board February 17, 2004.
INSULATING PRICE RESPONSIVE LOAD FROM RUC CAPACITY SHORT CHARGE Mark W. Smith J. Kay Trostle August 2008 DSWG.
Gloria Godson VP, Federal Regulatory Policy Reliability Pricing Model Part 2.
QSE Managers Working Group Meeting Notes 9 April, 2010 Report to WMS 21 April, 2010 David Detelich - Chairperson.
1 July 15, 2007Alcoa Energy Regulatory Affairs NARUC / FERC Demand Response Collaborative Perspectives of a Large End Use Participant of NYISO Programs.
Market Operations Presentation Board of Director’s Meeting November 18, 2003.
Demand Response in New York State Northwest Power and Conservation Council DR workshop February 24, 2006.
Energy Storage Definitions/Definitions ETWG 18 Feb 2013.
NARUC-FERC Demand Response Collaborative Meeting NARUC Fall Meeting Anaheim, CA T. Graham Edwards President & CEO November 11, 2007.
Reliability Risks and Lessons Learned In The Wake Of The Polar Vortex OPSI Annual Meeting October 14, 2014.
MISO’s Midwest Market Initiative APEX Ron McNamara October 31, 2005.
1 Presentation to the Wisconsin Industrial Energy Group (WIEG) T. Graham Edwards President & CEO August 9, 2007.
1 TAC Review of PRR 650 August 3, Board Charge to TAC Board remanded PRR 650 to TAC for: “an analysis of how to ensure that consumers pay only.
LTTR, FCM, RPM, MRTU: Do More Acronyms Mean Better RTO Markets? An Overview of Various RTO Capacity Constructs and their Impact on Load.
Utility Regulation March 10, 2011 Raj Addepalli Deputy Director, Electric, Office of Electric,Gas and Water New York State Department of Public Service.
The Convergence of Market Designs for Adequate Generating Capacity Peter Cramton and Steven Stoft 24 March 2006.
A Capacity Market that Makes Sense Peter Cramton & Steven Stoft 18 March 2005.
The Continuing Evolution of U.S. Electricity Markets
North American Electricity Markets APEX Paris, France October 15-16, 2007 Kenneth Laughlin, PJM.
Demand Response in MISO Markets NASUCA Panel on DR November 12, 2012.
John Dumas Director of Wholesale Market Operations ERCOT Operating Reserve Demand Curve.
ERCOT Public 1 AS Demand Curves for Real-Time Co-optimization of Energy & Ancillary Services.
Reliability Pricing Model (RPM) Overview Andrew Ott PJM Senior Vice President, Markets.
Floyd Trefny Director of Product Development Future of Demand Response In ERCOT A Presentation to the Workshop – September 15, 2006 Project Number
World Forum on Energy Regulation IV Athens, Greece October , 2009 "Reducing Regulatory and Technological Barriers to Demand Side Participation“
Demand Response in Midwest ISO Markets February 17, 2008.
32853 Evaluation of Demand-Response Programs in the Competitive Electric Market Workshop 1 September 15, 2006 Shawnee Claiborn-Pinto.
Reactive Power Federal Energy Regulatory Commission Open Meeting December 15, 2004.
1 Capacity Markets Investment in Generation Capacity Payments October 31, 2005 J. W. Charlton.
Wholesale Electricity Market – Western Australia APEx Conference 2008 – Sydney Allan Dawson 13 October 2008.
“Demand Response: Completing the Link Between Wholesale and Retail Pricing” Paul Crumrine Director, Regulatory Strategies & Services Institute for Regulatory.
Demand Response Workshop September 15, Definitions are important Demand response –“Changes in electricity usage by end-use customers from their.
PRS - RPRS Task Force Status Summary - August 14, PRS RPRS Task Force Status Summary Prepared for WMS and PRS August 2006.
Review of Proposed Zonal Market Improvements ERCOT Board of Directors Meeting February 17, 2009 Dan L. Jones Potomac Economics Vice President Director,
RPRS ERCOT System Wide Insufficiency Charge Presented at the Technical Advisory Committee June 1, 2006.
Long Term Solution Task Force TAC Report 5/5/07 Presented by: Bob Wittmeyer - LTSTF Co-Chair.
PJM©2013www.pjm.com Economic DR participation in energy market ERCOT April 14, 2014 Pete Langbein.
Report to TAC August In Brief Working Group Reports Working Group Reports CMWG CMWG DSWG (No report) DSWG (No report) MCWG MCWG MWG (No report)
Capacity mechanisms in Europe The fundamental issues behind the ongoing sector enquiry Session 2 - If a capacity mechanism, which design is most appropriate?
1 CRR Credit Policy Task Force Update WMS April 16, 2008.
Review of CAISO Wholesale Electricity Market Trends APEX Sydney Conference California Electricity Wholesale Market Trends October 13, 2008 Anjali Sheffrin,
1 Market Evolution Program Long-Term Resource Adequacy Regulatory Affairs Standing Committee Meeting May 14, 2003.
1 Reliability Deployment Task Force (RDTF Meeting) December 20 th 2011 December 20, 2011.
1 WMS Report TO TAC January In Brief Two Working Group Reports Two Working Group Reports Two Task Force Reports Two Task Force Reports One PRR.
PJM© Demand Response in PJM 2009 NASUCA Mid-Year Meeting June 30, 2009 Boston, MA Panel: Price Responsive Demand – A Long-Term Bargain.
PJM © 2006 The Institute for Regulatory Policy Studies Illinois State University Conference May 12, 2006 Jeff Bladen PJM Interconnection.
Resource Adequacy Task Force (RATF) Update to WMS June 12, 2013.
October 02, 2009 Austin, Texas Quick Start Task Force Meeting 1.
Load Resources Negative RRS Bidding in the Nodal Market Credit Working Group January 30, 2008.
OPSI Annual Meeting October 13, Session 6 Reliability Pricing Model: Are Further Changes Necessary? Reluctantly…yes But States should also be.
©2003 PJM North American Markets Status APEx Seoul, Korea October 29-31, 2006 Kenneth W. Laughlin.
Conference on Standard Market Design Issues Alice Fernandez, FERC Staff January 22-23, 2002.
SAWG Update to WMS September 2 nd, 2015 Brandon Whittle.
1 WMS Report TO TAC April In Brief Two Working Group reports Two Working Group reports Two Task Force Reports Two Task Force Reports BENA presentation.
NPRR 649 Addressing Issues Surrounding High Dispatch Limit (HDL) Overrides Katie Coleman for Air Liquide (Industrial Consumer) ERCOT Board February 9,
ERCOT Update on Day-Ahead Extract and other PUCT Posting changes DEWG Meeting 10/29/07 Matt Mereness.
1 Market Evolution Program Day Ahead Market Project Regulatory Affairs Standing Committee Meeting May 14, 2003.
The Wholesale Market Subcommittee Update Prepared for the July 31st TAC meeting.
1 WMS Report To TAC October In Brief One Working Group Report One Working Group Report One Task Force Report One Task Force Report Three Staff.
07/27/2006 Overview of Replacement Reserve Procurement ERCOT Staff PRS RPRS Task Force.
1 TAC Report to the ERCOT Board July 18, TAC Summary 4 PRRs for approval (3 unanimous) 4 PRRs for approval (3 unanimous) 5 Nodal PRRs for approval.
CRR Default and the Nodal Market Wholesale Market Subcommittee February 20, 2008.
Long-term Solution Task Force Ellis Rankin & Bob Wittmeyer Co-Chairs.
Long Term Solution Task Force TAC Report 5/5/07 Presented by: Bob Wittmeyer - LTSTF Co-Chair.
FERC Standard Market Design Working Papers
Asia-Pacific Energy Regulatory Forum
PRS Rejection of NPRR Mitigated Offer Caps for RMR Units
Resilience and Reliability in PJM’s Competitive Markets
Benefits of New England’s Proposed Capacity Market
Presentation transcript:

1 PRR 776 in the Context of the ERCOT Market Design Eric S. Schubert Regulatory Affairs Advisor BP Energy Company

2 Concerns about PRR 776 PRR 776 could undermine successful ERCOT energy-only market design Unintended consequences of proposal – PRR 776 could be problematic Ancillary service procurement Real-time reliability Long-term resource adequacy – Demand-response justification likely undermined by the consequences of parameters in PRR 776 Haste makes waste – Very little debate and review of proposal relative to market impact – RDF proposal was significantly improved by being remanded

3 Pricing in the ERCOT Balancing Energy Market Limited debate over PRR 776 has shown some potential misunderstandings – “Spot market prices always settle at short-run marginal costs in other U.S. markets” – “High offers by generators that cause high MCPEs in ERCOT are inappropriate” Need to put market offers and clearing prices in ERCOT into larger perspective

4 Resource Adequacy in Non-ERCOT Markets in the United States Loads: Mandatory contracting to cover spot market exposure – Centralized capacity auction (PJM, ISO-NE; 3-5 years ahead) – Bilateral capacity contracts (MISO: 30 days or more ahead) Generators: Mandatory participation in spot market – Earn revenues above their marginal costs outside the spot market – Accept a “must-offer” requirement into spot market Loads cover investment risk of generators in exchange for limited price risk associated with real-time redispatch FERC has recognized the need for shortage pricing to maintain – Reliability in real-time – Resource adequacy in the long run

5 Resource Adequacy in the ERCOT Market Resource adequacy mechanism in PUCT Substantive Rules and is unique within the U.S. – Allows retail and wholesale markets flexibility in contracting by placing Investment risk on generators Price risk on loads – Addresses system-wide market power through “small fish swim free” During the rulemaking process, the PUCT was told by – Retailers and industrial loads that they would accept price risk to avoid capacity payments seen in PJM – Generators would accept investment risk if they were allowed to make offers above short-run marginal costs Resource adequacy in ERCOT functions when investment risk for generators and price risk for loads are in rough balance “Small fish swim free” approach was approach chosen by PUCT to balance investment risk and price risk

6 Unintended Consequences of PRR 776 Disrupts balance between price risk and investment risk Artificially lowers spot price – Resource Adequacy impact: Reduces ability of generators to cover their fixed costs – Reliability impact: Increases demand and lowers supply for real-time energy Forces ERCOT to procure more RPRS – Increase uplift to loads because of a lack of direct assignment of RPRS procurement costs – Loads that short the market will have other loads pay for starting generation that was out of the money

7 Demand Side Fallacy Beginning Nov. 1 st, NSRS has been procured for all intervals – The $175 cap could serve as a de facto hard price cap for the real-time market – ERCOT will procure RPRS or OOMC to cover the shortfall – If RPRS or OOMC is procured, real-time price for energy often falls and undermines the price signal needed for demand response

8 PRR 776 Could Endanger ERCOT Energy-Only Market ERCOT is unique – Allows loads to prudently manage their contracts up to real- time – Designed to work with successful ERCOT retail market There is no free lunch for loads that want to chronically short the market – Greatly upsets the balance between supply and demand, price risk and investment risk – Alternatives to current market design would greatly reduce the ability of loads to manage risk through voluntary bilateral contracting

9 Requested Action by TAC Remand PRR 776 to WMS on a timeline to address issues Review tradeoffs in ancillary service pricing, uplift, reliability, and long-term resource adequacy Work with ERCOT staff and ERCOT IMM to determine software capabilities and parameter estimates