P ROJECT M ANAGEMENT, PMI A PPROACH (PMP) P ROJECT T IME AND S CHEDULE M ANAGEMENT Sayed Ahmed BSc. Eng. in CSc. & Eng. (BUET, Bangladesh) MSc. in CSc.

Slides:



Advertisements
Similar presentations
CP Chapter 4 Schedule Planning.
Advertisements

Work Breakdown Structures
Advanced Project Management - CPH
Chapter 10: Project Schedule Planning
Defining activities – Activity list containing activity name, identifier, attributes, and brief description Sequencing activities – determining the dependencies.
PMP/CAPM Prep Workshop Time
Chapter 6: Project Time Management
Eleanor Roosevelt High School
Managing Project Scheduling. What is Project Scheduling? The process of: – defining project activities – determining their sequence – estimating their.
Project Time Management
P ROJECT M ANAGEMENT, PMI A PPROACH (PMP) P ROJECT C OMMUNICATIONS MANAGEMENT Sayed Ahmed BSc. Eng. in CSc. & Eng. (BUET, Bangladesh) MSc. in CSc. (University.
Introduction to Project Management Chapter 6 Managing Project Scheduling Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George.
BSBPMG503A Manage Project Time 6.5 Develop Schedule The process of analysing activity sequences, durations, resource requirements and schedule constraints.
Project Management. What is a Project? One Time Effort Identifiable Start/End Points Specific Objectives Multiple Tasks Resources from Across the Organization.
Project Time Management
Importance of Project Schedules
Project Time Management
Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 6 Project Time Management.
This work is licensed under a Creative Commons Attribution 3.0 Unported LicenseCreative Commons Attribution 3.0 Unported License (CC-BY). Project Management.
Managing Project Scheduling. What is Project Scheduling? The process of: – defining project activities – determining their sequence – estimating their.
P ROJECT M ANAGEMENT, PMI A PPROACH (PMP) P ROJECT C OST M ANAGEMENT Sayed Ahmed BSc. Eng. in CSc. & Eng. (BUET, Bangladesh) MSc. in CSc. (University of.
The Critical Path – Precedence diagram method Luise Lorenz Christina Mohr.
P ROJECT M ANAGEMENT, PMI A PPROACH (PMP) P ROJECT H UMAN R ESOURCE M ANAGEMENT Sayed Ahmed BSc. Eng. in CSc. & Eng. (BUET, Bangladesh) MSc. in CSc. (University.
HIT241 - TIME MANAGEMENT Introduction
Time Management Week 7 - Learning Objectives You should be able to: n List and describe the processes, activities, inputs, and outputs in time management.
Chapter 6: Project Time Management Information Technology Project Management, Fifth Edition Note: some slides have been removed from the author’s original.
Scheduling Sequence & Time.
TIME MANAGEMENT Definition: Time management is a set of principles, practices, skills, tools, and systems that work together to help you get more value.
Chapter 6: Project Time Management
POST GRADUATE PROGRAM OF INFORMATION TECHNOLOGY
P ROJECT M ANAGEMENT, PMI A PPROACH (PMP) P ROFESSIONAL R ESPONSIBILITY OF P ROJECT M ANAGERS Sayed Ahmed BSc. Eng. in CSc. & Eng. (BUET, Bangladesh) MSc.
~ pertemuan 6 ~ Oleh: Ir. Abdul Hayat, MTI 03-Apr-2009 [Abdul Hayat, Project Time Management, Semester Genap 2008/2009] 1 PROJECT TIME MANAGEMENT.
Lecture 7. Review of Lecture 6 Project Scheduling: The process of defining project activities, determining their sequence, estimating their duration Scheduling.
Managing Project Resources. Project Resources Human Resources Project stakeholders: – Customers – Project team members – Support staff Systems analyst.
Lecture 6. Review of Lecture 5 Company strategic planning: mission and objective statements and competitive strategy. Planning Methods: Top-down, Bottom-up.
Chapter 6: Project Time Management Information Technology Project Management,
1IT Project Management, Third Edition Chapter 6 Chapter 6: Project Time Management.
P ROJECT M ANAGEMENT, PMI A PPROACH (PMP) P ROJECT I NITIATION P HASE Sayed Ahmed BSc. Eng. in CSc. & Eng. (BUET, Bangladesh) MSc. in CSc. (University.
Advanced Project Management Project Time Management Ghazala Amin.
Collecting requirements – Different methods Defining scope – Estimates for all resources Creating the WBS – Different approaches Verifying scope – Formal.
P ROJECT M ANAGEMENT, PMI A PPROACH (PMP) P ROJECT I NITIATION P HASE Sayed Ahmed BSc. Eng. in CSc. & Eng. (BUET, Bangladesh) MSc. in CSc. (University.
Chapter 6: Project Time Management Information Technology Project Management, Fourth Edition Using Critical Path and MS Project 2003 Tuesday, February.
Project Time Management Ashima Wadhwa. Schedule Development – Determining start and finish dates for project activities – Without realistic dates, project.
Project Time Management
P ROJECT M ANAGEMENT, PMI A PPROACH (PMP) P ROJECT R ISK MANAGEMENT Sayed Ahmed BSc. Eng. in CSc. & Eng. (BUET, Bangladesh) MSc. in CSc. (University of.
P ROJECT M ANAGEMENT, PMI A PPROACH (PMP) Sayed Ahmed BSc. Eng. in CSc. & Eng. (BUET, Bangladesh) MSc. in CSc. (University of Manitoba, Canada)
SOFTWARE PROJECT MANAGEMENT
Chapter 4 Note: See the text itself for full citations.
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
BSBPMG503A Manage Project Time Manage Project Time Project Time Processes Part 2 Diploma of Project Management Qualification Code BSB51507 Unit Code.
Project Time Management Based on PMBOK 5 th Edition Abdelrahman Sheta, PMP,ITIL 1PMP - Project Time Managementfacebook.com/Sheta.Page.
© 2008 Prentice Hall6-1 Introduction to Project Management Chapter 6 Managing Project Scheduling Information Systems Project Management: A Process and.
Project Management MGT 30725
Introduction to Project Management Chapter 7 Managing Project Resources Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George.
Plan Schedule Management
Eleanor Roosevelt High School
Based on the PMBOK® Guide 3rd Edition
Chapter 6: Project Time Management
CHAPTER 6 PROJECT TIME MANAGEMENT
PROJECT TIME MANAGEMENT
Project Time Management
Project Time Management
Project Time Management
Project Time Management
Project Time Management
Importance of Project Schedules
Project Time Management
CHAPTER 6 PROJECT TIME MANAGEMENT
Presentation transcript:

P ROJECT M ANAGEMENT, PMI A PPROACH (PMP) P ROJECT T IME AND S CHEDULE M ANAGEMENT Sayed Ahmed BSc. Eng. in CSc. & Eng. (BUET, Bangladesh) MSc. in CSc. (University of Manitoba, Canada) Just E.T.C for Business, Education, Technology, and Entertainment Solutions Resources: Book: PMP in Depth by Dr. Paul Sanghera Book: The PMP Exam, How to Pass on Your First Try By Andy Crowe Project Management Lessons in Undergraduate Study Work Experience

R EFERENCES & R ESOURCES Book: PMP in Depth by Dr. Paul Sanghera Read on 2007 Book: The PMP Exam, How to Pass on Your First Try by Andy Crowe Read on 2007 A Project Management lessons in undergraduate study Articles from the Internet Work Experience 2

L EARNING O BJECTIVES 3

O UR S ERVICES 4

P ROJECT T IME M ANAGEMENT P ROCESS 1. Define Activities Required 2. Sequence Activities 3. Estimate Resources for the Activities 4. Calculate Duration of the Activities 5. Develop Schedule 6. Control Schedule 5

P ROJECT T IME M ANAGEMENT P ROCESS Process: Define Activities Required List all the activities functionalities modules components That you want to develop When the project scope is defined use it to decompose the work into activity list Work breakdown structure will be useful at this stage List what modules, components the project will handle 6

P ROJECT T IME M ANAGEMENT P ROCESS Process: Define Activities Required List all the functionalities/activities that are required for each of the modules/components For each activity define properties assumptions quality requirements and output requirements Input : Define Activities Required Project scope statement Work breakdown structure Output : Define Activities Required Project activities [activity list] Activity attributes milestone list requested changes 7

P ROJECT T IME M ANAGEMENT P ROCESS Process: Define Activities Required Tools Decomposition Decompose work into smaller activities. Project team or the functional manager may be of good use here Templates The Company may have them other project may have them and some standards like IEEE may define some templates Rolling Wave Planning Many later aspects of the project may not be understood at the beginning Hence, initially decompose as much as possible and later with the progress, improve the decomposition Expert Judgment Take help of other experts in the field Project team or the functional manager may be of good use here 8

P ROJECT T IME M ANAGEMENT P ROCESS Process: Sequence Activities Find the order/sequence of the activities Some activities may be dependent on the completion of another activity – find them Some modules may be dependent on the completion of another module – find them Sometimes, it may be the case some activities/modules are not strictly dependent on another activity but may be preferable to start after another activity/module [Best Practice] Find them In this step, you need to find the sequence and then create a project network diagram Note module refers to a complete unit/component where each module may have many activities 9

P ROJECT T IME M ANAGEMENT P ROCESS Process: Sequence Activities Input Mostly from the first step Project scope statement Activity list Activity Attributes Milestone List Approved change requests 10

P ROJECT T IME M ANAGEMENT P ROCESS Process: Sequence Activities Tools Precedence Diagram Method (PDM) Activities are represented by the nodes where arrows represent the dependencies that exist between the activities Arrow Diagramming Method (ADM) Activities are represented using arrows where nodes represent the connection points We can create dummy activities with dotted arrows [not possible in PDM] 11

P ROJECT T IME M ANAGEMENT P ROCESS Process: Sequence Activities Tools Graphical Evaluative Review Technique (GERT): Like the PDM diagrams. Additionally, you can show dependencies among activities. Also, you can represent repeated processes. Network Templates: Sub networks of another project in the organization may be useful. Dependency Determination: like mandatory dependencies [you can not break the dependency] discretionary dependencies [best practices, the dependency is not strict], and external dependencies [out of the scope of the project]. Apply leads and lags: 12

P ROJECT T IME M ANAGEMENT P ROCESS Process: Sequence Activities Output Project schedule network diagram 13

P ROJECT T IME M ANAGEMENT P ROCESS Process: Estimate Resources for the Activities 3rd: Then you need to identify the resource requirements of each activity Process: Calculate Duration of the Activities 4th: Estimate duration for each activity It may be experience based practical examples based another completed project based mathematical analysis based Process: Develop Schedule 5th: Develop the schedule Project sequencing and time estimating will directly affect this Several projects may require the same resource Hence, the schedule should check when the resource is available and schedule accordingly Process: Control Schedule 6th: Monitor how the schedule is performing 14

P ROJECT S CHEDULE D EVELOPMENT In this phase, the following are determined Project duration Project finish date Schedules of the activities Input to the Phase Activity List Activity Attributes Project Schedule Network Diagrams Activity Duration Activity Resource Requirements Resource Calendars 15

P ROJECT S CHEDULE D EVELOPMENT Tools Critical Path Model (CPM) CPM is extensively used to determine the project duration CPM method also helps to identify how much individual activities can slip without affecting the total duration of the project Crashing and Fast tracking Crashing tries to add more resources into the project to ensure that the project will be finished on time or early. [Note: Fred's theory: adding resources to an already delayed project will/may increase the delay] Fast tracking tries to run multiple activities in parallel to ensure that the project will be finished on time or early Resource Leveling Apply the resource availability [and quantity] to the project duration It may increase the project duration when sufficient resource [in quantity or at the right time] is not available. 16

P ROJECT S CHEDULE D EVELOPMENT Critical Chain Method It is almost similar to the Critical Path Method Critical path method uses a concept called float CPM first calculates the total duration and then calculates float [ HOW MUCH IT CAN SLIP ] FOR EACH ACTIVITY CPM ensures that no activity exceeds its float In Critical Chain Method LATEST POSSIBLE START AND LATEST POSSIBLE FINISH DATES ARE DETERMINED FOR EACH ACTIVITY A FTERWARDS, BUFFERS ARE ADDED BETWEEN ACTIVITIES T HE GOAL IS NEVER TRY TO EXCEED THE BUFFER Company Calendar C OMPANY C ALENDARS MAY BE USED TO CHECK THE COMPANY HOLIDAYS, OR EVENTS that may affect the project duration/schedule Adjusting leads and lags 17

S TEPS IN CPM M ODEL Using CPM Model [steps] 1. CPM uses the arrow diagram method [activities and duration on arrows, nodes as connectors] to represent project activities and duration. 2. After building the diagram find the critical path [the path that takes the longest time from start to finish considering all alternatives] 3. Calculate float how much an activity can slip without affecting the critical path. 4. Calculate Early start The earliest date an activity can start considering the dependencies 5. Calculate Early finish Early start date + duration –

S TEPS IN CPM M ODEL 6. Calculate Late Start: What is the last date an activity can start considering the dependencies 7. Calculate Late Finish: Late start date + duration – 1 8. Calculate Free Float: Amount of time an activity can be delayed without affecting the dependent activities' early start date 9. Calculate Negative Float: Occurs when an activity's start date occurs before a preceding activity's finish date When you have calculated all the values the values will help greatly in the schedule control 19