MANA 705 DL © Sistema Universitario Ana G. Méndez, 2011. All rights reserved. W6 6.2 Operation Management Operation Management Managing Projects Techniques.

Slides:



Advertisements
Similar presentations
3 Project Management PowerPoint presentation to accompany
Advertisements

WBS: Lowest level OBS: Lowest level
F O U R T H E D I T I O N Project Management © The McGraw-Hill Companies, Inc., 2003 supplement 3 DAVIS AQUILANO CHASE PowerPoint Presentation by Charlie.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects…
3 - 1 Course Title: Production and Operations Management Course Code: MGT 362 Course Book: Operations Management 10 th Edition. By Jay Heizer & Barry Render.
Chapter 17: Learning Objectives
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
Operations Management Session 27: Project Management.
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
OPSM 301 Operations Management Class 27: Project Management: project crashing Koç University Zeynep Aksin
Gantt Chart Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack amount.
Chapter 3 Project Management. Chapter 3 Project Management.
© 2006 Prentice Hall, Inc.3 – 1 Operations Management Chapter 3 – Project Management Chapter 3 – Project Management © 2006 Prentice Hall, Inc. PowerPoint.
1 1 Slide © 2004 Thomson/South-Western Chapter 12 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
إدارة المشروعات Projects Management
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
University of Mediterranean Karpasia
MGMT 483 Week 8 Scheduling.
1 1 Slide © 2009 South-Western, a part of Cengage Learning Slides by John Loucks St. Edward’s University.
Chapter 3 (Continued) Outline Recap CPM (continued)  Assign time estimates to each activity  Compute the longest time path through the network.
Project Management Chapter 13
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edward’s University.
Chapter 10 Project Scheduling: PERT/CPM
6. Project Management.
Projects: Critical Paths Dr. Ron Lembke Operations Management.
Project Management Techniques.
Project Scheduling Professor Stephen Lawrence Leeds School of Business University of Colorado Boulder, CO
3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations.
Operations Management
Operations Management
Operations Management
Operations Management
© 2000 by Prentice-Hall Inc Russell/Taylor Oper Mgt 3/e Chapter 6 Project Management.
3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations.
© 2008 Prentice Hall, Inc.3 – 1 Operations Management Chapter 3 – Project Management PowerPoint presentation to accompany Heizer/Render Principles of Operations.
Project Scheduling Professor Stephen Lawrence Graduate School of Business Administration University of Colorado Boulder, CO
Operations Management Chapter 3 – Project Management.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
Network Planning Methods Example PERT & CPM
Project Management. Learning Objectives  Discuss the behavioral aspects of projects in terms of project personnel and the project manager.  Discuss.
Lecture 09 Project Management ISE Dept.-IU Office: Room 508.
3 - 1© 2011 Pearson Education 3 3 Managing Projects PowerPoint presentation to accompany Heizer and Render Operations Management, 10e, Global Edition Principles.
3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall  Complex and temporary task of many related activities. (not ‘business as usual’)  May.
3 Project Management PowerPoint presentation to accompany
© 2006 Prentice Hall, Inc.3 – 1 Operations Management Chapter 3 – Project Management Chapter 3 – Project Management © 2006 Prentice Hall, Inc. PowerPoint.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 17 Project Management Part.
1 1 Project Scheduling PERT/CPM Networks. 2 2 Originated by H.L.Gantt in 1918 GANTT CHART Advantages - Gantt charts are quite commonly used. They provide.
Project Management Techniques
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
3 - 1 Course Title: Production and Operations Management Course Code: MGT 362 Course Book: Operations Management 10 th Edition. By Jay Heizer & Barry Render.
Project Planning and Budgeting Recall the four stages Project Definition and Conceptualization Project Planning and Budgeting Project Execution and Control.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects…
Operations Management Project Management Chapter 3.
Operations and Project Management Session 3 Extra Some Additional Details on CPM and PERT.
Project Planning, Scheduling and Control Planning: –defines objectives, tasks and preceeding relationships; estimates time and resources Scheduling: –identifies.
PROJECT MANAGEMENT.
Project Management: PERT/CPM
Project Management (PERT/CPM) PREPARED BY CH. AVINASH
Learning Objectives When you complete this chapter, you should be able to : Identify or Define: Work breakdown structure Critical path AOA and AON Networks.
Projects: Critical Paths
PROJECT MANAGEMENT WITH CPM/PERT.
Project Scheduling Network Optimization can be used as an aid in the scheduling of large complex projects that consist of many activities A project is.
Project Planning and Budgeting
PLANNING ENGINEERING AND PROJECT MANAGEMENT
Slides Prepared by JOHN LOUCKS
Project Management CPM/PERT Professor Ahmadi.
Presentation transcript:

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. W6 6.2 Operation Management Operation Management Managing Projects Techniques © Ana G. Méndez University System, All rights reserved.

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 2 Managing Projects Techniques Business Change Analysis Critical path method Program Evaluation Review Technique Gap Analysis Network Diagram

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 3 Gantt chart Critical Path Method (CPM) Program Evaluation and Review Technique (PERT)

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 4 1.Helps you to plan out the tasks that need to be completed. 2.Give you a basis for scheduling when these tasks will be carried out. 3.Allows you to plan the allocation of resources needed to complete the project, and 4.Help you to work out the critical path for a project where you must complete it by a particular date.

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 5 1.Network techniques 2.Developed in 1950’s CPM by DuPont for chemical plants (1957) PERT by Booz, Allen & Hamilton with the U.S. Navy, for Polaris missile (1958) 3.Consider precedence relationships and interdependencies 4.Each uses a different estimate of activity times

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 6 Activity onActivityActivity on Node (AON)MeaningArrow (AOA) A comes before B, which comes before C (a) A B C BAC A and B must both be completed before C can start (b) A C C B A B B and C cannot begin until A is completed (c) B A C A B C

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 7 Activity onActivityActivity on Node (AON)MeaningArrow (AOA) C and D cannot begin until both A and B are completed (d) A B C D B AC D C cannot begin until both A and B are completed; D cannot begin until B is completed. A dummy activity is introduced in AOA (e) CA BD Dummy activity A B C D

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 8 Activity onActivityActivity on Node (AON)MeaningArrow (AOA) B and C cannot begin until A is completed. D cannot begin until both B and C are completed. A dummy activity is again introduced in AOA. (f) A C DB AB C D Dummy activity

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 9 Perform a Critical Path Analysis The critical path is the longest path through the network The critical path is the longest path through the network The critical path is the shortest time in which the project can be completed The critical path is the shortest time in which the project can be completed Any delay in critical path activities delays the project Any delay in critical path activities delays the project Critical path activities have no slack time Critical path activities have no slack time

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 10 Perform a Critical Path Analysis Earliest start (ES) =earliest time at which an activity can start, assuming all predecessors have been completed Earliest finish (EF) =earliest time at which an activity can be finished Latest start (LS) =latest time at which an activity can start so as not to delay the completion time of the entire project Latest finish (LF) =latest time by which an activity has to be finished so as not to delay the completion time of the entire project

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 11 Perform a Critical Path Analysis A Activity Name or Symbol Earliest Start ES Earliest Finish EF Latest Start LS Latest Finish LF Activity Duration 2

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 12 Begin at starting event and work forward Earliest Start Time Rule: If an activity has only a single immediate predecessor, its ES equals the EF of the predecessor If an activity has multiple immediate predecessors, its ES is the maximum of all the EF values of its predecessors ES = Max {EF of all immediate predecessors}

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 13 Begin at starting event and work forward Earliest Start Time Rule: The earliest finish time (EF) of an activity is the sum of its earliest start time (ES) and its activity time EF = ES + Activity time

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 14 Begin with the last event and work backwards Latest Finish Time Rule: If an activity is an immediate predecessor for just a single activity, its LF equals the LS of the activity that immediately follows it If an activity is an immediate predecessor to more than one activity, its LF is the minimum of all LS values of all activities that immediately follow it LF = Min {LS of all immediate following activities}

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 15 Begin with the last event and work backwards Latest Finish Time Rule: The latest start time (LS) of an activity is the difference of its latest finish time (LF) and its activity time LS = LF – Activity time

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 16 Start A2A2 2 EF of A = ES of A ES of A

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. E4E4 F3F3 G5G5 H2H D4D4 37 C2C2 24 B3B3 03 Start A2A2 20 LF = EF of Project 1513 LS = LF – Activity time 17

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. Prepared by Gilberto Clavell18 13 LS = LF – Activity time E4E4 F3F3 G5G5 H2H D4D4 37 C2C2 24 B3B3 03 Start A2A

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 19 After computing the ES, EF, LS, and LF times for all activities, compute the slack or free time for each activity Slack is the length of time an activity can be delayed without delaying the entire project Slack = LS – ES or Slack = LF – EF

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 20 Three time estimates are required Optimistic time (a) – if everything goes according to plan Pessimistic time (b) – assuming very unfavorable conditions Most likely time (m) – most realistic estimate Expected time: Variance of times: t = (a + 4m + b)/6 v = [(b – a)/6] 2

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 21 Probability Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b) Activity Time Probability of 1 in 100 of > b occurring Probability of 1 in 100 of < a occurring Estimate follows beta distribution

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 22 MostExpected Activity OptimisticLikelyPessimisticTimeVariance ambt = (a + 4m + b)/6[(b – a)/6] 2 A B C D E F G H A B C D E F G H

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 23 Project variance is computed by summing the variances of critical activities  2 = Project variance =  (variances of activities on critical path) p Project variance  2 = = 3.11 Project standard deviation  p = Project variance = 3.11 = 1.76 weeks p

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 24 It is not uncommon to face the following situations: The project is behind schedule The completion time has been moved forward Shortening the duration of the project is called project crashing

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved Compute the crash cost per time period. If crash costs are linear over time: Crash cost per period = (Crash cost – Normal cost) (Normal time – Crash time) 2.Using current activity times, find the critical path and identify the critical activities

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved If there is only one critical path, then select the activity on this critical path that; (a) can still be crashed, and (b) has the smallest crash cost per period. If there is more than one critical path, then select one activity from each critical path such that; (a) each selected activity can still be crashed, and (b) the total crash cost of all selected activities is the smallest. Note that the same activity may be common to more than one critical path.

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved Update all activity times. If the desired due date has been reached, stop. If not, return to Step 2. Time (Wks)Cost ($)Crash CostCritical Activity Normal Crash Normal CrashPer Wk ($)Path? A2122,00022,750750Yes B3130,00034,0002,000No C2126,00027,0001,000Yes D4248,00049,0001,000No E4256,00058,0001,000Yes F3230,00030,500500No G5280,00084,5001,500Yes H2116,00019,0003,000Yes A2122,00022,750750Yes B3130,00034,0002,000No C2126,00027,0001,000Yes D4248,00049,0001,000No E4256,00058,0001,000Yes F3230,00030,500500No G5280,00084,5001,500Yes H2116,00019,0003,000Yes

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. 28 ||| 123Time (Weeks) $34,000 $34,000 — $33,000 $33,000 — $32,000 $32,000 — $31,000 $31,000 — $30,000 $30,000 — — Activity Cost CrashNormal Crash Time Normal Time Crash Cost Normal Cost Crash Cost/Wk = Crash Cost – Normal Cost Normal Time – Crash Time = $34,000 – $30,000 3 – 1 = = $2,000/Wk $4,000 2 Wks

MANA 705 DL © Sistema Universitario Ana G. Méndez, All rights reserved. Dear Student: We have concluded the topic Managing Projects Techniques. It is important to do the recommended readings pertaining to this workshop. ¡Go ahead! 29 End