Hudson River Dredging: Overview and Update January, 2010.

Slides:



Advertisements
Similar presentations
ABSTRACT Background. Sydney Harbour (SH), Nova Scotia has long been subject to effluent and atmospheric inputs of metals, polycyclic aromatic hydrocarbons.
Advertisements

NYS Department of Environmental Conservation Update on the Niagara River U.S. RAP Niagara River Remedial Action Plan Implementers Session April 10, 2013.
UMR = Balance of Environment and Transportation 1. Pool # 8 - Environmental Management Project 2. Transportation Route – human habitation & settlement.
Discussion of Lower Passaic Cleanup Alternatives Presentation to the Fair Lawn Environmental Commission April 3,
A section has been added regarding Stream Restoration Design Criteria: A. Designs for stream restoration try to mimic natural conditions present in stable.
1 Effluent Guidelines for Construction Greg Davis USEPA
Lake County Water Authority Nutrient Reduction Facility (NuRF) Lance Lumbard Water Resources Project Manager.
Lower Yellowstone River Diversion Dam Project – Phase II - Physical Modeling of the Rock Ramp BRT, COE, MTAO Update Meeting November 4, 2010.
BoRit Superfund Site Timeline
TEXAS COMMISSION on ENVIRONMENTAL QUALITY. PROPOSED STUCTURE FOR CHAPTER 217 < Subchapter A Administrative Provisions < Subchapter B Design Bases < Subchapter.
Presentation to: Technical Advisory Committee Onondaga Lake.
PUBLIC INFORMATION SESSION: Old Fall River Road Landfill Dartmouth, MA Massachusetts Unlined Landfill Closure Policy March 28, 2013 Mark Dakers, Acting.
Assessment of gravel transport characteristics of the upper Santa Ana River Scott Wright and Toby Minear USGS California Water Science Center Sacramento,
Environmental Investigation by Con Edison Former E115th Street Gas Works November 13, 2007.
Examples for Mitigation Category 1 and 2 Streams.
A Preliminary Evaluation of the Potential Downstream Sediment Deposition Following the Removal of Four Dams on the Klamath River Yantao Cui 1, Christian.
The EU Water Framework Directive and Sediments The Water Framework Directive was transposed into law in EU Member States at the end of Nearly two.
Water Treatment for NYC Croton Schematic. NYC Filtration Plant for Delaware and Catskill Systems  Filtration avoidance criteria  Alternatives to Filtration.
Water Treatment for NYC Croton Schematic. NYC Filtration Plant for Delaware and Catskill Systems ä Filtration avoidance criteria ä Alternatives to Filtration.
NYC Filtration Plant for Delaware and Catskill Systems ä Filtration avoidance criteria ä Alternatives to Filtration? ä Where should the plant(s) be located?
ABSTRACT The upper Willamette basin from Eugene to Albany was settled by Euro-Americans in the 1840’s. Since then, the Willamette River had been a vital.
Dredging, Disposal Management and Impacts on Lake Sediments US Army Corps of Engineers.
1 Filter Backwash Recycling Rule FBRR Final: June 8, 2001.
The situation in Norway concerning sediments/dredging Tore Lundestad, Port of Borg, Norway.
Cleaning up the Hudson Andrew Brown. The Hudson River Official Source- Lake Tear in the Clouds in Adirondack Mountains Official Source- Lake Tear in the.
Equus Beds ASR Program – Wichita’s Future Water Supply September 6, 2012.
Ross MacNames Edward Jackson Samantha Quiroga.  Elevated levels of Polychlorinated Biphenyls (PCBs) found in sediment of the Little Brazos River
SRRTTF Synoptic Sampling Event August Sample scoping meeting and site reconnaissance on July , 2014 Scope revised to include vessel use,
Screen | 1 EPA - Drivers for Regionalisation Max Harvey Director Operations Environment Protection Authority Presentation, reference, author, date.
New Stormwater Regulations “C.3” Provisions in effect Feb. 15, 2005.
Materials Transport & NSCD Material Classes Velocity to Transport Relationships York NSCD Restoration PSY CCREP.
Basic Hydrology Water Quality: Sediment production and transport.
History and Cleanup at Chemical Commodities, Inc. Jeff Field US EPA Region 7 1.
Danny Reible – University of Texas Heidi Blischke - GSI 1 Polydimethyl siloxane 2 Solid Phase Microextraction.
Ghost River & Waiparous Creek in Waiparous Village on June 21, 2007.
Former DuPont Barksdale Works Project Update December 14, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center.
The Clean Water Act © Dr. B. C. Paul (Jan. 2000).
SITE STATUS UPDATE TOP STOP PETROLEUM RELEASE SITE GUNNISION, UTAH Morgan Atkinson – Division of Environmental Response and Remediation, Project Manager.
Environmental Dredging of Perfluorochemical-Impacted Sediment from a Sensitive Wetland Mark A. Gaetz (3M) Paul Lear (WRScompass)
Three Rivers Levee Improvement Authority June 8, 2007 Presentation to the State Reclamation Board Proposed Feather River Setback Levee.
Natural vs. Accelerated Soil Erosion Natural geologic erosion has occurred at a relatively slow rate since the earth was formed. Natural erosion produces.
A Combined Solution for Sediment Remediation and Waterfront Development A Combined Solution for Sediment Remediation and Waterfront Development John T.
BUILDING STRONG ® Mississippi River Ship Channel Gulf to Baton Rouge, LA Propeller Club for Port of New Orleans 24 September 2015.
US Army Corps of Engineers BUILDING STRONG ® Understanding Sedimentation and Land Use Cover Relationships in the Lake Sidney Lanier Watershed Russell A.
 These two agents: erosion and deposition are the most important agents that affect weathered materials.  Erosion involves the physical removal of weathered.
Status update presentation #1 for the Cayucos Sustainable Water Project Status update presentation #1 for the Cayucos Sustainable Water Project November.
US Army Corps of Engineers BUILDING STRONG ® Dredging with Turbidity Tests and the EPA in Green Bay Harbor Michael Staal, E.I.T. Civil Engineer U.S. Army.
Project Update: Hudson River PCBs Superfund Site October 24, 2012 Mr. David King, PE – USEPA Region 2 Mr. Gary Klawinski – USEPA Region 2 Mr. Mark Surette.
Margaret Byrne, U.S. Fish and Wildlife Service
Estimating the Volume of Fine-Grained Sediments Behind Four Low-Head Dams, Kalamazoo River, Michigan. In cooperation with the Michigan Department of Environmental.
Mercury and Suction Dredging Analysis of Data 10 May 2010 Eric Maksymyk.
US Army Corps of Engineers BUILDING STRONG ® Mississippi Coastal Improvements Program (MsCIP) “Comprehensive Barrier Island Restoration Plan” PIANC 2012.
Evaluation Measures for Municipal Storm Water Management Programs Daniel Rourke Fresno Metropolitan Flood Control District October 15, 2003 Counting Raindrops.
Coeur d’Alene Basin TLG Repository PFT meeting December 9, 2003.
BUILDING STRONG ® Rock Removal on the Middle Mississippi River 1 RRAT 2014.
1 FORMER COS COB POWER PLANT From Characterization to Redevelopment Brownfields2006 November 14, 2006.
Marian Anderson Place Site Update City Commission Special Workshop December 14, 2015.
Rail Shipments July 2004.Page number1 Rail Shipments of Radioactive Waste from Rocky Flats to Envirocare in Utah August 2004.
Cleaning up the Lower Fox River Greg Hill, Wisconsin DNR Winnebago Project University of Wisconsin Oshkosh, May 23, 2008.
SWPPP: Stormwater Pollution Prevention Plan Creating/Implementing a Plan for Compliance.
 Clean Water Act 404 permit  Ohio EPA Division of Surface Water 401 water quality certification  Ohio Revised Code 6111 – Placement of dredged materials.
TTWG Report & Technical Topics SRRTTF Meeting Dave Dilks March 16, 2016.
Rivanna Water & Sewer Authority Presentation to City of Charlottesville Workshop South Fork Rivanna Reservoir (SFRR) Dredging Concept Review May 6, 2008.
Bridges Reach analysis Fundamental tool for design
Upland Landfill Waste Discharge Application 7295 Gold River Highway
Continuing Authorities Program
Effects of persistent drought on Lake Mead and the Las Vegas Valley
John Tinger U.S. EPA Region IX
Pearce Creek DMCF Baseline Exterior Monitoring Spring 2017 Results
Presentation transcript:

Hudson River Dredging: Overview and Update January, 2010

The Hudson: History : PCBs used by GE capacitor manufacturing plants 1973: Removal of Ft Edward Dam - PCBs spread downstream 1976: New York and GE settle enforcement action for PCB discharges 1984: 1st EPA ROD calls for shoreline capping (60 acres), but no dredging : GE implements 1984 Remedy 1990 – EPA reassessment begins 2/1/2002 : new EPA ROD calls for dredging GE Hudson Falls Capacitor Plant 3 Dam Location

Upper Hudson River Hadley Glens Falls Hudson Falls Fort Edward WASHINGTON WARREN Schuylerville SARATOGA Thompson Is. Dam Fort Miller Dam Stillwater Mechanicville Hoosic River Waterford Cohoes Green Island Troy Mohawk R RENSSELAER Federal Dam Section 1 Bakers Falls mi 10 k Section 2 Section 3 Northumberland Dam

Dredging along 40 miles of river Phase 1: –1 st year dredging (May - November) –Test equipment/processing facility –Evaluate performance standards vis-à-vis the design Review of Phase 1: – Independent peer review panel – Receive public comments – EPA decision on modifications to project Phase 2: –Remaining dredging Project Phases

–2002: ROD selects dredging remedy –2004: EPA completes development of Quality of Life and Engineering Performance Standards, Siting of Processing Facility and Community Relations – : Three EPA/GE agreements to perform work —Sediment sampling (complete) — Engineering design of 2-phase project (Phase 1 complete) — Performance of project (Phase 1 complete). Agreement includes Phase 2 “opt-in/opt-out” provision for GE. Decision to be made in second half of If GE opts out, EPA retains all enforcement authorities to compel performance of Phase 2. – : Construction of Sediment Processing Facility –2009: Phase 1 dredging commences May 15, continues to November Project Overview

Construction of Processing Facility –2 miles of road; utilities; 90,000+ cy of fill –Rail yard with 7 miles of new track –1,500 foot long wharf to unload barges; widen canal by 65 feet –2 MGD water treatment plant –Screens and a bank of “hydrocyclones” to remove sand –12 filter presses –300,000 sq yds of liners, 55,000 sq yds paved area –7 acres of storm water basins to handle 100-year flood –5 staging areas for dewatered sediment (2 enclosed -- 19,000 cu yds each) 9

November 2008 Sediment Processing Facility April 2007 Champlain Canal

Sediment Processing Facility Operations Once at the processing facility, the sediment is off-loaded and debris is removed The sediment is then processed and the water is extracted. The water is treated on-site before being returned to the Champlain Canal The remaining sediment, called “filter cake,” is loaded onto railcars for transport to a secure, PCB-approved landfill in Andrews, Texas –some sediment was directly off loaded, dried and then placed in railcars

Phase 1 and 2 Dredge Area Delineation > 50,000 sediment samples taken ; sampling data collected to enable EPA and GE to: –determine the distribution of PCBs in the sediment –refine estimates of the amount and location of PCBs in the sediment –establish river sediment characteristics (e.g., silt, sand, gravel) 490 acres planned to be dredged – 90 acres during Phase 1, 400 acres during Phase 2

–May-November 2009; operating 24/6 –Up to 12 mechanical clamshell dredges working at same time –27 Hopper Barges/13 Tugs –Constant monitoring –Backfill (or cap) after dredging –Habitat replacement (in 2010) Phase 1 Dredging

Dredging Operations Dredging & Debris Removal Resuspension controls –Rock dike –Silt curtain –7,000 yds 2 steel sheeting Backfill, if area meets residual standard –165,000cy –12” of cover over much of area –38,000cy near-shore backfill to match original bathymetry –Add’l. backfill in specified planting areas Capping, if area cannot meet residual standard –Depends on residual concentrations –Consider capping if residuals not removed after 4 passes –Requires EPA approval Dredging and/or backfilling operations continued 24/6 while Champlain Canal was open (May – November, 2009)

Engineering Performance Standards Engineering Performance Standards were developed to: - minimize resuspension of PCBs during dredging - set limits on PCBs left in sediment, and - set production rates Resuspension standard designed to: - Protect drinking water intakes downriver of the dredging operations, and - Limit the downriver transport of PCBs Performance standards now being evaluated through peer review process Standards and design likely to be modified for Phase 2

Protection of Water Supplies Two communities downstream of dredging area – Waterford & Halfmoon -- utilize Hudson River for drinking water supplies. A third community – Stillwater – uses well field immediately adjacent to Hudson River EPA built new 4.5-mile water line for Waterford and Halfmoon to bring non-Hudson water from Troy during any time when Hudson River water downstream of dredging exceeds 500 ppt (federal drinking water standard) EPA provided GAC treatment for Stillwater Water supplies in Lower Hudson were sampled by DOH (with funding from EPA); 2009 levels were not elevated in comparison to baseline 2008 levels

Quality of Life Standards Air Noise Light Odor Navigation

Dredging Began May 15, 2009

The First Scoop of Mud

Shoreline Preparation Pre-Dredging Tree trimming

Removal of Logs, Stumps & Debris from Western Channel of Rogers Island

Debris is a Major Problem Debris removal

Dredging in Ft. Edward, NY

Residents Watch Dredging in the Ft. Edward Yacht Basin

Loading a Mini-Scow

Large Hopper Scow

Noise Monitors Along Shore of Rogers Island, Ft. Edward, NY

Locks Open May - November Barge transport through Lock 7

100+ Acre Processing Facility Unloading at processing facility

Installation of Plastic Liners in Rail Cars for Transport of Contaminated Sediment

Workers Load Rail Cars with Dried Sediment

Rail Transport to West Texas

Assessment & Peer Review Assessment of Phase 1 underway. Purpose is to evaluate engineering & performance standards and make appropriate changes EPA & GE prepared draft reports evaluating Phase 1; reports exchanged and released to public in mid- January; final reports released March 8 –Reports draw some significantly different conclusions from same facts Peer Review started mid-February, continues to June

EPA Report Findings: Overview –Phase 1 Plan: Minimum removal was to be 200,000 CY Target was 265,000 CY removed from 90 acres –Phase 1 Achieved: 283,000 CY removed from 48 acres >1.5 times more PCB mass removed than estimated in ROD –About the same mass as estimated in design, but from fewer acres 31 acres backfilled; 17 acres capped –Significantly less capping expected in Phase 2 – East Rogers Island area is atypical of rest of River – about 11.5 acres capped -- About half of the remaining capped areas were buried under several feet of clean backfill thus addressing habitat concerns

283,000 Cubic Yards 265,000 Cubic Yards

Phase 1 Target = 18 CUs dredged; Achieved = 10 CUs dredged

EPA Draft Report Findings Phase 1 indicated much greater mass of PCB in the areas dredged than estimated. In fact, PCB-bearing oils were frequently encountered. The depth of contamination (DOC) was greater than estimated in the design (in one area DOC was 13 feet deeper than designed). On average the depth of cut was 1.5 X deeper than designed. –Inaccurate estimates primarily attributable to woody debris interference with sediment sampling during design phase. If the actual DOC is better defined prior to actual dredging, the contaminated material can be removed with fewer and fuller bucket bites, and fewer passes over a given area. Fewer bucket bites equates to less resuspension and greater productivity.

EPA Draft Report Findings: Resuspension Standards Findings Near-field TSS m Evaluation Level mg/L Near-field TSS m Evaluation Level mg/L Max. allowable Total PCBs in water column ng/L Far-field net suspended solids concentration Evaluation Level mg/L Av. TSS well below Evaluation Level Av. TSS well below Evaluation Level; 4 exceedances observed (but not supported by continuous turbidity measurements). 3 exceedances; dredging activities halted less than 4 four days. Not exceeded

Monitoring PCBs During Dredging: Schuylerville, NY Data

EPA Draft Report Findings: Resuspension Standards Findings Far-field Total and Tri+ PCB load Control levels: 1,080 grams/day and 361 grams/day Exceeded at Thompson Island for majority of the dredging period. At Waterford, loads were significantly lower -- exceeded control level ~ 20% of time. Note: load criteria were not revised during Phase 1 to address the larger- than-planned PCB mass removed. Overall target of no more than 1% export to lower Hudson was achieved.

EPA Draft Report Findings: Residuals Standards Findings Affirmation of removal of all PCB-contaminated sediment inventory in target dredging areas (“Certi- fication Units” or CUs) Arithmetic average Tri+ PCBs concentration in the residual sediments ≤ 1 mg/kg Substantial removal of inventory confirmed in all CUs. Where inventory left in place, engineered caps constructed to isolate the remaining inventory. Expect that ≤ 1 mg/kg can be achieved in residual sediments during Phase 2

EPA Draft Report Findings: Productivity Standards Findings Target Phase 1 dredging volume = 265,000 CY Targeted Maximum Phase 1 monthly volume = 88,350 CY Shoreline stabilization, backfilling, and processing and shipment of removed sediment accomplished prior to the end of calendar year. Total volume removed = 283,000 cy Max. monthly Phase 1 volume removed = ~77,000 CY. (Very likely that the target of 88,350 CY would have been achieved but for shortages of empty scows.) Due to difficulties at disposal site, not all sediment shipped off-site by end of Provisions should be made for back-up disposal site for Phase 2.

Met or exceeded sediment volume & PCB mass goals Few shut-downs with limited impact on production ~70% of dredged area closed in compliance with the Residuals Standard No measurable impacts to Lower River We learned enough in Phase 1 to improve the project and do it well in Phase 2 What Went Well

Phase 1 Challenges Higher than normal flows Extent of wood debris DoC consistently underestimated NAPL releases Limitations on scow unloading Extent of erosion since 2001 – 35K CY lost in the 18 planned CU’s before start of dredging; system is dynamic, redistribution occurs all the time % of bedrock/clay bottom 48

Resuspension Standard: Summary of Observations No significant release of solids during dredging Water column PCB concentrations were significantly above baseline during dredging. PCB-bearing oil sheens were extensive and are likely a significant vector for PCB release. Water column concentrations of PCB decreased substantially downstream of Thompson Island to Waterford. –Tri+ PCB Loads at Lock 5 and Waterford were significantly lower than loads at Thompson Island, yet solids transport increased slightly (though still within the baseline variations) There were no observable impacts of dredging to PCB water column concentrations downstream of Albany.

Resuspension Standard Observations (con’t.) Net load at Thompson Island was still small relative to the overall mass removed : 440 kg vs. the 20,000 kg removed (roughly 2 percent). The net load to the Lower Hudson was roughly 150 kg total PCB. The resuspension goal of maintaining the Total PCB export rate to 1 percent or less relative to the mass of PCBs removed was achieved at Waterford and nearly met at Schuylerville. 50

Productivity Standard: Major Factors Affecting Productivity During Phase 1 Scow unavailability due to limited scow unloading capacity at Dewatering Facility Presence of wood debris in sediment Limited capacity of mini-scows Underestimated DoC Fine grading to meet cut line tolerances

Debris in Sediment

Impacts of Underestimated DoC and Fine Grading Underestimated DoC: – Additional dredge passes –Time lost in mapping, sampling, and designing new cut lines –CUs open longer Fine Grading: –Reduced production rate Both factors also increased resuspension losses

Phase 2 Productivity Standard Can be Met by: Addressing uncertainty in DoC to minimize passes Improving scow unloading capacity Minimizing fine grading and small cuts Conducting access dredging where needed

Residual Standard – Summary of Findings Resuspension, Productivity and Residual standards are related Basic problems arise from the uncertainty in the design DoC –Core samples used for design were often incomplete, yielding inaccurate design Modifications needed in the approaches for dredging and post-dredging sampling EPA is recommending simplifications to the Residuals Standard but not changes to the basic approach

Closure Summary

Simultaneously Meeting Standards Efficient dredging of inventory with fewer cuts (productivity) leads to fewer bottom disturbances and smaller dredging releases (resuspension) and quicker certification of post-dredging concentrations (residuals) reducing duration of exposed bottom surface (resuspension). Per Residual Standard, appropriate selection of cut lines is important in minimizing re-dredging...and therefore in meeting the standards simultaneously.

OVERALL BENEFITS OF PROJECT Far more PCBs in the River than estimated The River is NOT “cleaning itself” at the rate predicted by the model used in the 1990s. –Sediments are not being buried.. –Surface concentrations are 3x higher, and water column concentrations are 2-3 X higher, than 1990s model predicted. Both show little or no decline over a decade. Even with an increase in the resuspension standard, completion of the dredging project will confer significant and lasting benefits.

More Information For information on Hudson River Dredging Project: For EPA’s Report on Phase 1: For GE’s Report on Phase 1: