DQW Cryogenic Magnetic Shield Internal Review Niklas Templeton 06/05/15.

Slides:



Advertisements
Similar presentations
SPL Intercavity support Conceptual design review 04/11/ A. Vande Craen TE/MSC-CMI.
Advertisements

ME 450 Group Adrian Conrad Chris Cook Thomas Hylton Nathan Wagers High Pressure Water Fixture Conceptual Design Analysis December 10, 2007.
Vacuum Vessel Production Readiness Review
MICE Collaboration Meeting at Frascati, Jun 26~29, 2005 Iron Shield Mounting Design Stephanie Yang.
Integration of Cavities and Coupling Coil Modules Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting March 28 – April 1, 2004.
Progress on the MICE Cooling Channel Solenoid Magnet System
1 Update on Focus Coil Design and Configuration M. A. Green, G. Barr, W. Lau, R. S. Senanayake, and S. Q. Yang University of Oxford Department of Physics.
Background to the current problem 1. As a result of the high stresses in the bobbin due to the magnet load, the bobbin end plate needs to be increased.
FE calculations for the bolted helium vessel May 6th 2015
Influence of the Gravity, Vacuum and RF on CLIC Module T0 Behavior R. Raatikainen.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Cryomodule Concept for the ODU RF Dipole Crab Cavity Tom Nicol* - Fermilab December 10, 2013 * With lots of help from HyeKyoung, Tom J, Shrikant, Ofelia,
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe MLC external review October 03, 2012.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
3D Finite Element Analysis for Ribbed Structure Vacuum Vessel By: Hamed Hosseini Advisor: Prof. Farrokh Najmabadi.
ZTF Cryostat Finite Element Analysis Andrew Lambert ZTF Technical Meeting 1.
RFQ Thermal Analysis Scott Lawrie. Vacuum Pump Flange Vacuum Flange Coolant Manifold Cooling Pockets Milled Into Vanes Potentially Bolted Together Tuner.
Pixel Support Tube Requirements and Interfaces M.Olcese PST CDR: CERN Oct. 17th 2001.
Page 1 Jean Delayen HyeKyoung Park Center for Accelerator Science Department of Physics, Old Dominion University and Thomas Jefferson National Accelerator.
Stress and cool-down analysis of the cryomodule Yun He MLC external review October 03, 2012.
Cavity support scheme options Thomas Jones 25/06/15.
Cavity support scheme options Thomas Jones 25/06/15 to 06/07/15 1.
Stress and Cool-down Analysis Yun HE MLC Internal Review 9/5/2012Yun HE, MLC Internal Review1.
Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1.
Cold Magnetic Shield Update
Cavity support scheme options Thomas Jones 1. Introduction Both cavities will be supported by the fundamental power coupler and a number of blade flexures.
5 K Shield Study of STF Cryomodule Norihito Ohuchi, Norio Higashi KEK Xu QingJin IHEP 2008/3/3-61Sendai-GDE-Meeting.
Mechanical Designs of The Central Detector Jinyu Fu
56 MHz SRF Cavity Cryostat support system and Shielding C. Pai
56 MHz SRF Cavity Thermal Analysis and Vacuum Chamber Strength C. Pai
56 MHz SRF Cavity and Helium vessel Design
Cold Magnetic Shield Assembly Nik Templeton 25/08/2015.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Cavity support scheme options Thomas Jones 25/06/15 1.
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe.
LHC Cryostat evaluation Nikolay Solyak Thanks Rama Calaga, Tom Peterson, Slava Yakovlev, Ivan Gonin C11 workshop. FNAL, Oct 27-28, 2008.
HiLumi-LHC/LARP Crab Cavity System External Review – May Work partly supported by the EU FP7 HiLumi LHC grant agreement No and by the.
S1 global: thermal analysis TILC09, April 19th, 2009 Serena Barbanotti Paolo Pierini.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
5 K Shield Study of STF Cryomodule (up-dated) Norihito Ohuchi KEK 2008/4/21-251FNAL-SCRF-Meeting.
Thermal Shield Update Niklas Templeton 15/02/16 (final update of placement  )
Ralf Eichhorn CLASSE, Cornell University. I will not talk about: Cavities (Nick and Sam did this) HOM absorbers (did that yesterday) Power couplers (see.
HL-LHC-UK Thermal Shield Update Niklas Templeton 07/03/2016.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
704 MHz cavity design based on 704MHZ_v7.stp C. Pai
Panda Solenoid Content Interface Box Cold Mass Layout Cooling Lines
CERN – Zanon discussions
Stress and cool-down analysis of the cryomodule
Crab – RFD prototype: Production Status Update
HFM Test Station Main Cryostat
Crab Cavity HOM Coupler Specification Drawings & Tolerances
Status of design and production of LEP connection cryostat
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Fredrik Fors Mechanical Engineering, JLab 09/29/2016
Thermal and Outer Magnetic Shields
Thermal Shield Connection Study
Niklas Templeton – STFC – UK Collaboration
The 11T cryo-assembly: summary of design and integration aspects
Design of Distribution Feedbox at LHC P7
Chapter 8 : Natural Convection
Final Design CGEM Workshop HIEP, 14/03/2017 M. Melchiorri - INFN FE.
ESS elliptical cryomodule
Cryomodule Assembly Plan
Senad Kudumovic Design engineer
as a prototype for Super c-tau factory
Bunker Wall Design Wall ESS
Magnetic shielding and thermal shielding
SNS PPU Cryomodule Space Frame
SNS PPU Cryomodule Thermal Shield & MLI
SNS PPU CRYOMODULE FDR Magnetic Shields Gary Cheng June 10, 2019.
Presentation transcript:

DQW Cryogenic Magnetic Shield Internal Review Niklas Templeton 06/05/15

Contents Specification Opera Magnetic Analysis Overview –Design Approach –Common Features Design & Assembly Procedure –DQW –RFD Shield Analysis –Thermal Stress –Self Weight XYZ 1

Specification Less than 1µT on cavity surface Cold Magnetic Shield –1mm APERM Cryophy (to be used with 3mm Mu Metal outer shield) –Internal to Helium Vessel –Suspended in 2K Helium –Mounted off Helium vessel – no cavity connection Designed for (worst case) earth magnetic field. Local sources to be isolated separately –Earths South to North Field 48µT –SPS ambient Magnetic field with moderately shielded Busbars <200µT Magnetic shielding for SPL cavities: T Junginger 2010 Estimate of the Ambient Magnetic Field in the SPS Crab Cavity Location: J Bauche, A Macpherson

Summary of Opera Analysis - Kiril Maranov The magnet group within ASTeC (STFC) have converted the mechanical design CAD files into a simplified geometry acceptable for Opera 3D (Tosca) and then assessed shielding performance based on simulations. Two shielding solutions were considered: a single-layer solution (mu- metal only) and a double-layer solution (mu-metal + cryoperm) The conclusion from this work is to go ahead with the double-layer solution. The single layer solution meets the spec by a narrow margin, but there is no room for contingency and the risk is higher. 3

Magnetic shielding effect is anisotropic The external field is radial The external field is axial  A cylinder is twice as effective against radial field as against axial field. 4

Single layer: the field is parallel to the long side B Earth =60µT A single-layer shield is within spec (~0.5 µT) at the cavity locations, but this gives a limited factor of safety. B>1 µT 5

Performance: the field is parallel to the long side B Earth =60µT B>1 µT B<< 0.1 µT (very small!) 6

Shield Design Approach Satisfy space constraints –Internal to Bolted Helium Vessel –Close fitting to cavity Feasible assembly 1.Minimise number & size of penetrations 2.Ease of manufacture & assembly –Minimise number of panels –Bent / Folded sheet –*Pressed / Formed panels possible future batch shield orders 3.Maximise penetration attenuation 4.Maximise curvature 7

Reason for Close fitting shield High field regions requiring <1µT Reference - F. Pobell, Matter and Methods at Low Temperatures. Springer-Verlag, third ed.,

Common Design Features Helium Holes Shield peppered with at least 142 x Ø3mm holes on mm pitch for helium transfer 142 holes give 10cm 2 transfer area, so that at worst case heat load (10W) heat flow is at least 1W/cm 2 1mm APERAM Cryophy - Cold Rolled Strip Panels to be manufactured from Cryophy sheet metal which is cut, bent/folded, and fastened using self clinching nuts & spring washers 9

Common Design Features Tubular Shielding Prevents field penetration through openings. Ideally H = ØD Fitted & Curved Shape More effective at containing channelled magnetic flux Additional Cover Strips Overlapping joints prevent gaps & allows magnetic flux to follow a continuous low- reluctance path Flexi-Mounts Flexible Gr2 Titanium mounts connect the shield to the Helium Vessel. 8 mounting pairs are utilized in 3 orientations for maximum shield stability 10

YZX DQW Shield Design & Assembly Concept AConcept BConcept C No. of panels997 Curvature YZR40, R10, R50, R50 -R50, R50 Curvature XY-R100, R40, R30, R100 R100, R40 A B C Concept Analysis 11

DQW Shield Design & Assembly Assembled Shield Mass: ~10kg 12

DQW Shield Design & Assembly YZX 13

DQW Shield Design & Assembly YZX 2 Bottom Panels assembled 1 st Cavity orientation shown upside down for clarity 14

DQW Shield Design & AssemblyYZ X Shield & cavity mounted to base plate of the Helium Vessel Top End caps are attached as well as bottom side panel and Dummy beam pipe attenuation sleeve. 15

DQW Shield Design & Assembly Final 2 top panels are brought into place and remaining cover strips and brackets are fastened 16

DQW Shield Design & Assembly Side and top Vessel walls are assembled with remaining Flexi-Mounts before Helium Vessel is closed 17

RFD Shield Design & Assembly RFD Helium Vessel 20/04/15 Assembled Shield Mass: ~10kg 18

RFD Shield Design & Assembly 19

RFD Shield Design & Assembly Pre-assembled shield body is assembled Top and Bottom 20

RFD Shield Design & Assembly Shield Body is mounted to Helium Vessel Base 21

RFD Shield Design & Assembly Split folded-end panels are assembled around 3 ports End Cover is assembled to main body and fastened with cover panels and brackets 22

RFD Shield Design & Assembly 2 Curved-End panels are assembled around Beam Pipe 23

RFD Shield Design & Assembly Split panels complete the Shield at the FPC & HOM Ports Remaining cover strips are assembled 24

RFD Shield Design & Assembly Flexi Mounts are connected and Helium Vessel is assembled 25

FEA: Cool Down & Self Weight Material Data Helium Vessel & Flexi-Mounts: Titanium Grade2 (ES371110) –RT Yield Strength= 275MPa –Thermal Expansion from RT to -269K = -5.2 E-6.K Magnetic Shield: Aperam Cryophy (Magnetic Shielding LTD) –RT Yield Strength = 280MPa –Thermal Expansion from RT to -269K = -8 E-6.K 26

DQW & RFD Thermal Stress Loads & Constraints Cool down from RT to 2K Fixed at input coupler interface Results Solution contains erroneous result due to skew mesh geometry Stress > 150Mpa shown in red Some localised high stresses at shield connections Conclusion Cryophy Stresses affects shielding properties in immediate stress location, localised stresses are (at worst) comparable to a small hole – effect is negligible. Localised stress can be avoided using sufficient clearance at connections. 27

DQW Self Weight Horizontal Fixed at Flexi Mount – Helium Vessel interface Gravity applied in ANSYS Z direction Max shield deformation 0.08mm Max shield stress 13MPa 28

DQW Self Weight Vertical Fixed at Flexi Mount – Helium Vessel interface Gravity applied in ANSYS Y direction Max shield deformation 0.04mm Max shield stress 14MPa 29

DQW Self Weight Side Fixed at Flexi Mount – Helium Vessel interface Gravity applied in ANSYS X direction Max shield deformation 0.07mm Max shield stress 32MPa 30

DQW Self Weight Horizontal Fixed at Flexi Mount – Helium Vessel interface Gravity applied in ANSYS Z direction Max shield deformation 0.01mm Max shield stress 9MPa 31

RFD Self Weight Vertical Fixed at Flexi Mount – Helium Vessel interface Gravity applied in ANSYS Y direction Max shield deformation 0.01mm Max shield stress 9MPa 32

RFD Self Weight Side Fixed at Flexi Mount – Helium Vessel interface Gravity applied in ANSYS X direction Max shield deformation 0.02mm Max shield stress 27MPa 33

Discussions with Magnetic Shielding LTD We have liaised with Magnetic Shields LTD from the UK throughout the design of the shield. We obtained a budget cost for the previous shield concepts (welded helium vessel). Cost estimate was £8-12K (excluding VAT) per shield New designs could be more expensive, up to ~£15K (€20K) Formed / pressed shield panels are feasible for larger quantity orders. 34

Thank You! Questions?