Status of the MICE RF System K Ronald, University of Strathclyde For the MICE RF team 1MICE Project Board, 17th April 2015.

Slides:



Advertisements
Similar presentations
Andrew Moss ASTeC MICE RF workshop 16t h February 2012 Daresbury Laboratory Response to RF review for the MICE RF system.
Advertisements

RF Specification discussion MICE RF workshop 16 th April 2012.
MICE RF Cavities and RFCC Module Update Derun Li Lawrence Berkeley National Laboratory MICE RF Workshop Daresbury Laboratory, UK April 17, 2012 April 17,
1 RF Workshop 16 th & 17 th April 2012 Design Layout Alan Grant, STFC.
Status of the MICE RF System K Ronald, University of Strathclyde For the MICE RF team MICE Project Board & RLSR, 24th November
Andrew Moss ASTeC MICE Project Board 28 th June 2011 MICE RF System.
Areal RF Station A. Vardanyan RF System The AREAL RF system will consist of 3 RF stations: Each RF station has a 1 klystron, and HV modulator,
Collaboration meeting, RAL, 4 th – 7th November 2009 Andrew Moss ASTeC Collaboration meeting, RAL, 10 th – 13 th november 2009 MICE RF Amplifier Status.
RF systems for MICE Andrew Moss The MICE RF Group and the TIARA WP7 Team Contributions include Daresbury, RAL, CERN, LBNL, LANL, FNAL, Strathclyde & Sheffield.
Andrew Moss Daresbury Laboratory Collaboration Meeting th 19 th October 2012 RAL MICE RF System review.
Andrew Moss Daresbury Laboratory August 2013 Latest results of MICE amplifier testing.
RF Layout 3pi/2 for Discussion. 2 RF Design mtg 14/1/15 Output line from amplifier is lower than the PRY, needs to go high to clear PRY to couple to South.
Status of the MICE RF System K Ronald, University of Strathclyde For the MICE RF team 1MICE Project Board, 17th April 2015.
THE MICE RF SYSTEM J.F.Orrett* A.J.Moss, ASTeC, Daresbury Laboratory, WA4 4AD, UK Accelerator Science and Technology Centre
Safety Review: RF Issues Derun Li Absorber Safety Review December 9-10, 2003 Lawrence Berkeley National Laboratory Berkeley, CA
MuCool RF Status MICE Collaboration Meeting June 7-10, 2006, Fermilab A. Moretti June 9, 2006.
Status of the MICE RF System K Ronald, University of Strathclyde For the MICE RF team 1MICE Project Board, 17th April 2015.
RF Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICE Collaboration Meeting.
Single-Cavity Module Installation at MuCool Test Area Yağmur Torun MICE Collaboration Meeting February 15, 2013.
Andrew Moss ASTeC 7 th December 2011 MICE RF System.
Andrew Moss Daresbury Laboratory Collaboration Meeting th -16 th February 2013 Coseners House MICE RF HP System rprogress.
Collaboration meeting, DL, 19 h – 23 h October 2008 Andrew Moss ASTeC Collaboration meeting, DL, 19 th – 23 th October 2008 MICE RF distribution system.
Progress on the MICE RF Systems K Ronald, University of Strathclyde For the MICE RF team 1MICE Project Board 14th November 2013.
1 MICE RF Daresbury Laboratory Support Joe Orrett - ASTeC.
Status of RFCC-Module Development Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory MICE Collaboration Meeting at INFN-LNF, Frascati,
201 MHz NC RF Cavity R&D for Muon Cooling Channels
Emittance measurement: ID muons with time-of-flight Measure x,y and t at TOF0, TOF1 Use momentum-dependent transfer matrices to map  path Assume straight.
MICE RF – TIARA and General Progress Tim Stanley RAL 5 June 2013.
Andrew Moss ASTeC Collaboration meeting CM29 15 th - 18 th February 2011 MICE RF System.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
1 Status of EMMA Shinji Machida CCLRC/RAL/ASTeC 23 April, ffag/machida_ ppt & pdf.
Muon- RF Phase Determination K Ronald, Strathclyde Contributions from many MICE: Tim Stanley, Chris Rogers, Rutherford Lab, Yordan Karadzhov, Geneva, Paul.
Andrew Moss ASTeC CM32 9t h February 2012 RAL MICE RF System.
Anders Sunesson RF Group ESS Accelerator Division
MICE RF System Power Supplies, Control and Monitoring Status report February 2012 Chris White, STFC Daresbury Laboratory MICE Collaboration Meeting CM32,
Ding Sun and David Wildman Fermilab Accelerator Advisory Committee
MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids.
Progress on the MICE RF High Power Drive Systems K Ronald, University of Strathclyde For the MICE RF team 1MICE CM38 RF Parallel Session.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
1 Collaboration Meeting 33 - Glasgow 26 th June 2012 Design Layout Andrew Moss for Alan Grant, STFC.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
Andrew Moss ASTeC TIARA Mid term meeting 12 th 14 th June 2012 CIEMAT ICTF Progress on the MICE RF System.
MICE RF System Overview Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory Andrew Moss STFC Daresbury Laboratory MICE UK.
Status of the MICE RF System K Ronald, University of Strathclyde For the MICE RF team 1MICE Project Board, 30 th April 2014.
RF Review CM37 Andrew Moss. Amplifier results at Daresbury 2MW at 35kV, good efficiency and gain.
The MICE RF System K Ronald, University of Strathclyde For the MICE RF team 1MICE RF Review, 9th September 2015.
MICE Construction Project Update: SSs, PRY, Cavities, Tracker… 1MAP Friday Meeting – January 30, 2015 Alan Bross.
Status of the MICE RF System K Ronald, University of Strathclyde For the MICE RF team 1MICE Project Board, 6th April 2016.
MICE RF – Installation at RAL Tim Stanley RAL 7 November 2013.
MICE RF – Installation at RAL Tim Stanley, MICE RF Engineer, RAL 2 June 2014.
Andrew Moss STFC, ASTeC Example amplifier control system Example of current STFC copper cavity in operation –Using SF6 insulated waveguide –Conditioning.
MICE Demonstration of Ionisation Cooling Colin Whyte University of Strathclyde On behalf of the MICE collaboration 1RF Review 9th-10th Sept. 2015, Abingdon.
Standalone Commissioning Plan in MICE Hall K Ronald, University of Strathclyde For the MICE RF team 1MICE RF Review 9th Sept 2016.
RF Module Integration Colin Whyte University of Strathclyde on behalf of the MICE collaboration 1RF Review 9th & 10th Sept '15 Abingdon.
US Construction Project: SSs, PRY, Cavities and test program 1.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
Linac RF System Design Options Y. Kang RAD/SNS/NScD/ORNL Project – X Collaboration Meeting April , 2011.
RF System to RF Module Interface C Whyte, University of Strathclyde For the MICE RF team 1 MICE RF Module Engineering Review LBNL Center for Beam Physics.
The RF Phase Determination for MICE Alexander Dick For the MICE RF Team.
Muon-transit RF Phase Determination K Ronald, University of Strathclyde For the MICE RF group 1MICE Optics Review, 15th January 2016.
Andrew Moss ASTeC, Daresbury Laboratory October 2010 MICE RF Amplifier Status.
Areal RF Station A. Vardanyan
L. Coney UC Riverside MICE CM32 – Glasgow – June 2012
Resource Loaded Schedule and Budget Profile
Status of the MICE RF System
Completion of the MICE-US construction project
MICE RF System Power Supplies, Control and Monitoring Status report
RF Layout 3pi/2 for Discussion
Progress on the MICE RF Systems
Presentation transcript:

Status of the MICE RF System K Ronald, University of Strathclyde For the MICE RF team 1MICE Project Board, 17th April 2015

Content 2 Redesigned distribution network Change from STEP V design Used under-floor delivery The demonstration experiment has simpler distribution requirements Now makes sense to use ‘over air gap’ network Status of RF drive system Plans for test, delivery and installation of amplifiers Development of LLRF controls Status of the LLRF resources Muon-RF phase determination Initial tests with waveforms from MTA tests Hardware now at Strathclyde for RF tests MICE Project Board, 17th April 2015

MICE HPRF systems 3 MICE HPRF system requirements have changed Fewer cavities, no coupling coil Required operational date is Summer 2017 Enables demonstration of ionisation cooling with re-acceleration Data campaign complete before end US fiscal year 2018 The MICE Demonstration of Ionisation Cooling requires Two individual cavities bracketed by two thin LiH absorbers, sandwiching main absorber Cavities themselves are unchanged Each cavity is 430mm long with a Q of 44,000 and is resonant at MHz The cavities must still operate in a strong magnetic field environment Cavities are estimated (by simulation) to deliver 8MV/m at 1MW dissipation- shunt impedance 5.9 M  A. Bross has reported on the ongoing tests at FNAL MICE Project Board, 17th April 2015

MICE HPRF systems 4 The MICE Demonstration of Ionisation Cooling requires Two individual cavities bracketed by two thin LiH absorbers, sandwiching main absorber Cavities Technical Details Each cavity is 430mm long with a Q of 44,000 and is resonant at MHz The cavities must still operate in a strong magnetic field environment Cavities are estimated (by simulation) to deliver 8MV/m at 1MW dissipation- shunt impedance 5.9 M  2MW peak output from RF drive amplifiers, also unchanged LLRF requires ~10 % overhead to achieve regulation Estimated ~10 % loss in transmission line Power delivered to each cavity 1.62 MW, Anticipated gradient in each cavity 10.3 MV/m Slight uplift in gradient from 7.2 MV/m in each ‘STEP V’ cavity MICE Project Board, 17th April 2015

RF network: STEP V/VI 5MICE Project Board, 17th April 2015 Amplifiers installed behind shield wall Triodes on main floor, Tetrodes on Mezzanine Impact of B-fields negated by yoke Line installation planed before yoke support risers High power dynamic phase shifters removed 4 off 6 inch coax lines over wall Pressurised to increase power handling Line lengths matched using 3D CAD Manually adjustable line trimmers installed at cavity to take up assembly errors in coax length Flexible coax final feeds Allows for small misalignments 10 hybrid splitters Split power for the opposed couplers of each cavity Lines will be pressurised with 2Bar Nitrogen Amplifiers behind Shield Wall Distribution Network to MICE

RF network: Demonstration experiment 6MICE Project Board, 17th April 2015 Offcentre mounting of hybrid allows neat take up of 90 degree phase Orientation of load arbitrary- plan to align with the 6” distribution line and share mountings Minimised length of 4” line- minimises breakdown and losses Flexible coax Line Trimmers Hybrid Splitter Directional Coupler in each line 4616 Pre Amplifier TH116 Amplifier 500kW Load Directional Coupler 6 inch

RF network: Demonstration experiment 7MICE Project Board, 17th April 2015 Propose to have 1 load on the hybrid splitter to each RF cavity absorbs unbalanced reflections Crane hook height fully retracted does not clash with the coax over the wall. Support for network will be from present ‘shield wall’ and from yoke supports

RF network: Demonstration experiment 8MICE Project Board, 17th April nd TH116 amplifier moved to 3 rd position behind wall to use the space and ease installation in congested area With only 2 RF amplifiers now relatively straightforward to place auxiliary systems (cooling) Water cooling for load will need to route over the air gap on the transmission lines

RF network: Demonstration experiment 9MICE Project Board, 17th April 2015 Offcentre mounting of hybrid allows neat take up of 90 degree phase Orientation of load arbitrary- plan to align with the 6” distribution line and share mountings Minimised length of 4” line- minimises breakdown and losses

RF network: Demonstration experiment 10MICE Project Board, 17th April 2015 With slightly higher mounting of the RF network, work platform can be accommodated above channel Such a platform can be useful for RF and other work RF assemblies from hybrids to flexible lines can be prebuilt and craned in as components Rapid assembly and servicing/access

Implications for Power Distribution Network 11 The change to a two cavity system has some implications for the RF line loading New experiment will demand higher power (1MW peak, 1kW average) in 4” lines under floor Plan to implement SF 6 insulation 4” lines and components rated to 1.12MW peak in air at 1 bar (data from manufacturer/supplier) Likely during full reflect during cavity fill we will have up to double the voltage on the line (eq. to 4MW) This will be mitigated by slow fill Also mitigate with insulating gas MICE Project Board, 17th April 2015

HPRF System Status 12 MICE RF systems demonstrated Nominal power levels 2MW, Frequency (201.25MHz) for 1Hz First amplifier tested in MICE hall Triode amplifier (output stage) remains installed Tetrode and all modulator racks shipped to Daresbury New higher voltage solid state crowbar tested Electrical completion of triode No. 2 will commence Triode 2 will be tested using No. 1 tetrode and modulators Will use upgraded Triode No.1 modulator Each major No. 1 subsystem will be swapped for No. 2 sequentially Make fault finding more rapid Remote control philosophy being developed Will be tested during commissioning of No. 2 system Dependent on electrical engineering resource availability No 1 tetrode ready for re-commissioning at DL July 2015, Triode No 2 tests with No 1 racks and tetrode Design/Build Control Rack for No 1 racks- August 2015 Nov 2015, No 2 amplifiers tested with No 1 racks & controls MICE Project Board, 17th April 2015

Cooling Demonstration: Preparation Programme 13 From STEP IV the project becomes increasingly focussed on RF systems Relevant to define RF de-risking programme First cavities expected May 2016 Opportunity to perform system shakedown Cavity can be installed ‘upstream’ and parallel to beamline enclosure Installation between ISIS run cycles Opportunity to test vacuum pump down and clean and bake cavity Special transmission lines can be run from amplifier station no 1 Shielding can be provided across hall near upstream SS Triode amplifier No 1 already installed Require re-installation of entire RF amplifier chain Aux racks, Modulator racks, SSPA, Tetrode amplifier Require automation and control logic Require LLRF system Timing diagnostic: development of hardware Tested on bench at Strathclyde Test at MTA MICE Project Board, 17th April 2015

Preparation Programme: Timeframes 14 Amplifier No 1 programme Definition of controls and automation system/interfaces/interlocks End April Draft documents under review Amplifier no 1 automation system on PSU completion during 2015 Commission and test amplifier no 2 with automation & no 1 racks, Nov 2015 Re-Installation and test into loads at RAL with triode no 1, mid Aug 2016 Key resources, Electrical Engineering Effort 1 FTE EE, 0.5 FTE ED, 1 FTE ET, 0.5 FTE CE, 0.4 FTE MT Control and Monitoring programming: Pierrick Hanlet (time?) RF & EE system specification/RF & EE system testing: T Stanley, C White, S Griffiths, S Alsari, K Ronald, CG Whyte, AR Young with consulting input from A Moss 1-2 months of test operation through 2015, 2 months installation time. Team drawn from above list (minimum 2, ideally 3 required at any time) MICE Project Board, 17th April 2015

Preparation Programme: Timeframes 15 Cavity No 1 programme Arrival May 2016: Assume the modules are delivered assembled from LBNL Test tuning and prepare for vacuum operation Require clean room, may require tuning of couplers Require exercising of the tuners 2 weeks, RF (Ronald, Stanley, Whyte, Alsari) and mechanical technicians Prepare for evacuation, pump, gauge installation: Vacuum engineer and mechanical technicians 4 weeks Install in upstream space beside beamline (or next to shield wall), install X-ray shield 2 weeks Evacuation, Baking, estimate 2 weeks (RF and Vacuum Engineering) Install, tune overhead RF lines, 2 weeks concurrent with evacuation (RF, Mech. Technicians) Retest of cavity tune after bake and evacuation, 1 week Potential to be ready around July 2016 MICE Project Board, 17th April 2015

Preparation Programme: Timeframes 16 HPRF Tests, can start late August 2016, 4 weeks for each cavity As soon as amplifier no. 1 is available Requires modification of the controls system development Hitherto one rack was planned to control two amplifiers To facilitate tests would need to build discrete control racks for each system Seems feasible given sufficient Electrical Engineering Resource through Requires LLRF control Requires RF staffing needs addressed urgently on the software side Second cavity can be commissioned partially in parallel and be ready for test as soon as 1 st cavity completed Benefits Full shakedown of RF system Pre-prepped cavities by end 2016 MICE Project Board, 17th April 2015

HPRF System Controls 17 Plans exist (in discussion) for the controls and monitoring interfaces required for the RF system and interfacing to other vital subsystems Will allow expedited remote control and logging to be built as soon as effort is available Each Cavity: 17 analogue inputs, 2 analogue outputs, 4 digital inputs (2 logic states) Each RF system: 24 digital inputs (2 logic states), 4 digital inputs (3 states), 1 digital input (8+ logic states), 22 analogue inputs (12 are high, ~MHz, speed), 3 analogue inputs Note many of these may be reasonably logically ‘ANDed’ outside the control logic- simplifying the system and moderating cost and build time MICE Project Board, 17th April 2015

RF Control System RF systems will require remote, automated control system ‘State Machine’ description being evolved by MICE Team Headline list of primary states and required conditions below 18MICE Project Board, 17th April 2015 OFF No conditions ENABLED Hardware keys inserted STANDBY Heaters Nominal Hardware keys RF load coolant (3) RF tube coolant (5) Compressed Air PSU coolant Mains Quality READY PPS RF Permit HT enclosures shut Heaters Nominal Cavity and Vessel pressure Nominal Cavity coolant Nominal Cavity tuner pressures SF 6 pressure Hardware keys RF load coolant (3) RF tube coolant (5) Compressed Air PSU coolant Mains Quality ON Nominal RF waveforms Radiation & Arc sensors PPS RF Permit HT enclosures shut Heaters Nominal Cavity and Vessel pressure Nominal Cavity coolant Nominal Cavity tuner pressures SF 6 pressure Hardware keys RF load coolant (3) RF tube coolant (5) Compressed Air PSU coolant Mains Quality

LLRF systems MICE LLRF: provide 1% amplitude, 0.5 o phase regulation Will control tuner system LLRF system being developed by Daresbury LLRF group Using digital LLRF4 boards already procured First board operating at 201MHz in tests during August 2014 Synergy with ISIS requirements for LLRF system For new ISIS LINAC amplifier test and commissioning stand Similar installation to the MICE amplifier test stand System is closely related to the implementation for existing Daresbury accelerators 0.1 % amplitude and 0.3 o demonstrated in 1.3 GHz accelerating cavities Power ramp programming already demonstrated Boards will be tested during the amplifier commissioning programme LLRF system no 1 resources Crate build up, A Moss and DL Electronics staff Software: Expedite recruitment of experienced XILINX programmer: Synergistic with ASTEC/DL requirements: Exploring use of software work at ISIS building on DL practice. Completion of system No 1 by end test at DL then RAL 19MICE Project Board, 17th April 2015

Timing System, Desired Specification We wish to know the difference between Transit time of any of our muons (in essence through ToF1) A zero crossing of the RF system in any cavity- choose the first cavity Use tracker measurement of trajectories to project forward to each cavity in turn LLRF phase (0.5 o ) stability specification is ~3x stricter than the resolution desired for the RF timing system <20ps or <0.4% of the RF cycle In turn specification for RF timing is ~3x stricter than ToF resolution 50ps ~1% Should mean the timing accuracy is ~1% of RF cycle, defined by ToFs resolution Stability, and/or accurate knowledge, of all parameters in the system will be important Long cable runs, with dielectric insulated coaxial lines? Phase relationship between the cavity fields and the signals on the test ports Relationship between ToF signals and actual Muon transit MICE Project Board, 17th April

Overview of Timing Critical Elements Sketch illustrates relationships of key components in the Demonstration experiment Work in progress: Mathematical tests of digitiser interpolation Test sensitivity to vertical resolution, temporal sample rate, noise Work to be undertaken: Test TDC/Discriminators in MHz environment ToF 1 Cavity 1 RF Amp 1 LLRF Beamline HPRF RF Drive LLRF Feedback TDC’s (ToF) TDC’s (RF) Digitisers Datarecorders RF Clock Trigger Discriminators (RF) Discriminators (ToF) ToF Signals RG MHz LLRF MO MO Signal (RG213) Computers RF Amp 2 HPRF Cavity 2 RF Drive Cavity 2 (RG213) Cavity 1 (RG213) MICE Project Board, 17th April

‘Sub’ Nyquist digitisation To acquire at Nyquist on 200MHz would demand a sampling rate of ~1-2G.Sa/sec, for 1ms – Demands ~1 to 2MB per acquired channel, > 7.2GB/hr (assuming an 8 bit digitiser) – 400  s window presently being acquired at MTA- requires minutes of time to record traces Fourier domain signal reconstruction – The Fourier transform of the undersampled data maps the signal into its ‘unaliased’, relatively low frequency range We may then retransform to the time domain to determine the time evolution of the signal at some arbitrary point in time Must satisfy Nyquist on the linewidth- for our cavity natural linewidth is ~5kHz, effective linewidth is ~10kHz, so sampling rate ~few hundred k.Sa/sec should be sufficient We assume 20M.Sa/sec, with 1ms we now have about 20kB per 8 bit recorded channel, data rate of ~72MB/hr per channel MICE Project Board, 17th April

Comparison of rebuilt 20M.Sa/sec subsampled oscilloscope signal with 5G.Sa/sec recording: LeCroy 625Zi MICE Project Board, 17th April Visit to FNAL brought 100’s GB of data – Strathclyde has been processing these real traces using subsample Fourier domain reconstruction

Timing hardware and Tests Use TDC and discriminators used in ToF system TDC’s CAEN V ps multi-hit 25ps bin size maps to 7ps uncertainty (assuming Uniform PDF) LeCroy 4415A discriminators Needs to be tested in RF environment (alternatives available) Use of same electronics as ToF mitigates systematic uncertainty & drift TDC hardware, discriminators and crates now assembled at Strathclyde. RF connection boards being fabricated to allow tests at RF frequencies To make efficient integration into DAQ ideally use VME digitisers for the sub- sample reconstruction At present continue to use fast, 8 bit, DSO’s to capture signal Plan to use CAEN V1761 digitisers 1GHz, 4G.Sa/sec, 10 bit, 2 Channel instrument Capable of 57.6MS/Ch 24MICE Project Board, 17th April 2015

Summary 25MICE Project Board, 17th April 2015 Substantial redesign of distribution network Mitigates installation conflicts (both schedule and potential physical) Eliminates most of the 4” line Control/Automation requirements defined in draft form Needed to expedite control rack construction Expedited construction of control rack No 1 can enable full system and conditioning in late 2016 Will debug system ahead of operation in summer 2017 LLRF staffing issue has emerged Key software expertise has left Daresbury Require to address this urgently as also required to allow system test in late 2016 Possible solution based on development of DL system at ISIS Fourier domain reconstruction progressing with REAL pick off data from MTA Some variation in offset to understand Hardware to test TDC approach largely assembled