OPER 576 Project Management Reducing Project Duration or Project Crashing Greg Magnan, Ph.D. May 20, 2004.

Slides:



Advertisements
Similar presentations
Chapter 7 Project Management
Advertisements

F O U R T H E D I T I O N Project Management © The McGraw-Hill Companies, Inc., 2003 supplement 3 DAVIS AQUILANO CHASE PowerPoint Presentation by Charlie.
CHAPTER 17 Project Management.
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
Terminology Project: Combination of activities that have to be carried out in a certain order Activity: Anything that uses up time and resources CPM: „Critical.
pert and cpm ch 9 Learning objectives:
SW Project Management Project Schedule and Budget
1 1 Slide © 2009 South-Western, a part of Cengage Learning Slides by John Loucks St. Edward’s University.
1 7.1 Introduction A project is a collection of tasks that must be completed in minimum time or at minimal cost. Tasks are called “activities.” –Estimated.
CHAPTER 4 MANAGING PROJECT PROCESSES. THE CONCEPT A project is an interrelated set of activities that has a definite starting and ending point and that.
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edward’s University.
Chapter 10 Project Scheduling: PERT/CPM
Chapter 9: Reducing Project Duration
Reducing Project Duration
SWE Introduction to Software Engineering
Reducing Project Duration
Software project management (intro)
Time-Cost Trade-Off (Time Reduction = Time Compression = Time Shortening) 4/17/ :55 AM.
OPERATIONS MANAGEMENT INTEGRATING MANUFACTURING AND SERVICES FIFTH EDITION Mark M. Davis Janelle Heineke Copyright ©2005, The McGraw-Hill Companies, Inc.
Analyzing Cost-Time Trade-Offs There are always cost-time trade-offs in project management. – You can completing a project early by hiring more workers.
Time Management Week 7 - Learning Objectives You should be able to: n List and describe the processes, activities, inputs, and outputs in time management.
Allocating Resources to the Project
Project Management OPER 576 Resource Allocation Greg Magnan, Ph.D. May 6, 2004.
Quick Recap Monitoring and Controlling. 2 Control Project Cost.
Projects CHAPTER 10. Learning Objectives 1. Explain what project management is and why it is important. 2. Identify the different ways projects can be.
Time/Cost Trade-off Analysis
1 Slides used in class may be different from slides in student pack Chapter 3 Project Management  Definition of Project Management  Structuring Projects.
Chapter 9: Reducing Project Duration
Managing Project Resources. Project Resources Human Resources Project stakeholders: – Customers – Project team members – Support staff Systems analyst.
Time-Cost Tradeoffs Time-Cost Tradeoff Example Time-Cost Tradeoff Example (cont’d) Project Duration (weeks)Critical Path(s)Task(s) Reduced Total Direct.
“WHY ARE PROJECTS ALWAYS LATE?” (“and what can the Project Manager DO about that?) Craig Henderson, MBA, PMP ARVEST Bank Operations.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 17 Project Management Part.
1 Project Planning, Scheduling and Control Project – a set of partially ordered, interrelated activities that must be completed to achieve a goal.
Work Systems and the Methods, Measurement, and Management of Work by Mikell P. Groover, ISBN ©2007 Pearson Education, Inc., Upper Saddle.
Time-Cost Trade-Off (Time Reduction = Time Compression) (Time Shortening) Time-Cost Trade-Off (Time Reduction = Time Compression) (Time Shortening)
1 1 Project Scheduling PERT/CPM Networks. 2 2 Originated by H.L.Gantt in 1918 GANTT CHART Advantages - Gantt charts are quite commonly used. They provide.
1 1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Reducing Project Duration CHAPTER NINE Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Reducing Project Duration CHAPTER NINE Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
0 Production and Operations Management Norman Gaither Greg Frazier Slides Prepared by John Loucks  1999 South-Western College Publishing.
Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Patterson University Copyright 2007 John Wiley & Sons, Inc.5-1.
CPM – Critical Path Method Can normal task times be reduced? Is there an increase in direct costs? Additional manpower Additional machines Overtime, etc…
1 6. T IME -C OST O PTIMIZATION Objective: The optimization of project duration and cost by an appropriate crashing of activities. Summary: 6.1 Finding.
 Delay in project implementation invariably results in cost- overrun.  Delayed project implementation means delay in getting return on investments made.
TOPIC-6- TIME-COST TRADE OFF
1 Slides used in class may be different from slides in student pack Chapter 3 Project Management  Definition of Project Management  Work Breakdown Structure.
COB 300C Project Management Dr. Michael Busing. PERT ANALYSIS Optimistic-Likely-Pessimistic Project Times If you hold someone to a certain number, they.
3/18/ :47 AM 1 Time-Cost Trade-Off (Time Reduction = Time Compression = Time Shortening)
University Of Palestine Faculty Of Applied Engineering & Urban Planning Civil Engineering Department PROJECT MANAGEMENT Scheduling Resources and Costs.
Time-Cost Trade-off Models
Project Management 6e..
Reducing Project Duration
Chapter 16 – Project Management
Project Management Chapter 8.
Project Management.
Project Management Chapter Topics
Reducing Project Duration
Project Planning & Scheduling
UNIT II Scheduling Procedures & Techniques CRITICAL PATH ANALYSIS
Probabilistic Time Estimates
Chapter 3 Project Management.
Lecture 6: Time-Cost Trade-Offs
Manajemen Industri Teknologi informasi
Project Management Dr. Michael Busing
Reducing Project Duration
Where We Are Now. Where We Are Now Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity.
Where We Are Now. Where We Are Now Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity.
Where We Are Now. Where We Are Now Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity.
Presentation transcript:

OPER 576 Project Management Reducing Project Duration or Project Crashing Greg Magnan, Ph.D. May 20, 2004

Project Life Cycle Stages

Recall Pert/CPM Estimates

More PERT/CPM Estimates Activity Time Estimates for beta distribution –a: optimistic time, usually about 1 percent chance activity can be completed within a –b: most likely time –c: pessimistic time, usually about 1 percent chance that activity will take longer than c. Activity j’s expected time (b distribution) Activity j’s variance (b distribution)

PERT Notation D -- the desired project duration T e -- expected project duration Critical path variance = Z = number of standard normal deviates from mean =

Project Completion Probability What is the probability of finishing this project in less than 53 days? p(t < D) T E = 54 t D=53

PERT Network A(7) B (5.333) C(14) D(5) E(11) F(7) H(4) G(11) I(18) Duration = 54 Days  2 (A) =2 2 =4  2 (C) =16  2 (E) =4  2 (H) =1  2 (I) =16

(Sum the variance along the critical path.) = 41

There is a 43.6% probability that this project will be completed in less than 53 weeks. p(Z < -.156) = =.436, or 43.6 % T E = 54 p(t < D) t D=53

Crashing Activities Activity & project duration may be influenced by resource allocation decisions…more resources—less time needed Sometimes, we can expedite completion of a task by assigning more people or equipment. Thus, total direct costs tend to vary inversely with project duration. Indirect costs, however, tend to increase with overall project completion time. Total Costs Indirect Costs Direct Costs Project duration Expense

Time-Cost Tradeoffs in CPM Basic Assumption: Some activities can be expedited, at a cost Why accelerate an activity? –Complete the task in a shorter duration, thereby reducing the duration of the critical path, thereby reducing the length of the project Avoid late penalties Earn early completion incentive payments Time Cost Problem: Determine the optimum project duration based on time- cost tradeoffs

Project & Activity Costs PROJECT DIRECT COSTS: Directly assigned to work package or activity –“Normal” costs for “normal” time Direct labor expenses Materials Equipment Subcontractors INDIRECT EXPENSES: Cannot be associated with any work package or activity –Overhead expenses including supervisory expenses administration contractual penalties or early completion incentives –Consulting

Time & Costs: Normal vs. Crash For the time-only CPM project schedule, we typically assume that activity duration is fixed at its NORMAL TIME, or the duration with the lowest direct activity cost (i.e., NORMAL COST). However, some activities may be expedited if higher resource levels are available. The shortest activity duration is called CRASH TIME. The cost to complete an activity in that amount of time is called CRASH COST.

Linear Time-Cost Tradeoff In theory, the normal or expected duration of a task can be reduced by assigning additional resources to the task Time Cost Crash Point Normal Point Slope (b j ) = Increase in cost by reducing task by one time unit Normal timeCrash time Normal cost Crash cost

Selecting Activities to Crash Cost Slope = Rise / Run Cost Slope = CC – NC / NT – CT = CC – NC NT – CT where, –CC = Crash Cost –NC = Normal Cost –NT = Normal Time –CT = Crash Time Calculate for each activity on Critical Path = CC – NC = $800 - $400 NT – CT 10 – 5 = $400/5 = $80 per unit of time

Balancing Overhead & Direct Costs Project Duration Cost Indirect (overhead) Costs Direct Costs Total Cost Crash Time Normal Time Minimum Cost Solution

Software Project Schedules “Observe that for the programmer, as for the chef, the urgency of the patron may govern the scheduled completion of the task, but it cannot govern the actual completion. An omelet, promised in ten minutes, may appear to be progressing nicely. But when it has not set in ten minutes, the customer has two choices--wait or eat it raw. Software customers have the same choices. The cook has another choice; he can turn up the heat. The result is often an omelet nothing can save--burned in one part, raw in another.” F.P. Brooks, “The Mythical Man-Month”, Datamation, Vol. 20, No 12 (Dec, 1974), pp

Time/Cost Trade-off Analysis You might think that total project costs will increase when we begin to crash activities But, total project costs consist of both indirect (project-based) costs (PBC) and direct (activity-based) costs (ABC) –ABC (direct) go up when we crash activities in an effort to finish the project early –But, PBC (the indirect costs) go down if we finish the project early

Which Activities are the Best Candidates for Crashing? Any activity that is on the critical path Activities with relatively long durations Bottleneck activities (that appear on multiple critical paths) Activities with relatively low costs to crash Activities that are not likely to cause quality problems if crashed Activities that occur relatively early in the schedule and are labor intensive

Options for Crashing Activities Adding Resources Outsourcing Project Work Overtime Establishing Core Project Team Temporary Fixes Fast-Tracking Critical Chain PM Brainstorming Reducing Scope Phasing Project Deliverables

Potential Problems with Crashing Reduced flexibility and less margin for error  increased risk of failure to complete project on time Raises potential for poor quality Increases potential for staff burnout, stress, and turnover (from what Yourdon calls Death March projects) Raises activity-based costs May negatively affect other projects May create unrealistic expectations for future projects Hard to know true indirect costs

Time-Cost Tradeoff Heuristic 1.Set each activity duration to its normal time. 2.Determine the critical path(s) and project duration based on the current activity times. 3.Calculate total direct costs and indirect costs for the current schedule. 4.Chose an activity or activities that can be expedited to reduce project duration by one time unit. Use cost slopes and critical path information to guide your choice. If no further reduction in project duration is possible, go to step 5. Otherwise, go to step 2. 5.Plot the project's direct and indirect costs for each possible duration. Select the duration that minimizes total costs.

Network Crashing Example

Crashing Summary In planning, crashing can pull your project into the delivery window Once started, a late project can get pulled back in to schedule compliance Crashing can increase the size of the “critical core,” thereby reducing flexibility Capability in MS Project