Presentation is loading. Please wait.

Presentation is loading. Please wait.

Chapter 3 Project Management.

Similar presentations


Presentation on theme: "Chapter 3 Project Management."— Presentation transcript:

1 Chapter 3 Project Management

2 OBJECTIVES Definition of Project Management Project Control Charts
Structuring Projects Work Breakdown Structure Critical Path Scheduling CPM with a Single Time CPM with Three Time Estimates 2

3 Project Management Defined
A series of related jobs usually directed toward some major output and requiring a significant period of time to perform Project Management The management activities of planning, directing, and controlling resources (people, equipment, material) to meet the technical, cost, and time constraints of a project 3

4 Project Management Project are usually: Infrequent
Exact duration is difficult to estimate Control may be difficult because of: Makeup of the project team Expert among experts

5 Structuring Projects: Pure Project Defined
A pure project is where a self-contained team works full-time on the project 8

6 Structuring Projects Pure Project: Advantages
The project manager has full authority over the project Team members report to one boss Shortened communication lines Team pride, motivation, and commitment are high

7 Structuring Projects: Pure Project Disadvantages
Duplication of resources Equipment and people not shared across projects Organizational goals and policies are ignored Team members detached from headquarters Lack of technology transfer Due to weakened functional division Team members have no functional area "home“ Project termination often delayed as members worry about life after the project 8

8 Structuring Projects: Functional Projects Defined
A functional project is housed within a functional division President Research and Development Engineering Manufacturing Project A B C D E F G H I Example, Project “B” is in the functional area of Research and Development. 9

9 Structuring Projects: Functional Project Advantages
A team member can work on several projects Technical expertise is maintained within the functional area The functional area is a “home” after the project is completed Critical mass of specialized knowledge 10

10 Structuring Projects: Functional Project Disadvantages
Aspects of the project that are not directly related to the functional area get short-changed Motivation of team members is often weak Needs of the client are secondary and are responded to slowly 11

11 Structuring Projects: Matrix Project Organization Structure
President Research and Development Engineering Manufacturing Marketing Manager Project A Project B Project C 12

12 Structuring Projects: Matrix Project Advantages
Enhanced communications between functional areas Pinpointed responsibility Duplication of resources is minimized Functional “home” for team members Policies of the parent organization are followed 13

13 Structuring Projects: Matrix Projects Disadvantages
Too many bosses Functional manager often listened to first because of direct influence on promotions and raises Depends on project manager’s negotiating skills Potential for sub-optimization PM’s could hoard resources for own projects Other projects could be harmed 14

14 Phases of Project Management
Planning Work breakdown structure Feasibility study Precedence determination Scheduling Construct the chart and apply times Identify priorities Execution and control Review and modify the project

15 Work Breakdown Structure Defined
A work breakdown structure defines the hierarchy of project tasks, subtasks, and work packages Program Project 1 Project 2 Task 1.1 Subtask 1.1.1 Work Package Level 1 2 3 4 Task 1.2 Subtask 1.1.2 Work Package 4

16 Work Breakdown Structure
Allows the elements to be worked on independently Make them manageable in size Give authority to carry out the program Monitor and measure the program Provide the required resources

17 Project Control Charts: Gantt Chart
Vertical Axis: Always Activities or Jobs Horizontal bars used to denote length of time for each activity or job. Activity 1 Activity 2 Activity 3 Activity 4 Activity 5 Activity 6 Time Horizontal Axis: Always Time 6

18 Network-Planning Models
A project is made up of a sequence of activities that form a network representing a project The path taking longest time through this network of activities is called the “critical path” The critical path provides a wide range of scheduling information useful in managing a project Critical Path Method (CPM) helps to identify the critical path(s) in the project networks 15

19 Prerequisites for Critical Path Methodology
A project must have: well-defined jobs or tasks whose completion marks the end of the project; independent jobs or tasks; and tasks that follow a given sequence. 16

20 Types of Critical Path Methods
CPM with a Single Time Estimate Used when activity times are known with certainty Used to determine timing estimates for the project, each activity in the project, and slack time for activities CPM with Three Activity Time Estimates Used when activity times are uncertain Used to obtain the same information as the Single Time Estimate model and probability information Time-Cost Models Used when cost trade-off information is a major consideration in planning Used to determine the least cost in reducing total project time 15

21 Steps in the CPM with Single Time Estimate
Activity Identification Activity Sequencing and Network Construction Determine the critical path From the critical path all of the project and activity timing information can be obtained 15

22 Example 1. CPM with Single Time Estimate
Consider the following consulting project: Activity Designation Immed. Pred. Time (Weeks) Assess customer's needs A None 2 Write and submit proposal B 1 Obtain approval C Develop service vision and goals D Train employees E 5 Quality improvement pilot groups F D, E Write assessment report G Develop a critical path diagram and determine the duration of the critical path and slack times for all activities.

23 Example 1: First draw the network
Act. Immed. Pred. Time A None 2 B A 1 C B 1 D C 2 D(2) E(5) E C 5 F D,E 5 G F 1 F(5) A(2) B(1) C(1) G(1) 18

24 Example 1: Determine early starts and early finish times
EF=6 D(2) E(5) ES=0 EF=2 ES=2 EF=3 ES=3 EF=4 ES=9 EF=14 ES=14 EF=15 F(5) A(2) B(1) C(1) G(1) ES=4 EF=9 Hint: Start with ES=0 and go forward in the network from A to G. 21

25 Example 1: Determine late starts and late finish times
Hint: Start with LF=15 or the total time of the project and go backward in the network from G to A. ES=4 EF=6 D(2) E(5) ES=0 EF=2 ES=2 EF=3 ES=3 EF=4 ES=9 EF=14 ES=14 EF=15 LS=7 LF=9 F(5) A(2) B(1) C(1) G(1) ES=4 EF=9 LS=3 LF=4 LS=2 LF=3 LS=0 LF=2 LS=9 LF=14 LS=14 LF=15 LS=4 LF=9 22

26 Determining the Critical Path & Slack
A path is a sequence of connected activities running from start to end node in a network The critical path is the path with the longest duration in the network It is also the minimum time, under normal conditions, to complete the project Delaying activities on the critical path will delay completion time for the project A slack is amount of scheduling flexibility Critical activities have no slacks

27 Example 1: Critical Path & Slack
SLACK=LS-ES=LF-EF ES=4 EF=6 Slack=(7-4)=(9-6)= 3 Wks D(2) ES=0 EF=2 ES=2 EF=3 ES=3 EF=4 ES=9 EF=14 ES=14 EF=15 LS=7 LF=9 F(5) A(2) B(1) C(1) G(1) ES=4 EF=9 LS=3 LF=4 LS=2 LF=3 LS=0 LF=2 LS=9 LF=14 LS=14 LF=15 E(5) A PATH IS CRITICAL IF: ES=LS, EF=LF, and EF-ES=LF-LS=D LS=4 LF=9 Duration = 15 weeks 23

28 CPM with Three Activity Time Estimates
Task times assumed variable (probabilistic) The variability is based on the beta distribution Uses three time estimates Optimistic Most Likely Pessimistic Consolidates them into one expected time Then calculates ES, EF, LS, LF, & CP as in before

29 Example 2. CPM with Three Activity Time Estimates

30 Example 2. Expected Time Calculations
ET(A)= 3+4(6) ET(A)=42/6=7

31 Example 2. Network A(7) B C(14) D(5) E(11) F(7) H(4) G(11) I(18)
ES=7 EF=21 ES=21 EF=32 A(7) B (5.333) C(14) D(5) E(11) F(7) H(4) G(11) I(18) Duration = 54 Days ES=32 EF=36 ES=0 EF=7 LS=7 LF=21 LS=21 LF=32 ES=7 EF=12 ES=12 EF=21 LS=0 LF=7 LS=32 LF=36 ES=36 EF=54 LS=20 LF=25 LS=25 LF=32 ES=0 EF=5.3 ES=5.3 EF=16.3 LS=36 LF=54 LS=19.7 LF=25 LS=25 LF=36

32 Example 2. Probability Exercise
What is the probability of finishing this project in less than 53 days? p(t < D) t D=53 TE = 54

33 (Sum the variance along the critical path.)

34 p(t < D) t TE = 54 D=53 p(Z < -.156) = .438, or 43.8 % (NORMSDIST(-.156) There is a 43.8% probability that this project will be completed in less than 53 weeks.

35 Example 2. Additional Probability Exercise
What is the probability that the project duration will exceed 56 weeks? 30

36 Example 2. Additional Exercise Solution
TE = 54 p(t < D) D=56 p(Z > .312) = .378, or 37.8 % (1-NORMSDIST(.312)) 31

37 Time-Cost Models Basic Assumption: Relationship between activity completion time and project cost Time Cost Models: Determine the optimum point in time-cost tradeoffs Activity direct costs Project indirect costs Activity completion times 32

38 Time-Cost Model Trade-Offs
Prepare a CPM-type network listing Normal and crash times for each Normal and crash costs for each Determine incremental cost per unit of time each activity is expedited Incremental cost =(CC-NC)/(NT-CT) Calculate the critical path Shorten the CP at the least cost

39 Time-Cost Model: Example
For the project with the following times, find the cost of reducing its duration to its lowest possible time. If the project is reduced by just 2 days, how much would it cost? NORMAL CRASH Activity Time Cost Time Cost IN CL=NT-CT A B C D

40 B B A A D D C C B B A A D D C C ES= EF= ES= EF= 1 2 ES= EF= ES= EF=
LS= LF= LS= LF= A A D D LS= LF= LS= LF= LS= LF= LS= LF= ES= EF= ES= EF= C C LS= LF= LS= LF= ES= EF= ES= EF= 3 4 B B ES= EF= ES= EF= ES= EF= ES= EF= LS= LF= LS= LF= A A D D LS= LF= LS= LF= LS= LF= LS= LF= ES= EF= ES= EF= C C LS= LF= LS= LF=

41 B B A A D D C C B B A A D D C C ES= EF= ES= EF= 1 2 ES= EF= ES= EF=
LS= LF= LS= LF= A A D D LS= LF= LS= LF= LS= LF= LS= LF= ES= EF= ES= EF= C C LS= LF= LS= LF= ES= EF= ES= EF= 3 4 B B ES= EF= ES= EF= ES= EF= ES= EF= LS= LF= LS= LF= A A D D LS= LF= LS= LF= LS= LF= LS= LF= ES= EF= ES= EF= C C LS= LF= LS= LF=

42 CPM Assumptions/Limitations
Project activities can be identified as entities (There is a clear beginning and ending point for each activity.) But this is seldom true Project activity sequence relationships can be specified and networked Sometime we do not know all project activities ahead of time 15

43 CPM Assumptions/Limitations
Project control should focus on the critical path But there are near-critical activities The activity times follow the beta distribution, with the variance of the project assumed to equal the sum of the variances along the critical path But activities are infrequent. Can we assume normality? Are we really sure that it is beta distributed?

44 Chapter3: Problem 7 #s: a, b, c B,2 E,3 H,4 A,3 C,6 F,2 I,5 K,6.8 D,5
ES= EF= ES= EF= B,2 E,3 ES= EF= H,4 ES= EF= ES= EF= ES= EF= ES= EF= A,3 C,6 F,2 I,5 ES= EF= K,6.8 ES= EF= ES= EF= ES= EF= D,5 G,7 J,4

45 Chapter3: Problem 7 #: d(1) B,2 E,1 H,4 A,3 C,6 F,2 I,5 K,6.8 D,5 G,7
ES= EF= ES= EF= B,2 E,1 ES= EF= H,4 ES= EF= ES= EF= ES= EF= ES= EF= A,3 C,6 F,2 I,5 ES= EF= K,6.8 ES= EF= ES= EF= ES= EF= D,5 G,7 J,4

46 Chapter3: Problem 7 #: d(2) B,2 E,3 H,4 A,3 C,4 F,2 I,5 K,6.8 D,5 G,7
ES= EF= ES= EF= B,2 E,3 ES= EF= H,4 ES= EF= ES= EF= ES= EF= ES= EF= A,3 C,4 F,2 I,5 ES= EF= K,6.8 ES= EF= ES= EF= ES= EF= D,5 G,7 J,4

47 Chapter3: Problem 7 #: d(3) B,2 E,3 H,4 A,3 C,6 F,2 I,5 K,6.8 D,5 G,5
ES= EF= ES= EF= B,2 E,3 ES= EF= H,4 ES= EF= ES= EF= ES= EF= ES= EF= A,3 C,6 F,2 I,5 ES= EF= K,6.8 ES= EF= ES= EF= ES= EF= D,5 G,5 J,4


Download ppt "Chapter 3 Project Management."

Similar presentations


Ads by Google