A) If average demand per day is 20 units and lead time is 10 days. Assuming zero safety stock. ss=0, compute ROP. b) If average demand per day is 20 units.

Slides:



Advertisements
Similar presentations
Re-Order Point Problems Set 1: General
Advertisements

Stochastic Inventory Modeling
Inventory Management for Independent Demand Chapter 12, Part 2.
Distribution Inventory Systems Dr. Everette S. Gardner, Jr.
Inventory Control Chapter 17 2.
OPSM 301 Operations Management Class 16: Inventory Management: safety inventory Koç University Zeynep Aksin
Inventory Management McGraw-Hill/Irwin Copyright © 2012 by The McGraw-Hill Companies, Inc. All rights reserved.
12 Inventory Management.
1 Part II: When to Order? Inventory Management Under Uncertainty u Demand or Lead Time or both uncertain u Even “good” managers are likely to run out once.
Supply Chain Logistics Management
McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. 12 Inventory Management.
12 Inventory Management.
Chapter 12 Inventory Management
Operations Management
Other Inventory Models 1. Continuous Review or Q System 2 The EOQ model is based on several assumptions, one being that there is a constant demand. This.
Inventory Management A Presentation by R.K.Agarwal, Manager (Finance), PFC.
Chapter 13 Inventory Management McGraw-Hill/Irwin
Inventory Management IE 314: Operations Management KAMAL Lecture 7.
Transportation/Logistic Strategy Introduction to Inventory Total Cost Analysis Computation of Safety Stocks Setting Order Points Joint Replenishment Number.
Operations Management
Operations Management Inventory Management Chapter 12 - Part 2
Class 22: Chapter 14: Inventory Planning Independent Demand Case Agenda for Class 22 –Hand Out and explain Diary 2 Packet –Discuss revised course schedule.
11 Inventory Management CHAPTER
(a) : If average demand per day is 20 units and lead time is 10 days. Assuming zero safety stock. ss=0, compute ROP? (b): If average demand per day is.
Customer Demand Customer demand varies in both timing and quantity:
Chapter 12: Inventory Control Models
EOQ: How much to order; ROP: When to order Re-Order Point (ROP) in periodic inventory system is the start of the period. Where is ROP in a perpetual system?
Inventory Management McGraw-Hill/Irwin Copyright © 2012 by The McGraw-Hill Companies, Inc. All rights reserved.
Managing Flow Variability: Safety Inventory
13 Inventory Management.
Re-Order Point Problems Set 2: NVP
McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. 12 Inventory Management.
Inventory- a stock or store of goods
Inventory Management.
13-1 McGraw-Hill/Irwin Operations Management, Seventh Edition, by William J. Stevenson Copyright © 2002 by The McGraw-Hill Companies, Inc. All rights reserved.
Solved Problems Chapter 12: Inventory 1. Solved Problem The data shows projected annual dollar usage for 20 items. Exhibit 12.3 shows the data sorted,
1 Slides used in class may be different from slides in student pack Chapter 17 Inventory Control  Inventory System Defined  Inventory Costs  Independent.
1 Inventory Analysis under Uncertainty: Lecture 6 Leadtime and reorder point Uncertainty and its impact Safety stock and service level Cycle inventory,
1 Managing Flow Variability: Safety Inventory Forecasts Depend on: (a) Historical Data and (b) Market Intelligence. Demand Forecasts and Forecast Errors.
When to re-order with EOQ Ordering
Economic Order Quantity The economic order quantity (EOQ) is the fixed order quantity (Q) that minimizes the total annual costs of placing orders and holding.
Inventory Management MD707 Operations Management Professor Joy Field.
Independent Demand Inventory Planning CHAPTER FOURTEEN McGraw-Hill/Irwin Copyright © 2011 by the McGraw-Hill Companies, Inc. All rights reserved.
Inventory Management. Learning Objectives  Define the term inventory and list the major reasons for holding inventories; and list the main requirements.
Inventory Control Model
Budi Harsanto Dept. of Management & Business, Faculty of Economics, Universitas Padjadjaran Inventory Management.
LSM733-PRODUCTION OPERATIONS MANAGEMENT By: OSMAN BIN SAIF LECTURE 19 1.
Chapter 12 : Inventory Management Outline  The Importance of Inventory  Functions of Inventory  Types of Inventory.
STORES FUNCTIONS 1.RECEIPT2.STORAGE3.RETRIEVAL4.ISSUE 5.RECORD KEEPING 6.HOUSE KEEPING 7.SURPLUS MANAGEMENT 8.VERIFICATION9.COORDINATION.
1 Managing Flow Variability: Safety Inventory Forecasts Depend on: (a) Historical Data and (b) Market Intelligence. Demand Forecasts and Forecast Errors.
1. 2 Dependent VS Independent E(1) Independent Demand (Demand not related to other items) Dependent Demand (Derived)
LSM733-PRODUCTION OPERATIONS MANAGEMENT By: OSMAN BIN SAIF LECTURE 18 1.
Inventory Management for Independent Demand Chapter 12.
1 Inventory Control: Part 3 – Independent Demand Inventories.
Time Inventory Demand During Lead Time. LT ROP when demand during lead time is fixed.
Inventory Control. Meaning Of Inventory Control Inventory control is a system devise and adopted for controlling investment in inventory. It involve inventory.
McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. 12 Inventory Management.
Managing Uncertainty with Inventory I
Inventory Models (II) under SC environment
Assignment 5: Part (A) The Dine Corporation is both a producer and a user of brass couplings. The firm operates 220 days a year and uses the couplings.
NATCOR Stochastic Modelling Course Inventory Control – Part 2
Managing Uncertainty in the Supply Chain: Safety Inventory
Random Demand: Fixed Order Quantity
Inventory Management EOQ Model ROP-Reorder Point Safety Stock
Inventory Control: Part 3 –Independent Demand Inventories
a1) On average, how long a diskette spend in stock?
Managing Flow Variability: Safety Inventory
Managing Flow Variability: Safety Inventory
EOQ Inventory Management
Presentation transcript:

a) If average demand per day is 20 units and lead time is 10 days. Assuming zero safety stock. ss=0, compute ROP. b) If average demand per day is 20 units and lead time is 10 days. Assuming 70 units of safety stock. ss=70, compute ROP? c) If average demand during the lead time is 200 and standard deviation of demand during lead time is 25. Compute ROP at 90% service level. Compute ss. d) If average demand per day is 20 units and standard deviation of daily demand is 5, and lead time is 16 days. Compute ROP at 90% service level. Compute ss. e) If demand per day is 20 units and lead time is 16 days and standard deviation of lead time is 4 days. Compute ROP at 90% service level. Compute ss. ROP Problems

ROP (Re-Order Point) in periodic inventory control is the beginning of each period. ROP in perpetual inventory control is the inventory level equal to the average demand during the lead time plus a safety stock to cover demand variability. Lead Time is the time interval from placing an order until receiving the order. If there were no variations in demand (it was constant) then safety stock (ss) is zero. In the case of ss=0, ROP is when inventory on hand is equal to the average demand during the lead time. Demand Forecast, and Lead Times

a) If average demand per day is 20 units and lead time is 10 days. Assuming zero safety stock. ss = 0 Compute ROP. ROP = demand during lead time + ss ROP = demand during lead time Demand during lead time = (lead time) × (demand per unit of time) Demand during lead time = 20 × 10 = 200 ROP; Fixed d, Fixed LT, Zero SS

b) If average demand per day is 20 units and lead time is 10 days. Assuming 70 units of safety stock. ss = 70 Compute ROP. ROP = demand during lead time + ss Demand during lead time = 200 ss = 70 ROP = = 270 ROP; Fixed d, Fixed LT, Positive SS

c) If average demand during the lead time is 200 and standard deviation of demand during lead time is 25. Compute ROP at 90% service level. Compute ss ROP; total demand during lead time is variable

Risk of a stockout Service level Probability of no stockout Safety stock 0z Quantity z-scale Safety Stock and ROP Each Normal variable x is associated with a standard Normal Variable z Average demand There is a table for z which tells us a)Given any probability of not exceeding z. What is the value of z b)Given any value for z. What is the probability of not exceeding z x is Normal (Average x, Standard Deviation x)  z is Normal (0,1) ROP

Common z Values RiskService levelz value Risk of a stockout Service level Probability of no stockout Safety stock 0z Quantity z-scale Average demand ROP

Relationship between z and Normal Variable x Risk of a stockout Service level Probability of no stockout Safety stock 0z Quantity z-scale Average demand ROP z = (x-Average x)/(Standard Deviation of x) x = Average x +z (Standard Deviation of x) μ = Average x σ = Standard Deviation of x RiskService z value level  x = μ +z σ

ROP and ss Risk of a stockout Service level Probability of no stockout Safety stock 0z Quantity z-scale Average demand ROP LTD = Lead Time Demand (Demand during the lead time) ROP = Average LTD +z (Standard Deviation of LTD) ss = z (Standard Deviation of LTD) ROP = Average LTD +ss RiskService z value level

c) If average demand during the lead time is 200 and standard deviation of demand during lead time is 25. Compute ROP at 90% service level. Compute ss ROP; total demand during lead time is variable ROP Risk of a stockout Service level Probability of no stockout Expected demand Safety stock x RiskService z value level

z = 1.28 z = (X- μ )/σ X= μ +z σ μ = 200 σ = 25 X= × 25 X= ROP = 232 ss = 32 ROP; total demand during lead time is variable

d) If average demand per day is 20 units and standard deviation of demand is 5 per day, and lead time is 16 days. Compute ROP at 90% service level. Compute ss. ROP; Variable d, Fixed LT

Previous Problem: If average demand during the lead time is 200 and standard deviation of demand during lead time is 25. Compute ROP at 90% service level. Compute ss. This Problem: If average demand per day is 20 units and standard deviation of demand is 5 per day, and lead time is 16 days. Compute ROP at 90% service level. Compute ss. If we can transform this problem into the previous problem, then we are done, because we already know how to solve the previous problem. ROP; Variable d, Fixed LT

d) If average demand per day is 20 units and standard deviation of demand is 5 per day, and lead time is 16 days. Compute ROP at 90% service level. Compute ss. What is the average demand during the lead time What is standard deviation of demand during lead time ROP; Variable d, Fixed LT

Demand During Lead Time If demand is variable and Lead time is fixed

ROP; Variable d, Fixed LT

The Problem originally was: If average demand per day is 20 units and standard deviation of demand is 5 per day, and lead time is 16 days. Compute ROP at 90% service level. Compute ss. We transformed it to: The average demand during the lead time is 320 and the standard deviation of demand during the lead time is 20. Compute ROP at 90% service level. Compute ss. Which is the same as the previous problem: If average demand during the lead time is 200 and standard deviation of demand during lead time is 25. Compute ROP at 90% service level. Compute ss. Now it is transformed into our previous problem where total demand during lead time is variable

z = 1.28 z = (X- μ )/σ X= μ +z σ μ = 320 σ = 20 X= × 20 X= X= ROP = 346 SS = 26 ROP; Variable d, Fixed LT

e) If demand per day is 20 units and lead time is 16 days and standard deviation of lead time is 4 days. Compute ROP at 90% service level. Compute ss. What is the average demand during the lead time What is standard deviation of demand during lead time ROP; Variable d, Fixed LT

Demand Fixed, Lead Time variable If lead time is variable and demand is fixed

Lead Time Variable, Demand fixed e) Demand of sand is fixed and is 20 units per day. The average lead time is 16 days. Standard deviation of lead time is 4 days. Service level is 90%. Service level ; 90%  z = 1.28