Copyright 2009 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter 9 Roberta Russell & Bernard W. Taylor, III
Copyright 2009 John Wiley & Sons, Inc.9-2 Lecture Outline Project Planning Project Scheduling Project Control CPM/PERT Probabilistic Activity Times Project Crashing and Time-Cost Trade-off
Copyright 2009 John Wiley & Sons, Inc.9-3 What is a Project? Project unique, one-time operational activity or effort Examples constructing houses, factories, shopping malls, athletic stadiums or arenas developing military weapons systems, aircrafts, new ships launching satellite systems constructing oil pipelines developing and implementing new computer systems planning concert, football games, or basketball tournaments introducing new products into market
Copyright 2009 John Wiley & Sons, Inc.9-4 Project Elements Objective Scope Contract requirements Schedules Resources Personnel Control Risk and problem analysis
Copyright 2009 John Wiley & Sons, Inc.9-5 Project Management Process Project planning Project scheduling Project control Project team made up of individuals from various areas and departments within a company made up of individuals from various areas and departments within a company Matrix organization a team structure with members from functional areas, depending on skills required a team structure with members from functional areas, depending on skills required Project Manager most important member of project team most important member of project team
Copyright 2009 John Wiley & Sons, Inc.9-6 Project Scope Scope statement a document that provides an understanding, justification, and expected result of a project a document that provides an understanding, justification, and expected result of a project Statement of work written description of objectives of a project written description of objectives of a project Work breakdown structure breaks down a project into components, subcomponents, activities, and tasks breaks down a project into components, subcomponents, activities, and tasks
Copyright 2009 John Wiley & Sons, Inc.9-7 Work Breakdown Structure for Computer Order Processing System Project
Copyright 2009 John Wiley & Sons, Inc.9-8 Organizational Breakdown Structure a chart that shows which organizational units are responsible for work items a chart that shows which organizational units are responsible for work items Responsibility Assignment Matrix shows who is responsible for work in a project shows who is responsible for work in a project
Copyright 2009 John Wiley & Sons, Inc.9-9 Project Scheduling Steps Define activities Define activities Sequence activities Sequence activities Estimate time Estimate time Develop schedule Develop schedule Techniques Gantt chart Gantt chart CPM CPM PERT PERT Microsoft Project Microsoft Project
Copyright 2009 John Wiley & Sons, Inc.9-10 Gantt Chart Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack amount of time an activity can be delayed without delaying the project
Copyright 2009 John Wiley & Sons, Inc.9-11 |||||||||| Activity Design house and obtain financing Lay foundation Order and receive materials Build house Select paint Select carpet Finish work MonthMonth Example of Gantt Chart
Copyright 2009 John Wiley & Sons, Inc.9-12 Project Control Time management Cost management Quality management Performance management Earned Value Analysis Earned Value Analysis a standard procedure for numerically measuring a project’s progress, forecasting its completion date and cost and measuring schedule and budget variation a standard procedure for numerically measuring a project’s progress, forecasting its completion date and cost and measuring schedule and budget variation Communication Enterprise project management
Copyright 2009 John Wiley & Sons, Inc.9-13 CPM/PERT Critical Path Method (CPM) DuPont & Remington-Rand (1956) DuPont & Remington-Rand (1956) Deterministic task times Deterministic task times Activity-on-node network construction Activity-on-node network construction Project Evaluation and Review Technique (PERT) US Navy, Booz, Allen & Hamilton US Navy, Booz, Allen & Hamilton Multiple task time estimates Multiple task time estimates Activity-on-arrow network construction Activity-on-arrow network construction
Copyright 2009 John Wiley & Sons, Inc.9-14 Project Network Activity-on-node (AON) nodes represent activities, and arrows show precedence relationships Activity-on-arrow (AOA) arrows represent activities and nodes are events for points in time Event completion or beginning of an activity in a project Branch Node
Copyright 2009 John Wiley & Sons, Inc.9-15 AOA Project Network for a House Lay foundation Design house and obtain financing Order and receive materials Dummy Finish work Select carpet Select paint Build house
Copyright 2009 John Wiley & Sons, Inc.9-16 Concurrent Activities 23 Lay foundation Order material (a)Incorrect precedence relationship (b)Correct precedence relationship 3 42 Dummy Layfoundation Order material 1 20
Copyright 2009 John Wiley & Sons, Inc.9-17 AON Network for House Building Project Start Design house and obtain financing Order and receive materials Select paint Select carpet Lay foundations Build house Finish work
Copyright 2009 John Wiley & Sons, Inc Start Critical Path Critical path Longest path through a network Longest path through a network Minimum project completion time Minimum project completion time A: = 9 months B: = 8 months C: = 8 months D: = 7 months
Copyright 2009 John Wiley & Sons, Inc.9-19 Activity Start Times Start Start at 3 months Start at 6 months Start at 5 months Finish at 9 months Finish
Copyright 2009 John Wiley & Sons, Inc.9-20 Mode Configuration Activity number Activity duration Earliest start Latest start Earliest finish Latest finish
Copyright 2009 John Wiley & Sons, Inc.9-21 Forward Pass Start at the beginning of CPM/PERT network to determine the earliest activity times Earliest Start Time (ES) earliest time an activity can start ES = maximum EF of immediate predecessors Earliest finish time (EF) earliest time an activity can finish earliest start time plus activity time EF= ES + t
Copyright 2009 John Wiley & Sons, Inc.9-22 Earliest Activity Start and Finish Times Start Design house and obtain financing Select pain Lay foundations Select carpet Build house Finish work Order and receive materials
Copyright 2009 John Wiley & Sons, Inc.9-23 Backward Pass Determines latest activity times by starting at the end of CPM/PERT network and working forward Latest Start Time (LS) Latest time an activity can start without delaying critical path time LS= LF - t Latest finish time (LF) latest time an activity can be completed without delaying critical path time LS = minimum LS of immediate predecessors
Copyright 2009 John Wiley & Sons, Inc.9-24 Latest Activity Start and Finish Times Start Design house and obtain financing Select pain Lay foundations Select carpet Build house Finish work Order and receive materials
Copyright 2009 John Wiley & Sons, Inc.9-25 * Critical Path *7* *4* *2* *1*1 Slack S EF LF ES LS Activity Activity Slack
Copyright 2006 John Wiley & Sons, Inc.9-26 Probabilistic Time Estimates Beta distribution a probability distribution traditionally used in CPM/PERT a = optimistic estimate m = most likely time estimate b = pessimistic time estimate where Mean (expected time): t = a + 4 m + b 6 Variance: 2 = b - a 6 2
Copyright 2006 John Wiley & Sons, Inc.9-27 Examples of Beta Distributions P(time) Time amtbamtb m = t Time Time ba
Copyright 2006 John Wiley & Sons, Inc.9-28 Project Network with Probabilistic Time Estimates: Example StartFinish 2 3,6,9 3 1,3,5 1 6,8,10 5 2,3,4 6 3,4,5 4 2,4,12 7 2,2,2 8 3,7,11 9 2,4,6 10 1,4,7 11 1,10,13 Equipment installation System development Position recruiting Equipment testing and modification Manual testing Job Training Orientation System training System testing Final debugging System changeover
Copyright 2006 John Wiley & Sons, Inc.9-29 Activity Time Estimates TIME ESTIMATES (WKS)MEAN TIMEVARIANCE ACTIVITY ambt б 2
Copyright 2006 John Wiley & Sons, Inc.9-30 Activity Early, Late Times, and Slack ACTIVITY t б ESEFLSLFS
Copyright 2006 John Wiley & Sons, Inc.9-31 StartFinish Critical Path Earliest, Latest, and Slack
Copyright 2006 John Wiley & Sons, Inc.9-32 2 = б б б б 11 2 = = 6.89 weeks Total project variance
Copyright 2006 John Wiley & Sons, Inc.9-33 Probabilistic Network Analysis Determine probability that project is completed within specified time where = t p = project mean time =project standard deviation x =proposed project time Z =number of standard deviations x is from mean Z =Z =Z =Z = x -
Copyright 2006 John Wiley & Sons, Inc.9-34 Normal Distribution Of Project Time = t p Timex ZZ Probability
Copyright 2006 John Wiley & Sons, Inc.9-35 Southern Textile Example What is the probability that the project is completed within 30 weeks? 2 = 6.89 weeks = 6.89 = 2.62 weeks Z = = = 1.91 x - From Table A.1, (appendix A) a Z score of 1.91 corresponds to a probability of Thus P(30) = = = 25 Time (weeks) x = 30 P( x 30 weeks)
Copyright 2006 John Wiley & Sons, Inc.9-36 Southern Textile Example = 25 Time (weeks) x = 22 P( x 22 weeks) What is the probability that the project is completed within 22 weeks? 2 = 6.89 weeks = 6.89 = 2.62 weeks Z = = = x - From Table A.1 (appendix A) a Z score of corresponds to a probability of Thus P(22) = =
Copyright 2006 John Wiley & Sons, Inc.9-37 Project Crashing Crashing reducing project time by expending additional resources Crash time an amount of time an activity is reduced Crash cost cost of reducing activity time Goal reduce project duration at minimum cost
Copyright 2006 John Wiley & Sons, Inc Project Crashing: Example
Copyright 2006 John Wiley & Sons, Inc.9-39 Project Crashing: Example (cont.) $7,000 – $6,000 – $5,000 – $4,000 – $3,000 – $2,000 – $1,000 – – ||||||| Weeks Normal activity Normal time Normal cost Crash time Crashed activity Crash cost Slope = crash cost per week
Copyright 2006 John Wiley & Sons, Inc.9-40 Normal Activity and Crash Data TOTAL NORMALCRASHALLOWABLECRASH TIMETIMENORMALCRASHCRASH TIMECOST PER ACTIVITY(WEEKS)(WEEKS)COSTCOST(WEEKS)WEEK 1127$3,000$5,0005$ ,0003, ,0007,00013, ,00071,00037, , , ,00022,00017,000 $75,000$110,700
Copyright 2006 John Wiley & Sons, Inc $400 $500 $3000 $7000 $200 $ Project Duration: 36 weeks FROM … $400 $500 $3000 $7000 $200 $ Project Duration: 31 weeks Additional Cost: $2000 TO…
Copyright 2009 John Wiley & Sons, Inc.9-42 Crashing costs increase as project duration decreases Indirect costs increase as project duration increases Reduce project length as long as crashing costs are less than indirect costs Time-Cost Relationship
Copyright 2009 John Wiley & Sons, Inc.9-43 Time-Cost Tradeoff Cost ($) Project duration CrashingTime Minimum cost = optimal project time Total project cost Indirect cost Direct cost
Copyright 2009 John Wiley & Sons, Inc.9-44 Copyright 2009 John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that permitted in section 117 of the 1976 United States Copyright Act without express permission of the copyright owner is unlawful. Request for further information should be addressed to the Permission Department, John Wiley & Sons, Inc. The purchaser may make back-up copies for his/her own use only and not for distribution or resale. The Publisher assumes no responsibility for errors, omissions, or damages caused by the use of these programs or from the use of the information herein.