Presentation is loading. Please wait.

Presentation is loading. Please wait.

Principle, Ariel Training Consultants

Similar presentations


Presentation on theme: "Principle, Ariel Training Consultants"— Presentation transcript:

1 Principle, Ariel Training Consultants
Project Management by Miles M. Hamby, PhD Principle, Ariel Training Consultants

2 Topics The Elements of Project Management
Elements of a Project Proposal Document SOW, OBS, RAM, CPM/PERT Networks Probabilistic Activity Times Using Excel to create Gantt charts Cost-Benefit and Earned Value Analysis

3 Unique (one-time effort) Fixed duration Specific goal
Nature of a Project Unique (one-time effort) Fixed duration Specific goal

4 The Project Team Includes engineers, line workers, HR personnel, budget experts, technical experts, outside consultants Headed by the Project Manager Must coordinate various skills of team members into single, focused effort Great pressure due to uncertainty inherent in project schedule, budget, and quality.

5 If anything can go wrong – it will!
Nature of Project Management Why manage a project? Murphy’s Law If anything can go wrong – it will! Complete on-time In budget Meet expectations (quality)

6 Nature of Project Management
Controlling an activity for a relatively short period of time until project is completed, then operations begin. Project manager not involved in operations. 3 components of PM: Planning Scheduling Controlling individual activities.

7 The Project Management Process
PLANNING SCHEDULING CONTROLLING GANTT ON TIME SOW Scope OBS IN BUDGET asdf 1 3 2 5 4 6 START FINISH PERT/CPM CREDIT DEBIT $24, $21,300 $34, $33,450 asdf asdf asdf MEETS EXPECTATIONS RAM ACT DESIGN RESOUC CPMSTR QA 1 O.P S 2 P O 3 RESOURCES $

8 Elements of Project Management
Project Control Process of ensuring progress toward successful completion ~ on time, in budget, meet expectations. Monitoring project to minimize deviations from project plan and schedule. Corrective actions necessary if deviations occur. Key elements of project control Time management Cost management Performance management Earned value analysis.

9 Project Planning Document
- a document for the customer, individuals, team members, groups, departments, subcontractors and suppliers, describing what is required for successful completion - on time, in budget, meet expectations.

10 The Project Planning Document
Cover page TOC SOW and Scope OBS RAM Activity Schedule PERT/CPM – AON diagram & Gantt Chart Budgeting Resources (Human and Materials) Technology Cost-Benefit and Earned Value Analysis (EVA) Execution and Control Plan (Quality Assurance) Protection of the Environment Risk Assessment and Management

11 SOW and Scope Statement of Work (SOW) – statement of work to be performed, justification describing the factors giving rise to need for project, expected duration (on time), total cost (budget), and performance standards (meeting expectations). Scope – identification of boundaries and limitations on specific aspects of the project, including size, resources, work to be performed and performance standards

12 Organizational Breakdown Structure (OBS)
Wilson Bridge Renovation Project Acme Construction Company Organization Breakdown Structure (OBS) Project Manager Bob Smith Design Manager Jane Doe Construction Mgr Bill Jones Electrical Mgr Rene Flemming Resources Mgr John Henry (Tasking) (Tasking) (Tasking) (Tasking)

13 Responsibility Assignment Matrix
OBS leads to the responsibility assignment matrix (RAM) RAM is a table or a chart showing which organizational units are responsible for work items. Project Manager assigns work elements to organizational units, departments, groups, individuals or subcontractors. RAM shows who is responsible for oversight (O), performance (P), and support (S) of each task

14 Responsibility Assignment Matrix (RAM)
ACME Construction Company Wilson Bridge Renovation Responsibility Assignment Matrix (RAM) Key: O = Oversight, P = Performance, S = Support Activity OBS Unit Design Construction Electrical Resources 1 – Design O, P S 2 - Acquire materials 3 - Prepare foundation 4 - Set piles 5 - Construct piers P 6 - Construct roadway

15 Project Scheduling Project Schedule evolves from planning documents, with focus on timely completion. Scheduling is the source of most conflicts and problems. Schedule development steps: 1. Define activities 2. Sequence activities, 3. Estimate activity times 4. Construct schedule. Gantt chart and CPM/PERT techniques used. Computer software packages available, e.g. Microsoft Project.

16 Work Breakdown Structure (WBS)
Basis for project development, management , schedule, resources and modifications. WBS breaks down project into major modules. Modules are further broken down into activities and, finally, into individual tasks. Identifies activities, tasks, resource requirements and relationships between modules and activities.

17 Activity Schedule ACME Construction Company Wilson Bridge Renovation
ACTVITY PREDESSOR DURATION (months) 1 – Design -- 14 2 - Acquire materials 1 3 - Prepare foundation 4 - Set piles 3 5 - Construct piers 4 8 6 - Construct roadway 5

18 CPM – Critical Path Method
CPM/PERT CPM – Critical Path Method PERT – Project Evaluation and Review Technique AON – Activity on Node

19 CPM/PERT Activity-on-Node (AON) Network
A branch reflects an activity of a project. A node represents the beginning and end of activities, referred to as events. Branches in the network indicate precedence relationships. When an activity is completed at a node, it has been realized. 1 14 2 3 4 5 8 6 START FINISH

20 AON Concurrent Activities
Network aids in planning and scheduling. Time duration of activities shown on branches. Activities can occur at the same time (concurrently). A dummy activity shows a precedence relationship but reflects no passage of time. Two or more activities cannot share the same start and end nodes. 1 12 2 3 4 5 8 6 START FINISH

21 The Critical Path (CPM)
The critical path is the longest path through the network; the minimum time the network can be completed Path A: 1  2  4  5  6 = 28 month Path B: 1  3  4  5  6 = 29 months  Critical Path

22 Gantt Chart Bar chart developed by Henry Gantt (1914).
A visual display of project schedule showing activity start and finish times and where extra time is available. Based on Activity Schedule – order, duration, predecessors Drawback: precedence relationships are not always discernible.

23 Activity Early Start Schedule (for Gantt Chart)
ACME Construction Company Wilson Bridge Renovation Activity Schedule ACTVITY EARLY START DURATION (months) 1 – Design 6 2 - Acquire materials 7 3 - Prepare foundation 12 1 4 - Set piles 13 5 - Construct piers 19 8 6 - Construct roadway 27

24 Gantt Chart

25 House Building Project Example
No. Activity Predecessor Duration (Months) Design house and obtain financing 2. Lay foundation 3. Order Materials 4. Build house , 5. Select paint , 6. Select carpet 7. Finish work ,

26 The Critical Path (CPM)
The critical path is the longest path through the network; the minimum time the network can be completed. Path A: 1  2  4  7, = 9 month CPM Path B: 1  2  5  6  7, = 8 months Path C: 1  3  4  7, = 8 months Path D: 1  3  5  6  7, = 7 months

27 Activity Early Start Times

28 AON Earliest/Latest Times Configuration
Earliest Start Earliest Finish Activity 1 3 12 Duration Latest Start Latest Finish

29 Activity Scheduling: Earliest/Latest Times
ES – Earliest Start time an activity can start: ES = Maximum (EF) EF - Earliest Finish, start time plus the activity time: EF = ES + t 1 12 3 1 12 3 1 12 3 1 12 3 1 12 3

30 Computer Network Example
Computer Network Project Activity Optimistic (a) Most Probable (m) Pessimistic (b) Weighted Mean Time (t) Variance (v) 1 – Equipment Installation 6 8 10 2 – System Development 3 9 3 – Position Recruiting 1 5 4 – Equip testing & Mod 2 4 12 5 – Manual Testing 6 – Job Training 7 – Orientation 8 – System training 11 9 – System Testing 10 – Final Debugging 7 11 – System Changeover 13

31 AON Probabilistic Times Configuration
1 2, 3, 5 Activity Optimistic (a) Most likely (m) Pessimistic (b)

32 AON Probabilistic Times
10 1,4,7 8 3,7,11 4 2,4,12 6 3,4,5 7 2,2,2 3 1,3,5 1 6,8,10 9 2,4,6 11 1,10,13 5 2,3,4 2 3,6,9 FINISH START Computer Network Project

33 Probabilistic Activity Times
Activity time estimates usually cannot be made with certainty. PERT used for probabilistic activity duration times. In PERT, three time estimates are used: most likely time (m), the optimistic time (a) , and the pessimistic time (b). These provide an estimate of the mean and variance of a beta distribution: Weighted Mean (expected time): Variance:

34 Computer Network Example
Computer Network Project Activity Optimistic (a) Most Probable (m) Pessimistic (b) Weighted Mean Time (t) Variance (v) 1 – Equipment Installation 6 8 10 .44 (4/9) 2 – System Development 3 9 1 3 – Position Recruiting 5 4 – Equip testing & Mod 2 4 12 2.78 (25/9) 5 – Manual Testing .11 (1/9) 6 – Job Training 7 – Orientation 1.78 (0) 8 – System training 11 7 2.11 (16/9) 9 – System Testing 10 – Final Debugging 1 (9/9) 11 – System Changeover 13 4 (36/9) 34 34

35 Probabilistic Activity Times
Critical Path Critical Path is the path with the longest mean time and is also the Expected Project Time (tp) Path Mean Times 1  4  10 = 17 weeks 2  5  8 = 16 weeks 2  5  9  11 = 22 weeks CPM 3  6  8 = 14 weeks 3  6  9  11 = 20 weeks 3  7  11 = 14 weeks

36 Expected Project Time and Variance
The Project Variance (vp) is the sum of the variances of the critical path activities. Critical Path:  5  9  11 Project time: = 22 weeks Variance: = 7.22 weeks Standard Deviation: Sqrt of Variance = 2.69

37 Probability Analysis of a Project Network
Expected project time (tp) is assumed to be normally distributed (based on central limit theorem). As such, the expected project time (tp) and variance (vp) are interpreted as the mean () and variance (2) of a normal distribution Project time: = 22 weeks Variance: = 7.22 weeks Std Dev: Sqrt 7.22 = 2.69 -3 = weeks Time (Duration) 3 = weeks  = 22 weeks

38 Probability Analysis of a Project Network
Example 1 From Computer Network example: Critical Path:  5  9  11 Project time: = 22 weeks Variance: = 7.22 weeks What is the probability that the new order processing system will be ready in 20 weeks? µ = 22 weeks 2 = 7.22, therefore,  = weeks Z = (x-)/  = ( )/2.69 = -.74

39 Table of Areas (p-values)
+/- Z 0.00 0.01 0.02 0.03 0.04 0.05 0.06 0.07 0.08 0.09 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2.0 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 3.0 0.0000 0.0398 0.0793 0.1179 0.1554 0.1915 0.2257 0.2580 0.2881 0.3159 0.3413 0.3643 0.3849 0.4032 0.4192 0.4332 0.4452 0.4554 0.4641 0.4713 0.4772 0.4821 0.4861 0.4893 0.4918 0.4938 0.4953 0.4965 0.4974 0.4981 0.4987 0.0040 0.0438 0.0832 0.1217 0.1591 0.1950 0.2291 0.2611 0.2910 0.3186 0.3483 0.3665 0.3869 0.4049 0.4207 0.4345 0.4463 0.4564 0.4649 0.4719 0.4778 0.4826 0.4864 0.4896 0.4920 0.4940 0.4955 0.4966 0.4975 0.4982 0.0080 0.0478 0.0871 0.1255 0.1628 0.1985 0.2324 0.2642 0.2939 0.3212 0.3461 0.3686 0.3888 0.4066 0.4222 0.4357 0.4474 0.4573 0.4656 0.4726 0.4783 0.4830 0.4868 0.4898 0.4922 0.4941 0.4956 0.4967 0.4976 0.0120 0.0517 0.0910 0.1293 0.1664 0.2090 0.2357 0.2673 0.2967 0.3238 0.3485 0.3708 0.3907 0.4082 0.4236 0.4370 0.4484 0.4582 0.4664 0.4732 0.4788 0.4834 0.4871 0.4901 0.4925 0.4943 0.4957 0.4968 0.4977 0.4983 0.4988 0.0160 0.0557 0.0948 0.1331 0.1700 0.2054 0.2389 0.2704 0.2995 0.3264 0.3508 0.3729 0.3925 0.4099 0.4251 0.4382 0.4495 0.4591 0.4671 0.4738 0.4793 0.4838 0.4875 0.4904 0.4927 04945 0.4959 0.4969 0.4984 0.0199 0.0596 0.0987 0.1368 0.1736 0.2088 0.2422 0.2734 0.3023 0.3289 0.3531 0.3749 0.3944 0.4115 0.4265 0.4394 0.4505 0.4599 0.4678 0.4744 0.4798 0.4842 0.4878 0.4906 0.4929 0.4946 0.4960 0.4970 0.4978 0.4989 0.0239 0.0636 0.1026 0.1406 0.1772 0.2123 0.2454 0.2764 0.3051 0.3315 0.3554 0.3770 0.3962 0.4131 0.4279 0.4406 0.4515 0.4608 0.4686 0.4750 0.4803 0.4846 0.4881 0.4909 0.4931 0.4948 0.4961 0.4971 0.4979 0.4985 0.0279 0.0675 0.1064 0.1413 0.1808 0.2157 0.2486 0.2794 0.3078 0.3340 0.3577 0.3790 0.3980 0.4147 0.4292 0.4418 0.4525 0.4616 0.4693 0.4756 0.4808 0.4850 0.4884 0.4911 0.4932 0.4949 0.4962 0.4972 0.0319 0.0714 0.1103 0.1480 0.1844 0.2190 0.2517 0.2823 0.3106 0.3365 0.3599 0.3810 0.3997 0.4162 0.4306 0.4429 0.4535 0.4625 0.4699 0.4761 0.4812 0.4854 0.4887 0.4913 0.4934 0.4951 0.4963 0.4973 0.4980 0.4986 0.4990 0.0359 0.0753 0.1141 0.1517 0.1879 0.2224 0.2549 0.2850 0.3133 0.3389 0.3621 0.3830 0.4015 0.4177 0.4319 0.4441 0.4545 0.4633 0.4706 0.4767 0.4817 0.4857 0.4890 0.4916 0.4936 0.4952 0.4964

40 Probability Analysis of a Project Network
Z value of -.74 corresponds to probability of (table of areas under the curve). Therefore, the probability of completing the project in 20 weeks is = x - µ Z = 2.69 = P = .2704 = .2296 Z= -.74 (20 weeks) Time (Duration)  = 22 weeks

41 Cost – Benefit Analysis
Given an amount of capital to invest, what is the cost and what is the benefit? Project Owner’s perspective ~ is the project worth doing, or do we invest in something else, like another project or the market? Project Manager’s perspective ~ what do I do with money waiting to be spent on the project – keep it in the bank, or invest it?

42 Cost - Benefit Project – replace old computerized production control system for an auto assembly plant The project will cost $3M over 3 years and save $7M over 10 years However, if we invest $3M over ten years, we make $8M, but lose $5M in extra costs from the outdated system ITEM BENEFIT ($M) COST GAIN or (LOSS) (Benefit-Cost) New System 7 (in savings) 3 (install new system) 4 Old System 8 (from investment) 5 (using old system) 3

43 Earned Value Analysis (EVA)
Measures progress of a project in terms of: Planned Value (PV) or Budgeted Cost Work Scheduled (BCWS) – what is supposed to be done Earned Value (EV) or Budgeted Cost, Work Performed (BCWP) – what has actually been done Actual Cost (AC) or Work Performed (ACWP) – actual labor and materials expended

44 Earned Value - Example Project: Build a deck
PV: 40 labor-hours x $20/hr = $800 + $600 materials $1,400 PV (BCWS) Changes after work begun: Labor rate now $22/hr, materials price increase to $700, project only 95% completed after 40 hours EV: 95% completed x $1,400 = $1,330 EV(BCWP) AC: hrs x $22/hr = $880 labor materials $1,580 AC (ACWP)

45 Should be proportionate to project time
Earned Value Should be proportionate to project time Project Time Monitoring Schedule 1 week 1 month 6 months > 6 months Daily Twice weekly Weekly Monthly

46 End of Chapter


Download ppt "Principle, Ariel Training Consultants"

Similar presentations


Ads by Google