Status of the LHC Mike Lamont for the LHC team. The LHC Very big Very cold Very high energy 2.

Slides:



Advertisements
Similar presentations
LHC Beam Operations Past, Present and Future Maria Kuhn on behalf of the LHC team Moriond QCD 2013.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Collimation MDs LHC Study Working Group Daniel Wollmann for the Collimation-Team, BLM-Team, Impedance-Team, … LHC Study Working Group,
(n)QPS LHC status and plans LHC Status and Plans Mike Lamont for the LHC team 1.
(n)QPS LHC status LHC: past, present and future Mike Lamont for the LHC team
LHCC 3rd June 2015 Mike Lamont for the LHC team
LHC status The Large Hadron Collider Mike Lamont for the LHC team.
(n)QPS LHC status and plans LHC status and plans for 2011 Mike Lamont for the LHC team 1.
Sat/Sun 26/27 th March Sat 18h20: Stable beams. Fill #1653. Sun 10h02: Stable beams continued. vdM scans. Length calibrations. 16h59: Beam dump. Delivered.
LHC beam operation past, present, future Mike Lamont for the LHC team.
LHC machine status Mike Lamont for the LHC team. 75 ns50 ns 2011 – recap Increase number of bunches Reduce beam size from injectors Squeeze further Increase.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
LHC Status - SUSY Bonn 1 Drawing by Sergio Cittolin Status of the LHC 6 months of beam operation in 2010 J. Wenninger CERN.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
RHIC Status: Startup Run 12 V. Schoefer RHIC Spin Collaboration Meeting 1/13/12.
Luminosity expectations for the first years of CLIC operation CTC MJ.
The LHC from commissioning to operation Mike Lamont for the LHC team.
LHC progress Report LHCC Wednesday 23 rd March 2011.
The Large Hadron Collider Contents: 1. The machine II. The beam III. The interaction regions IV. First LHC beam [R. Alemany] [CERN AB/OP] [Engineer In.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
Evian 2014 historical perspective run 1: 2010: L peak >10 32 cm -2 s -1  2x10 32 cm -2 s : produce >1 fb -1  delivered.
Machine development - results and plans – critical results, what’s to be done? R. Assmann 15/07/2011 R. Assmann for the LHC MD coordination team (R. Assmann,
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
1 Commissioning and Operation of the machine protection system L. Ponce Acknowledgements: M. Zerlauth, J. Wenninger, D. Wollmann, V. Chetvertkova, G. Valentino,
Β*-dependence on collimation R. Bruce, R.W. Assmann C. Alabau Pons, F. Burkart, M. Cauchi, D. Deboy, M. Giovannozzi, W. Herr, L. Lari, G. Muller, S. Redaelli,
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
LHC Machine Operational Status and Plans LHCC, 22nd September 2010 Steve Myers (On behalf of the LHC team and international collaborators)
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Thursday 27 th October 00:57 fill 2257 dumped during squeeze (RQTF.A67B1) 03:52 stable beams fill #2258 4:33 Dumped, problem of LBDS dilution kicker power.
Plan for 500 GeV Development Vadim, Mei. Goals 1.Explore polarization transmission to the 500 Gev CM energy. 2. Inspect the luminosity aspects (with 2.
Turnaround time in modern hadron colliders & store-length optimization
LHC Status Report 1 Jan Uythoven For the LHC Team LPCC
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Mike Lamont An attempt at synthesis Acknowledgements all round
Mike Lamont for the LHC team
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
The CERN Physics Programme
BEAM LOSS MONITORING SYSTEM
LHC Commissioning with Beam
MPI-ATL Calor Meeting 7-Sep-2009 H. Oberlack MPI für Physik, Munich
LHC Machine Status report
The LHC - Status Is COLD Is almost fully commissioned
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008
LHC status Benoit Salvant (Beams department, Accelerator and Beam Physics group) for the LHC complex teams With many thanks for their inputs to J. Boyd,
BEAM LOSS MONITORING SYSTEM
Initial Experience with the Machine Protection System for LHC
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
LHC Morning Meeting - G. Arduini
Summary of Week 16 G. Arduini, J. Wenninger
J. Uythoven, W. Venturini Delsolaro, CERN, Geneva
6 months of beam operation in 2010
LHC (SSC) Byung Yunn CASA.
Optic design and performance evaluation for SPPC collimation systems
LHC Beam Operations Past, Present and Future
Collimation margins and *
Summary Thursday h21: Stable beams fill #1303.
Machine Tolerances in Cleaning Insertions
Machine plans - CMS startup workshop
Collimators: Operations - Baseline Assumptions
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Monday :15 fill 3523 dumped by BPMs IP6
Summary Tuesday h23: Machine closed. Precycle started.
Fri :52 Stable beams fill #2536
Another Immortal Fill….
LS 1 start date 12th June Schedule Extension 2012 run Extension of 2012 run approved by the DG on 3rd July 2012.
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Status of the LHC Mike Lamont for the LHC team

The LHC Very big Very cold Very high energy 2

Energy  ~3 GJ of energy stored in the magnets  100 MJ stored in each beam ~21 kg of TNT. Underpins our thoughts 3.5 TeV with 1380 bunches – September 2011 During an SPS extraction test in 2004… The beam was a 450 GeV full LHC injection batch of p+ in 288 bunches [2.5 MJ] LHC status 3

LHC Timeline September 10, 2008 First beams around September 19, 2008 Disaster Accidental release of 600 MJ stored in one sector of LHC dipole magnets November 29, 2009 Beam back August 2008 First injection test August, e33, 2.6 fb bunches October e bunches November 2010 Ions March 30, 2010 First collisions at 3.5 TeV 1380 June bunches LHC status 4

FebruaryMarchAprilNovemberOctoberMayJuneJulyAugustSeptember March 30 First collisions 3.5 TeV A closer look at 2010 April Commission squeeze Feb 27 Beam back June Commission nominal bunch intensity QUALIFICATION September Crossing angles on LHC status 5 October Luminosity production

2010 – integrated luminosity EXPLOITATION COMMISSIONING and frantic debugging CONSOLIDATION LHC status 6

Nominal cycle Beam dump Ramp down/precycle Injection Ramp Squeeze Collide Stable beams Ramp down35 mins Injection~30 mins Ramp17 mins Squeeze8 mins Collide1 mins Stable beams0 – 30 hours Fastest turn around down from 3h40m in 2010 to 2h7m in 2011 after optimization LHC status 7

Aperture Aperture systematically measured (locally and globally) Better than anticipated w.r.t. tolerances on orbit & alignment Aperture compatible with a well-aligned machine, a well centred orbit and close to design mechanical aperture LHC status 8

Optics Optics stunningly stableand well corrected Two measurements of beating at 3.5 m 3 months apart Local and global correction at 1.5 m LHC status 9

Magnet model Model based feed-forward reduces chromaticity swing from 80 to less than 10 units Knowledge of the magnetic machine is remarkable All magnet ‘transfer functions’, all harmonics including decay and snapback of persistent currents Tunes, momentum, optics remarkably close to the model LHC status 10

Reproducibility Tune corrections made by feedback during squeeze 7 e-3 LHC magnetically reproducible with rigorous pre-cycling - set-up remains valid from month to month LHC status 11

Machine protection – the challenge Beam 100 MJ Beam 100 MJ SC Coil: quench limit mJ/cm 3 SC Coil: quench limit mJ/cm 3 56 mm Situation at 3.5 TeV (in August 2011) Not a single beam-induced quench at 3.5 TeV … YET 11 magnet quench at 450 GeV – injection kicker flash-over LHC status 12

Beam Interlock System Beam Dumping System Injection Interlock Powering Interlocks superconducting magnets Powering Interlocks normal conducting magnets Magnet protection system (20000 channels) Power Converters ~1600 AUG UPS Power Converters Magnets Fast Magnet Current change Monitor Cryogenics some channels RF System (f_RF + P) Vacuum System Beam Loss Monitors BCM Collimation System Jaw Position Temperature Screens and Mirrors beam observation LHC Experiments BPMs Beam loss monitors BLM Special BLMs Monitors aperture limits (some 100) Monitors in arcs (several 1000) Timing System (Post Mortem Trigger) Operator Buttons CCC Safe LHC Parameter Software Interlock System Safe Beam Parameter Distribution Safe Beam Flag Access System Beam Interlock System LHC status 13

Beam Dump System (LBDS) Expected about two asynchronous dumps per year – one to date with beam Absolutely critical. Rigorous and extensive program of commissioning and tests with beam. IR6 H Beam2, extracted LHC status 14

Collimation beam 1.2 m Two warm cleaning insertions IR3: Momentum cleaning 1 primary (H) 4 secondary (H,S) 4 shower abs. (H,V) IR7: Betatron cleaning 3 primary (H,V,S) 11 secondary (H,V,S) 5 shower abs. (H,V) Local IP cleaning: 8 tertiary coll. Total = 108 collimators About 500 degrees of freedom. LHC status 15

Collimation Triplet aperture must be protected by tertiary collimators (TCTs) TCTs must be shadowed by dump protection (not robust) Dump protection must be outside primary and secondary collimators Hierarchy must be satisfied even if orbit and optics drift after setup – margins needed between collimators LHC status 16

Collimation cleaning at 3.5 TeV Generate higher loss rates: beam across the 3rd order resonance. Betatron Off-momentum Dump TCTs Beam 1 Legend: Collimators Cold losses Warm losses Outstanding performance: No beam-induced quenches in 2010/ LHC status 17

Exit 2010: beam parameters 2010Nominal Energy [TeV]3.57 beta* [m]3.5, 3.5, 3.5, 3.5 m0.55, 10, 0.55, 10 Emittance [microns] 2.0 – 3.5 start of fill 3.75 Bunch intensity1.2e111.15e11 Number of bunches collisions/IP 2808 Stored energy [MJ]28360 Peak luminosity [cm -2 s -1 ] 2e321e LHC status 18

Collisions within 54 hours of first injection Lead ion run Experience and Lorentz’s law. LHC status 19

fb pb -1 /day LHC status 20

Emittance As we move around the machine the shape of the phase space ellipse will change as  (s) changes with the varying quadrupole (de-)focusing However the area of the ellipse (  ) does not change Emittance shrinks naturally as we go up in energy (p S increases, p T doesn’t) Define energy independent normalized emittance: Units are mm.mrad but normally use microns (and drop ‘normalized’) Useful – constant across complex (give or take some blow- up) x’x’ x  x LHC status 21

Aim: maximize peak luminosity N Number of particles per bunch KbKb Number of bunches f Revolution frequency Beam size at interaction point F Reduction factor due to crossing angle Emittance Normalized emittance Beta function at IP LHC status 22

Beam from injectors Excellent performance Higher than nominal bunch intensity Smaller than nominal emittance Bunch spacing From Booster Np/bunch Emittance H&V [mm.mrad] 150 Single batch 1.1 x Single batch 1.2 x Single batch 1.45 x Double batch 1.6 x Double batch 1.2 x At present: ~1.3 x ppb, 2.0 microns into collision LHC status 23

MD, technical stop Intermediate energy run, technical stop, scrubbing 75 ns50 ns Smaller emittance from injectors MD, technical stop, SQUEEZE 2011 LHC status 24

2011: (c/o Atlas & LHCb) Peak stable luminosity3.29 x cm -2 s -1 Max. luminosity in one fill114 pb -1 Max. luminosity delivered in 7 days pb -1 Longest time in stable beams26.0 hours Longest time in stable beams for 7 days107.1 hours (63.7%) Fastest turnaround2 hours 7 minutes 33% of design luminosity: - half design energy - nominal bunch intensity+ - ~half nominal emittance - beta* = 1.0 m (design 0.55 m) - half nominal number of bunches LHC status 25

Fill 2006: Luminosity lifetime H growth rate ~64 hours V growth rate ~84 hours Lifetime beam 2 A “typical” fill that lasted 26 hours and delivered 100 pb Luminosity lifetime 30 hours Lifetime beam hours LHC status 26

2011 parameters – now Energy [TeV]3.5 Beta* [m]1.0, 10, 1.0, 3.0 m Normalized emittance [microns]~2.0+ start of fill Bunch intensity 1.3e11 Number of bunches collisions/IP1&5 Bunch spacing [ns]50 Stored energy [MJ]90 to 100 Peak luminosity [cm -2 s -1 ]3.3e33 Beam-beam tune shift (start fill)~ LHC status 27

AVAILABILITY - EFFICIENCY Premature end to fills LHC status 28

UFOs in the LHC 35 fast loss events led to a beam dump. Since July 2010, 35 fast loss events led to a beam dump. 18 in 2010, 17 in around MKIs. 6 dumps by experiments. 1 at 450 GeV. Typical characteristics: Loss duration: about 10 turns Often unconventional loss locations (e.g. in the arc) U FO The events are believed to be due to (Unidentified) Falling Objects (UFOs). Spatial and temporal loss profile of UFO on

Single Event Effects Major campaign ongoing: shield and relocate LHC status 30

Dumps > 450 GeV July-August LHC status 31 Room for improvement

Availability Beam in ~49% of the time LHC status 32

Rest of this year LHC status 33

Rest of this year fb -1 plus……another ~40 days and reasonable efficiency: might just manage another 2 fb -1 LHC status e33 cm -2 s -1

Days Commissioning23 MD22 Technical stops20 Recovery & ramp-up16 Initial ramp-up16 Proton running~130 Special runs~8 Ion setup4 Ion run Possible energy increase? 50 ns versus 25 ns? LHC status 35 DRAFT!

Pile-up Luminosity per crossing Inelastic cross section (~72 mb at 3.5 TeV) average number of visible interactions per bunch crossing LHC status 36

Pileup Bunch spacing No. of bunches Energy [TeV] Beta* [m] Normalized emittance [micron] Protons per bunch [e11] Peak lumi [cm-2s-1] Peak mean mu 50 ns ns ns ns ns ns days at reasonable efficiency – might hope to push towards 10 fb -1 LHC status 37

NB: not yet approved Further ahead LHC status 38

Conclusion Successful commissioning and good transition from commissioning to operations – Cycle is solid – Performance is quite staggering (and will now flatten out) – Machine protection working well – Availability with high intensity acceptable with issues being addressed The LHC is a beautiful machine and a real testament to those who conceived, built and installed it LHC status 39