Presentation is loading. Please wait.

Presentation is loading. Please wait.

6 months of beam operation in 2010

Similar presentations


Presentation on theme: "6 months of beam operation in 2010"— Presentation transcript:

1 6 months of beam operation in 2010
Status of the LHC 6 months of beam operation in 2010 LHC Status - SUSY Bonn J. Wenninger CERN Drawing by Sergio Cittolin

2 Outline Introduction LHC energy 2010/11
LHC performance targets and achievements LHC beam operation Outlook for 2010/11 and conclusions LHC Status - SUSY Bonn

3 The Large Hadron Collider LHC
Installed in 26.7 km LEP tunnel Depth of m Lake of Geneva LHC ring LHC Status - SUSY Bonn CMS, Totem LHCb Control Room SPS ring ATLAS, LHCf ALICE

4 LHC layout and parameters
8 arcs (sectors), ~3 km each 8 long straight sections (700 m each) beams cross in 4 points 2-in-1 magnet design with separate vacuum chambers → p-p collisions RF - β* = 0.55 m (beam size =17 μm) - Crossing angle = 285 μrad - L = 1034 cm-2 s-1 Nominal LHC parameters Beam energy (TeV) 7.0 No. of particles per bunch 1.15x1011 No. of bunches per beam 2808 Stored beam energy (MJ) 362 Transverse emittance (μm) 3.75 Bunch length (cm) 7.55

5 LHC accelerator complex
≥ 7 seconds from source to LHC Beam 1 TI2 Beam 2 TI8 LHC proton path The LHC needs most of the CERN accelerators...

6 LHC challenges The LHC surpasses existing accelerators/colliders in 2 aspects : The energy of the beam of 7 TeV that is achieved within the size constraints of the existing 26.7 km LEP tunnel. LHC dipole field 8.3 T HERA/Tevatron ~ 4 T The luminosity of the collider that will reach unprecedented values for a hadron machine: LHC pp ~ 1034 cm-2 s-1 Tevatron pp 3x1032 cm-2 s-1 SppS pp 6x1030 cm-2 s-1 Very high field magnets and very high beam intensities: Operating the LHC is a great challenge. There is a significant risk to the equipment and experiments. A factor 2 in field A factor 4 in size LHC Status - SUSY Bonn A factor 30 in luminosity

7 LHC dipole magnet 1232 dipole magnets.
B field 8.3 T ( K (super-fluid Helium) 2 magnets-in-one design : two beam tubes with an opening of 56 mm. Operating challenges: Dynamic field changes at injection. Very low quench levels (~ mJ/cm3) LHC Status - SUSY Bonn

8 Stored energy Increase with respect to existing accelerators :
A factor 2 in magnetic field A factor 7 in beam energy A factor 200 in stored beam energy LHC Status - SUSY Bonn Damage threshold

9 Collimation To operate at nominal performance the LHC requires a large and complex collimation system Previous colliders used collimators mostly for experimental background conditions. beam 1.2 m Ensure ‘cohabitation’ of: 360 MJ of stored beam energy, super-conducting magnets with quench limits of few mJ/cm3 Almost 100 collimators and absorbers. Alignment tolerances < 0.1 mm to ensure that over 99.99% of the protons are intercepted. Primary and secondary collimators are made of Carbon to survive large beam loss. LHC Status - SUSY Bonn

10 Outline Introduction LHC energy 2010/11
LHC performance targets and achievements LHC beam operation Outlook for 2010/11 and conclusions LHC Status - SUSY Bonn

11 LHC target energy: the way down
When Why All main magnets commissioned for 7TeV operation before installation Detraining found when hardware commissioning sectors in 2008 5 TeV poses no problem Difficult to exceed 6 TeV Machine wide investigations following S34 incident showed problem with joints Commissioning of new Quench Protection System (nQPS) 7 TeV Design 12 kA 5 TeV Summer 2008 Detraining 9 kA LHC Status - SUSY Bonn Late 2008 3.5 TeV Joints Spring 2009 6 kA 1.18 TeV Nov. 2009 nQPS 2 kA 450 GeV

12 LHC target energy: the way up
When What Train magnets 6.5 TeV is in reach 7 TeV will take time Repair joints Complete pressure relief system Commission nQPS system 7 TeV 2014 ? Training 6 TeV 2013 Stabilizers LHC Status - SUSY Bonn 2011 3.5 TeV nQPS 2010 1.18 TeV 2009 450 GeV

13 Ramp rate At the start of the run the ramp rate had to be limited to 2 A/s (1.2 GeV/s) for magnet protection reasons. Ramp duration TeV: 46 minutes Since mid-July the rate for down-ramps and magnet pre-cycles (magnetic history reset) were increased to nominal value of 10 A/s (6 GeV/s). Ramp speed with beam will be increased to 10 A/s (6 GeV/s) in September. Ramp duration TeV: 16 minutes LHC Status - SUSY Bonn 3500 GeV 2 A/s 10 A/s 450 GeV

14 Outline Introduction LHC energy 2010/11
LHC performance targets and achievements LHC beam operation Outlook for 2011 and conclusions LHC Status - SUSY Bonn

15 Collider luminosity Collision rate is proportional to luminosity
Parameters: Number of particles per bunch  Number of bunches per beam kb Beam sizes at the collision point s Betatron function (focusing) at IP b* Normalized transverse emittance e Revolution frequency f Crossing angle factor F ~ 1 Intensity LHC Status - SUSY Bonn Interaction Region Beam quality (emittance) “Thus, to achieve high luminosity, all one has to do is make (lots of) high population bunches of low emittance to collide at high frequency at locations where the beam optics provides as low values of the amplitude functions as possible.” PDG 2005, chapter 25

16 Collimation performance
Present stage collimation system sets limit to total intensity. Assumptions: Max. loss rate of 0.1%/s assumed (0.2h lifetime). Ideal cleaning. Performance degradation: Deformed jaws. Tilt & offset & gap errors. Machine alignment. Machine stability Tight coll. settings are a challenge at early stage. Intermediate coll. settings make use of aperture to relax tolerances. Collimator settings LHC Status - SUSY Bonn Imax ~61013 protons per beam at 3.5TeV with intermediate collimator settings (about 20% nominal intensity) 30 MJ stored beam energy

17 Goals for 2010-2011 Collect 1 fm-1 of data/exp at 3.5 TeV/beam.
2009 2010 2011 Repair of Sector 34 1.18 TeV nQPS 6kA 3.5 TeV Isafe < I < 0.2 Inom β* ~ 3.5 m Ions ~ 0.2 Inom No Beam B Beam Goal for the run: Collect 1 fm-1 of data/exp at 3.5 TeV/beam. To achieve this goal the LHC must operate in 2011 with L ~ 2×1032 cm-2s-1 ~ Tevatron Luminosity which requires ~700 bunches of 1011 p each ~ 7x1013 p (stored energy of ~30 MJ – 10% of nominal) Implications: Strict and clean machine setup. Machine protection systems at near nominal performance.

18 Commissioning phases Phase 1: low intensity commissioning of the LHC.
Low intensity single bunches. No/very limited risk of damage. Commissioning of the protection systems. Phase 2: operation without crossing angle. Bunches with large spacing (> ms). Up to around kb=50 bunches. Simplified operation in the interaction regions. Machine protection system running in. Phase 3: operation with crossing angle. Bunches with close spacing (≤ 150 ns). Aim for ~400 bunches in 2010. LHC Status - SUSY Bonn We are at end of phase 2

19 Commissioning steps in 2010
Restart with beam. Commissioning to 3.5 TeV. Low intensity beams. First collisions at 3.5 TeV. Squeeze (b* reduction) commissioning. b* = 2 m for collisions (injection 10 /11 m). Increase number of bunches to 13 per beam. Bunch population N = 31010 p ~ 30% of nominal. Switch to nominal bunch intensity. Luminosity ~N2 Gain ~ 10 Back off in b* to 3.5 m. Loss ~ 0.6 Increase number of bunches up to 49 per beam. Bunch population N = 9-101010 p. Stability run in August with 25 bunches/beam. Feb. 28th March March 30th Mid April Mid-April – mid-May June July - August LHC Status - SUSY Bonn

20 Peak luminosity performance
Peak luminosity = 9.51030 cm-2s-1 (48 bunches/beam, 36 colliding bunches) LHC Status - SUSY Bonn 36 colliding pairs 8 colliding pairs/IR

21 Integrated luminosity
Integrated luminosity ~ 2.2 pb-1 ( ) Figures : status 16th Aug 2010 LHC Status - SUSY Bonn

22 Availability About 30% of time in physics data-taking.
A lot commissioning still on-going ! Min. turn-around time collisions to collisions ~4 hours. 3.5 TeV Energy LHC Status - SUSY Bonn 6.51030 cm-2s-1 01 – 21 August 2010 Lumi

23 Outline Introduction LHC energy 2010/11
LHC performance targets and achievements LHC beam operation Outlook for 2010/11 and conslusions LHC Status - SUSY Bonn

24 Machine Protection Extensive testing of the machine protection system was performed, mostly in March/April 2010.  20’000 signal enter the beam abort system. Only about 10% of the beams above injection energy are dumped by the operators ! LHC Status - SUSY Bonn Beam dumps > 450 GeV

25 Extraction septum magnets
Beam dump Extraction kickers Dilution kickers Extraction septum magnets Dump block Complex beam dumping system commissioned. Beam swept over dump surface (power load) LHC Status - SUSY Bonn

26 Aperture and collimation
With collisions the aperture limit of the LHC is in the strong focusing quadrupoles (triplets) that are installed just next to the experiments. Hierarchy of collimators must be preserved in all phases to avoid quenching super-conducting magnets and for damage protection. b* is presently limited to 3.5 m by aperture and tolerances. Collimation hierarchy Exp. LHC Status - SUSY Bonn Primary 6 σ Secondary 8.8 σ Dump Protection 10.5 σ Tertiary 15 σ Triplet 18 σ

27 Collimation Collimator alignment is made with beam and then monitored from the loss distribution around ring. Beam cleaning efficiencies ≥ 99.98% ~ as designed TCT = tertiary coll. LHC Status - SUSY Bonn

28 Magnet quenches A local loss of some ~107 protons/s may lead to a quench at 3.5 TeV. Compared to 51012 stored protons. So far no quench was observed at 3.5 TeV thanks to the excellent performance of the collimation system for absorbing lost protons and to the fast reaction of the loss monitors. In only 5 occasions did some beam escape and was lost locally around super-conducting elements. Beam loss detection system dumped the beams in time before a magnet could quench. Events are under investigation... Possible cause are dust particles! LHC Status - SUSY Bonn The absence of problems with beam loss and quenches is good news for increasing the beam intensity !

29 Relative beam size error
Beam Optics Beam optics is within specifications and reproducible over 3 months. A stable machine is essential to reach high intensity and minimize frequent setup overhead, in particular for collimation. Relative beam size error  (Db/b)   10% LHC Status - SUSY Bonn Specification:  0.2

30 Beam Emittance Beam emittances below nominal can be produced and injected into the LHC (e = 2 mm rad as compared to 3.5 mm rad design). This provides margin for emittance blow-up due to various noise sources – great value for a machine in early phase of operation. Momentum and magnetic fields at the LHC are sufficiently strong for the protons to emit visible light that can be used to image the beams in real-time. The energy loss per turn is 7 keV at 7 TeV, 0.4 keV at 3.5 TeV. LHC Status - SUSY Bonn Beam emittances in collisions are now mostly at design or below – the only exception being beam 2 in the vertical plane.

31 Noise on the beam The beams are periodically excited by an unknown noise source (‘hump’) of varying frequency – affects mostly beam2 in vertical plane. Amplitude ~ mm. When the frequency coincides with the beam eigen-modes (‘tunes’) it leads to emittance blow-up. Time Horizontal plane Beam 1 Beam 2 LHC Status - SUSY Bonn Tune 1 hour Noise hump Vertical plane Beam 1 Beam 2 Noise hump Frequency/Rev. frequency

32 Beam-beam interaction
Effects of the beam-beam force are visible on the lifetime of the various bunches. Also sensitive to tune working point. This will become even more complicated with trains of bunches. - black witness bunches (zero collisions); - red bunches colliding in IP 1 5 and 2 (3 collisions); - blue bunches colliding in IP 1 5 and 8 (3 collisions); - green bunches colliding in IP 2 and 8 (2 collisions). LHC Status - SUSY Bonn Beams in collision Beam1 Beam2 Intensity loss (%)

33 Lifetimes Beam intensity lifetimes with colliding beams:
Dip to 2-5 hours in first minutes. Progressive increase to ~100 hours. Luminosity lifetimes: Around hours due to emittance growth. LHC Status - SUSY Bonn Lifetime (h) Beams in collision 300 200 100

34 Present LHC parameters
Nominal Limited by N (p/bunch) 11011 1.151011 kb (no. bunches) 48 2808 Machine protection e (mm rad) 2.5-5 3.75 b* (m) 3.5 0.55 Aperture, tolerances L (cm-2s-1) 9.51030 1034 LHC Status - SUSY Bonn Squeezing at the IP (b*) is limited by aperture and tolerances. Beams are larger at 3.5 TeV ~ 1/g. sx = sy = ~45-60 mm - nominal value is 15 mm at 7 TeV. The number of bunches is limited by machine protection and by the fact that LHC is not yet operated with bunch trains. Bunch separation is large (>1 ms), no crossing angle at the IR.

35 Outline Introduction LHC energy 2010/11
LHC performance targets and achievements LHC beam operation Outlook for 2010/11 and conclusions LHC Status - SUSY Bonn

36 Fall 2010 To reach the target of 1032 cm-2s-1 an intensity increase of factor 10 is required until end of October (start of Pb ion run). But the most important is the slope of the increase! LHC Status - SUSY Bonn Switch to bunch trains 336

37 Fall 2010-2011 To reach the target of 1032 cm-2s-1,
the intensity must be increased very rapidly, bunch train operation must be commissioned (1-2 weeks). >> Achievable integrated L is ~ pb-1 in 2010. The goal is quite ambitious given the time left before the Pb ion run, but the main point is not the exact final luminosity, but rather that no problems or show-stoppers are encountered on the way. So far there are no limitations. The prospects for a very good run in 2011, 1 fm-1 of data, will be very high with a problem-free intensity (luminosity) increase in 2010. But the most important is the slope of the increase! LHC Status - SUSY Bonn

38 Summary and outlook 2011 Main beam commissioning phase of the LHC ended in June when operation with ~ nominal bunch intensities was established. The LHC is now operating for physics data taking, with some interleaved commissioning activities in view of higher intensity. Efficiency for physics data taking ~30% with peak luminosities of 9.5x1030 cm-2s-1 Machine protection and collimation systems perform well, and one can anticipate a luminosity increase towards few 1031 to 1032 cm-2s-1 in 2010. Final value for 2010 will depend on machine availability and length of commissioning bunch train operation. A long run at 1032 cm-2s-1 or above is in sight for 2011. 1 fm-1 of integrated data is in reach. LHC Status - SUSY Bonn


Download ppt "6 months of beam operation in 2010"

Similar presentations


Ads by Google