Target System Operations and Hg Handling P.T. Spampinato V.B. Graves MERIT Hg System Safety Review CERN June 19-20, 2006.

Slides:



Advertisements
Similar presentations
PressureGuard Module One - Introduction.
Advertisements

Generic Pressurized Water Reactor (PWR): Safety Systems Overview
Morgan City Rentals Diesel Jet Pump 6 x 6 Peerless Safe Operating Practices and Procedures.
Welcome to Malaga WeBex Common Rail Fuel System
© Blue Graphics Concept Sauer-Danfoss START-UP PROCEDURE PROPEL PUMP Instruction Sauer-Danfoss Belgium – T. Van Mossevelde.
Mercury Intense Target (MERIT) Update Status of the Target System Design P.T. Spampinato V.B. Graves T.A. Gabriel Muon Collaboration Friday Meeting October.
A Free Jet Hg Target Operating in a High Magnetic Field Intersecting a High Power Proton Beam Van Graves, ORNL P. Spampinato,T. Gabriel, ORNL H. Kirk,
MERIT Hg System Design V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Review Meeting Brookhaven National Laboratory Dec 12, 2005.
NTOF11 Hg System Design Status Van Graves Tony Gabriel, Phil Spampinato Collaboration Meeting – Princeton University Apr 2005.
Suction Pumps.
Harold G. Kirk Brookhaven National Laboratory The CERN Target Experiment Schedule and Budget MERIT Review BNL December 12, 2005.
Hydraulics.
MERIT Hg System Final Design Review Hg Target System Design Interfaces V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma.
Diesel Generator Reliability: Lessons Learned from Storms
Target System Transportation and Decommissioning P.T. Spampinato V.B. Graves Hg System Safety Review CERN June 19-20, 2006.
Hg System Design V.B. Graves P.T. Spampinato MERIT Hg System Safety Review CERN June 19-20, 2006.
Neutrino Factory Mercury Flow Loop V. Graves C. Caldwell IDS-NF Videoconference March 9, 2010.
Safety in the Chemical Laboratory Chemistry 550
MERIT Collaboration Meeting ISSUES RELATING TO THE Hg-JET TARGET SYSTEM P.T. Spampinato V.B. Graves T.A. Gabriel Princeton University November 17, 2005.
MERIT Hg System Design Update V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting Princeton University Nov 17-18, 2005.
N UCLEAR S CIENCE AND T ECHNOLOGY D IVISION O AK R IDGE N ATIONAL L ABORATORY U.S. D EPARTMENT OF E NERGY Muon Collider-Neutrino Factory Collaboration.
High Power Hg Target Conceptual Design Review Hg Target System Cost Estimate V.B. Graves P.T. Spampinato T.A. Gabriel Oak Ridge National Laboratory February.
CERN Hg Jet System V.B. Graves P.T. Spampinato T.A. Gabriel MUON Collaboration Meeting Lawrence Berkeley National Laboratory February 16, 2005.
Harold G. Kirk Brookhaven National Laboratory MERIT Installation Issues CERN Meeting June 20, 2006.
Mercury Nozzle Status V.B. Graves Hg Jet Design Meeting Princeton University Nov 15, 2004.
High Power Hg Target Conceptual Design Review Hg Target System Controls V.B. Graves P.T. Spampinato T.A. Gabriel Oak Ridge National Laboratory February.
High Power Hg Target Conceptual Design Review Hg Target Design P.T. Spampinato V.B. Graves T.A. Gabriel Oak Ridge National Laboratory February 7-8, 2005.
N UCLEAR S CIENCE AND T ECHNOLOGY D IVISION O AK R IDGE N ATIONAL L ABORATORY U.S. D EPARTMENT OF E NERGY Muon Collider-Neutrino Factory Collaboration.
MERIT Hg System Final Design Review Hg Target System Design V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma Science & Fusion.
MERcury Intense Target (MERIT) Overview Van Graves, ORNL Syringe Procurement Kickoff Meeting Airline Hydraulics Bensalem, PA Oct 28, 2005.
Hg System Status V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting October 20, 2006.
Mercury Catcher Status V.B. Graves Hg Jet Design Meeting Princeton University Nov 15, 2004.
Baseplates and Hg System Handling V.B. Graves P.T. Spampinato MERIT Hg System Safety Review CERN June 19-20, 2006.
High Power Hg Target Conceptual Design Review Hg Target Interface with Solenoid V.B. Graves P.T. Spampinato T.A. Gabriel Oak Ridge National Laboratory.
Hg System Decommissioning V.B. Graves P.T. Spampinato CERN Feb 7-8, 2008.
High Power Hg Target Conceptual Design Review Design Requirements, Interfaces, and Schedule P.T. Spampinato V.B. Graves T.A. Gabriel Oak Ridge National.
High Power Hg Target Conceptual Design Review Equipment Installation at CERN V.B. Graves P.T. Spampinato T.A. Gabriel Oak Ridge National Laboratory February.
Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support Facilities V.B. Graves Meeting on High Power Targets.
Mercury Chamber Considerations V. Graves IDS-NF Target Studies July 2011.
Water Tests of Hg System V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting Dec 8, 2006.
Target Design Meeting Nozzle & Hg Collection Tests, Design Requirements, Instrumentation, Containment, Windows, Diagnostics, Controls, Base Support Structure,
MODULE 7 Unload a Cargo Tank Motor Vehicle (CTMV).
Hydronic Mechanical Controls
Hydraulics For The Long Term
Lease Automatic Custody Transfer
IDS-NF Mercury System Overview Van Graves IDS-NF 5 th Plenary Meeting April 9, 2010.
NTOF11 Collaboration Meeting Non-Design Issues for the Mercury Jet Target P.T. Spampinato V.B. Graves T.A. Gabriel Princeton University April 29-30, 2005.
MERIT Hg System Final Design Review Hg Target System Operations V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma Science.
Managed by UT-Battelle for the Department of Energy Hg System Decommissioning Activities V.B. Graves NFMCC Friday Meeting Feb 29, 2008.
Release Reporting. Lesson #17 - Release Reporting How Do I Know If I Have a Leak in My UST System?
Summary of Hg System Review at CERN Van Graves 13 Sep 2005.
NFPA 31 Standard for the installation of Oil- Burning Equipment
N UCLEAR S CIENCE AND T ECHNOLOGY D IVISION O AK R IDGE N ATIONAL L ABORATORY U.S. D EPARTMENT OF E NERGY Issues Dealing With Safe Handling of Mercury.
ANL Bubble Chamber Superheated Active Target System B. DiGiovine N 2 O and C 2 F 6 as Active Fluids.
CCNA1 v3 Module 9 v3 A+ Type 2 JEOPARDY K. Martin.
Student Book © 2004 Propane Education & Research CouncilPage Reducing Cargo Tank Vapor Pressure Using a Plant Compressor In order to use.
3.4.3 Student Book © 2004 Propane Education & Research CouncilPage Bulk Plant Emergency Shutdown Equipment and Periodic Examination Methods One.
MERIT Hg System Final Design Review Hg Target System Controls V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma Science &
Radiation Protection aspects for SHIP Doris Forkel-Wirth, Stefan Roesler, Helmut Vincke, Heinz Vincke CERN Radiation Protection Group 1 st SHIP workshop,
Baseplates and Hg System Handling V.B. Graves P.T. Spampinato MERIT Hg System Safety Review CERN June 19-20, 2006.
3.1.8 Student Book © 2004 Propane Education & Research CouncilPage Identifying Procedures for Conducting Container Vapor Flaring Operations Before.
OILGEAR PVV PUMPS PVV 200 Performance Curves.
Design of the thermosiphon Test Facilities 2nd Thermosiphon Workshop
14 Refrigerant Recovery, Recycling, and Recharging.
SABRE PoP Fluid Handling
Hg System Decommissioning Activities
SB Packing Automatic Downpuller Power Unit
NEW COMPLIANCE REGULATIONS
Presentation transcript:

Target System Operations and Hg Handling P.T. Spampinato V.B. Graves MERIT Hg System Safety Review CERN June 19-20, 2006

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 2 Hg System Safety Review June 2006 Outline  Containment Boundary Leak Check  Filling and Draining Hg  Air Filtration (Hg Vapor)  Off-Normal Conditions  Equipment for Hg Handling  Equipment Maintenance

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 3 Hg System Safety Review June 2006 Containment Leak Check  Primary containment will be pressurized at ORNL with 1-atmos nitrogen prior to water tests  Each fitting and welded joint will be soap-bubble checked followed by 24-h pressure decay  Secondary containment will be pressurized with 2-3 psig nitrogen  Bulkhead penetrations, joints, and both filter/vent ports will be soap- bubble checked Primary Enclosure Secondary Enclosure

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 4 Hg System Safety Review June 2006 Containment Leak Check (cont.)  Leak check will be done again at MIT for primary and secondary but only the pressure decay test for primary containment  Same for CERN … but  … adjustments to laser optics may be required after transport  Requires opening secondary containment  Could this be done prior to installation in the MIT magnet lab, and installation in TT2A tunnel ??

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 5 Hg System Safety Review June 2006 Filling and Draining Hg  Basic Requirement: filling and draining must be achieved without opening secondary containment  Equipment Needed  Peristaltic pump  Tygon® tubing  Steel flasks/plastic bottles Secondary Enclosure Pump/Flask Setup

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 6 Hg System Safety Review June 2006 Hg Transfer By Pumping  Peristaltic pump tests with water and Hg were successfully conducted for TTF (Appendix I)  Pump flow rate for water was a maximum of ~ 0.15 liters/sec  Pump flow rate for mercury was 0.03 l/s based on ~volume and ~time measurements  The measured flow rate for Hg equates to emptying a flask in ~75 seconds

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 7 Hg System Safety Review June 2006 Hg Fill Procedure  Place the pump and flask at an elevation higher than the fill port if possible  Flask is in a gauze-lined tray  Weigh and record weight of each flask before the fill operation  Siphon Hg from the flask until suction in the tube is lost  Record the weight of the empty flask  Displaced air is vented through primary filter (and then into snorkel)  Local air is continuously sampled with the Jerome monitor  Secondary enclosure is unopened

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 8 Hg System Safety Review June 2006 Hg Drain Procedure  Place a 3-liter bottle in a gauze- lined tray under the drain port  Using the hand valve for flow control, gravity-drain Hg up to the 2-liter mark  Air will be allowed to vent into the Fill Port during the operation  Transfer 2-liters of Hg from the bottle into a flask  Install the steel plug and weigh the flask  Remove Hg remaining in the sump tank or drain line using the pump

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 9 Hg System Safety Review June 2006 Waste Materials  All waste materials generated during Hg fill and drain operations … gloves, gauze, drip shields, etc. will be double-bagged, taped and placed in the Satellite Accumulation Area (SAA)  The SAA is a 55-gal. drum, properly marked, and having a locking cover Satellite Accumulation Area

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 10 Hg System Safety Review June 2006 Air Filtration (Hg Vapor)  Secondary containment has two sulfur-impregnated charcoal filter assemblies  Primary filter is 432 x 255 x 51 mm  Secondary filter is 267 x 267 x 38 mm  Same filter as the Scavenger® snorkel  Filter ports (5”diam.) normally closed  Filter efficiency 99.9% per mfgr.  ORNL tests will verify filter effectiveness  Double filtration is possible if needed using the snorkel

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 11 Hg System Safety Review June 2006 Dose Rate Summary Table

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 12 Hg System Safety Review June 2006 Off-Normal Conditions 1) Vapor leak into secondary containment  Secondary enclosure is continuously monitored for vapor with Jerome 431-X  Monitor located in TT2 (verify remote operation with ORNL tests)  Threshold warning set for mg/m 3  If threshold level is exceeded  Check conductivity probe and other sensors incl. vapor monitor for tunnel area  If reading ok, may conclude  Minor leak from primary containment, or  False-positive signal from vapor monitor  Visually inspect w/ health physics oversight … continue beam tests

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 13 Hg System Safety Review June 2006 Off-Normal Conditions (cont.) 2) Hg leak into secondary containment  Detected by vapor monitor, conductivity probe  Confirm with visual inspection after suitable cool down period … 1 week …  Cease test operations … wait up to 1 month for Hg cool down to <10 -2 mSv/h (<1 mrem/h)  Extract Hg from target loop and refill flasks  Health Physics surveillance will be required

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 14 Hg System Safety Review June 2006 Off-Normal Conditions (cont.) 3) System Overpressure  Nozzle blockage is the only reason for a system overpressure  Not a very credible occurrence, but …  Hydraulic system pressure would increase above its nominal level of 200 bar  Pump relief valve set for 220 bar would open  Hydraulic fluid would divert from pump directly in the reservoir preventing overpressure of either the hydraulic loop or the Hg loop

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 15 Hg System Safety Review June 2006 Off-Normal Conditions (cont.) 4) Power Failure  Loss of electric power to Hg delivery system or hitting the “E-Stop” immediately shuts down the pump system  Flow of jet ceases  The possibility of a “water hammer” shock caused by the separation of flowing Hg will be investigated at ORNL

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 16 Hg System Safety Review June 2006 Off-Normal Conditions (cont.) 5) Loss of Network Connectivity  Labview® hardware has an internal system controller that provides network connectivity to the laptop computer  A “watchdog” timer detects loss of communication  If loss is detected the system is configured to power down the pump system and place the equipment in an inoperable state

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 17 Hg System Safety Review June 2006 Equipment to Support Hg Operations

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 18 Hg System Safety Review June 2006 Equipment Maintenance  There is no scheduled maintenance for the target system  Visual inspections, check performance of sensors, and test the emergency stop in the control system, will be made routinely  Initial assembly of the equipment and qualification will be done hands on at ORNL  After beam operations commence, the equipment design allows for minimal personnel contact to achieve ALARA

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 19 Hg System Safety Review June 2006 Summary and Conclusions  Experience and the procedures developed over 6 years of operating SNS/TTF are the basis for the design and operation of the MERIT target system  Target system has features that allow Hg fill/drain without opening secondary containment  Secondary containment provides the boundary for liquid Hg or vapors if a primary containment failure occurs  Contains filter assemblies to deal with displaced air during fill and drain operations  Visual inspection capability  System operating characteristics will be quantified during ORNL and MIT testing