Gwynneth Davidoff, Kendall Pletcher, Mary Schmidt, Amy Whitcombe
Timeline update from Keith LED, 10kV DC-DC converter will be sent tomorrow No readily available vacuum pump system at Olin, so it will take a week to send the MXS (with MCA and source) This moves MXS testing back a few days, giving us more time for lab testing/ making improvements See chart at /files/PERT_chart.xlsx /files/PERT_chart.xlsx
Full block diagram
What we’re doing – block diagram
Coding progress GUI: Reorganized code Looking at Brad’s code PIC: Took out unnecessary portions of Brad’s code
Next steps Continue finalizing GUI and PIC code Work on interfacing GUI and PIC Test circuits for current, temperature measurement