■ Project duration can be reduced by assigning more resources to project activities. ■ However, doing this increases project cost. ■ Decision is based.

Slides:



Advertisements
Similar presentations
Project Scheduling: PERT-CPM
Advertisements

WOOD 492 MODELLING FOR DECISION SUPPORT
Introduction to Management Science
CPM, Crashing, Resource Leveling using MS Excel & MS Project
WOOD 492 MODELLING FOR DECISION SUPPORT Lecture 22 Network Problems.
Project Management Operations -- Prof. Juran. 2 Outline Definition of Project Management –Work Breakdown Structure –Project Control Charts –Structuring.
PERT/CPM Models for Project Management
Chapter 9: Reducing Project Duration
Reducing Project Duration
Chapter 7 Networks and Scheduling Project Management for Business, Engineering, and Technology.
Reducing Project Duration
Project Management An interrelated set of activities with definite starting and ending points, which results in a unique outcome for a specific allocation.
EMGT 501 HW # Due Day: Sep 27.
EMGT 501 HW #2 Answer. 020/3 X 3 05/601-1/62/3050/3 X 6 0-5/300-2/3-1/3180/3 (c).3/230with )3/80,0,0,3/50,3/20,0(*)*, ( solution Optimal   Z.
EMGT 501 HW #2 Solutions Chapter 6 - SELF TEST 21 Chapter 6 - SELF TEST 22.
Project Scheduling The Critical Path Method (CPM).
Roberta Russell & Bernard W. Taylor, III
Time-Cost Trade-Off (Time Reduction = Time Compression = Time Shortening) 4/17/ :55 AM.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
CEM 514 Modeling of Construction Operations The LP/IP hybrid method for construction time-cost trade-off analysis By Samir Abdallah Sulaiman.
Analyzing Cost-Time Trade-Offs There are always cost-time trade-offs in project management. – You can completing a project early by hiring more workers.
Copyright 2006 John Wiley & Sons, Inc. Project Management OPIM 310.
Network Optimization Models
Project Management Chapter 8.
ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Example 2 nd Semester 2010/2011 Eng:
Project Management Chapter 8 (Crashing).
Projects CHAPTER 10. Learning Objectives 1. Explain what project management is and why it is important. 2. Identify the different ways projects can be.
Network Planning Methods Example PERT & CPM
1 Project Management Chapter Lecture outline Project planning Project scheduling Project control CPM/PERT Project crashing and time-cost trade-off.
Lean Project Management
Time/Cost Trade-off Analysis
Chapter 9: Reducing Project Duration
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 17 Project Management Part.
Time-Cost Trade-Off (Time Reduction = Time Compression) (Time Shortening) Time-Cost Trade-Off (Time Reduction = Time Compression) (Time Shortening)
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Project Management - PERT/CPM What is project management? Consider building a house: Step A: Prepare site. (5 days) Step B: Build foundation. (8 days)
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 6 Project Management To Accompany.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Reducing Project Duration CHAPTER NINE Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Reducing Project Duration CHAPTER NINE Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Project Planning and Budgeting Recall the four stages Project Definition and Conceptualization Project Planning and Budgeting Project Execution and Control.
1 6. T IME -C OST O PTIMIZATION Objective: The optimization of project duration and cost by an appropriate crashing of activities. Summary: 6.1 Finding.
TOPIC-6- TIME-COST TRADE OFF
Chapter 7 Schedule Control. 22 Learning Objectives  Perform the steps in the project control process  Determine the effects of actual schedule performance.
McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 10 Projects.
3/18/ :47 AM 1 Time-Cost Trade-Off (Time Reduction = Time Compression = Time Shortening)
Chapter 8 - Project Management1 Lecture 2 Today’s lecture covers the followings: 1.To study “project crashing” concept 2.LP formulation for project management.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Time-Cost Trade-off Models
PERT / CPM – Time-Cost Tradeoffs BSAD 30 Dave Novak Source: Anderson et al., 2015 Quantitative Methods for Business 13 th edition – some slides are directly.
Project Management 6e..
Reducing Project Duration
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
Project Management Chapter 8.
Project Management Chapter Topics
Project Management Operations -- Prof. Juran.
Project Management: PERT/CPM
Project Planning & Scheduling
Reducing Project Duration
Project Planning & Scheduling
Chapter 8 - Project Management
Project Planning and Budgeting
Probabilistic Time Estimates
Project Management Operations -- Prof. Juran.
Basic Project Scheduling Line of Balance
Lecture 6: Time-Cost Trade-Offs
Where We Are Now. Where We Are Now Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity.
Where We Are Now. Where We Are Now Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity.
Where We Are Now. Where We Are Now Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity.
Presentation transcript:

■ Project duration can be reduced by assigning more resources to project activities. ■ However, doing this increases project cost. ■ Decision is based on analysis of trade-off between time and cost. ■ Project crashing is a method for shortening project duration by reducing one or more critical activities to a time less than normal activity time. Project Crashing and Time-Cost Trade-Off Overview 9-Jun-15Dr.Bokkasam Sasidhar1

The Project Network House Building Project Data NumberActivityPredecessorDuration 1Design house and obtain financing --12 months 2Lay foundation18 months 3Order and receive materials 14 months 4Build house2,312 months 5Select paint2, 34 months 6Select carper54 months 7Finish work4, 64 months 9-Jun-15Dr.Bokkasam Sasidhar2

Project Crashing and Time-Cost Trade-Off Example Problem The project network for building a house

Normal activity and crash data for the network Project Crashing and Time-Cost Trade-Off Example Problem

Project Crashing and Time-Cost Trade-Off Example Problem Time-cost relationship for crashing activity 1 Crash cost & crash time have a linear relationship 9-Jun-15Dr.Bokkasam Sasidhar5

Network with normal activity times and weekly crashing costs Project Crashing and Time-Cost Trade-Off Example Problem

Revised network with activity 1 crashed Project Crashing and Time-Cost Trade-Off Example Problem As activities are crashed, the critical path may change and several paths may become critical.

Project Crashing and Time-Cost Trade-Off QM for Windows Output

Project Crashing and Time-Cost Trade-Off QM for Windows

Project Crashing and Time-Cost Trade-Off General Relationship of Time and Cost ■ Project crashing costs and indirect costs have an inverse relationship. ■ Crashing costs are highest when the project is shortened. ■ Indirect costs increase as the project duration increases. ■ The optimal project time is at the minimum point on the total cost curve. 9-Jun-15Dr.Bokkasam Sasidhar10

Project Crashing and Time-Cost Trade-Off General Relationship of Time and Cost The time-cost trade-off 9-Jun-15Dr.Bokkasam Sasidhar11

Example 9-Jun-15Dr.Bokkasam Sasidhar12 Sharon Lowe, Vice President for Marketing for the Electronic Toys Company, is about to begin a project to design an advertising campaign for a new line of toys. She wants the project completed within 47 days in time to launch the advertising campaign at the beginning of the Christmas season. Sharon has identified the six activities (labeled A, B, …, F) needed to execute this project. Considering the order in which these activities need to occur, she also has constructed the following project network.

Example (Contd.) 9-Jun-15Dr.Bokkasam Sasidhar13

Example (Contd.) 9-Jun-15Dr.Bokkasam Sasidhar14 Activity Time (days)CostMaximum Reduction in Time Crash Cost per day saved NormalCrashNormalCrash A129$210,000$270,0003$20,000 B2318$410,000$460,0005$10,000 C1512$290,000$320,0003$10,000 D2721$440,000$500,0006$10,000 E1814$350,000$410,0004$15,000 F64$160,000$210,0002$25,000 To meet the deadline of 47 days, Sharon has decided to crash the project, using the CPM method of time-cost trade- offs to determine how to do this in the most economical way. She has gathered the data needed to apply this method, as given below.

Example - Solution 9-Jun-15Dr.Bokkasam Sasidhar15 The upper path is A-C-E-F with a path length of 51 days. Of the activities on the path, activity C has the smallest crash cost per day saved ($10,000) and activity E is next ($15,000). Activity C can only be reduced by 3 days, so activity E also will need to be crashed somewhat. Therefore, we find that the most economical way of reducing the length of this path to 47 days is to shorten activity C by 3 days and activity E by 1 day with an additional total cost of $45,000. Activity to crashCrash CostLength of Path A-C-E-F 51 C$10,00050 C$10,00049 C$10,00048 E$15,00047

Example - Solution 9-Jun-15Dr.Bokkasam Sasidhar16 The lower path is B-D with a path length of 50 days. From the time-cost trade-off data, both activities B and D have a crash cost per day saved of $10,000, and both can be reduced by more than 3 days. Therefore, using marginal cost analysis, we find that the most economical way of reducing the length of this path to 47 days is to shorten either activity (it doesn’t matter which one) by 3 days with an additional total cost of $30,000. Activity to crashCrash CostLength of Path B-D 50 B or D$10,00049 B or D$10,00048 B or D$10,00047

Example - Solution 9-Jun-15Dr.Bokkasam Sasidhar17 Combining both the results, the total crashing cost for the optimal way of meeting the deadline of 47 days is $30,000 + $45,000 = $75,000.