Lecture 3 Earthmoving Materials

Slides:



Advertisements
Similar presentations
CTC-275 Construction Methods
Advertisements

 Soil compaction :  Compaction is the reduction in voids content due to air being forced out of the soil or dissolved in the soil water by mechanical.
ENGINEERING MATERIAL PROPERTIES (CE1303)
Earthwork Operations & Equipments
3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine.
Lecture 4 Excavating and Lifting
Eng. Malek Abuwarda Lecture 8 P1P1 Construction Methods Lecture 8 Loading and Hauling.
Lecture 7 Loading and Hauling
Chapter 3 Measuring Excavation and Sitework
Measuring Sitework, Excavation, and Piling
Earthmoving Materials and Operations
Earthwork QTO Stage 1 Preconstruction Stage 2: Procurement
Chapter 3 Compaction. To improve the density and other properties of soil Increases the solid density improves strength Lowers its permeability Reduces.
Introduction to Soil Mechanics
ESTIMATING EARTHWORK Prof Awad S. Hanna.
Excavating and Lifting Part 2
Lecture (4). The presence of clay minerals in a fine-grained soil will allow it to be remolded in the presence of some moisture without crumbling. If.
CTC-375 Construction Methods
Earthmoving Materials and Operations
ENGINEERING SURVEYING & PHOTOGRAMMETRY CVE 314
Land levelling design methods - plane method
ENCI 5791 Compaction In-situ soils used as: –Bases for the construction of highway pavements –embankments or leveling material for construction projects.
Engineering Properties of Soils Soil Types
CE 453 Lesson 24 Earthwork and Mass Diagrams
5. Soil Consistency (Plasticity)
Earthwork: Use of Fine Grained & Granular Material.
Estimating Ahmed Elyamany, PhD, AVS. EARTHWORK AND EXCAVATION bank  Earth that is to be excavated is called bank measure. loose  Earth that is to be.
Construction Methods Lecture 9 Compacting Lecture 9.
CHAPTER TWO SOIL COMPRESSION.
Eng. Malek Abuwarda Lecture 11 P1P1 Construction Methods Lecture 11 Compaction Equipment and Procedures.
Lecture 6 Loading and Hauling
4. Phase Relations (Das, Chapter 3) Sections: All except 3.6
Calculations On completion of this unit the Learner should be able to demonstrate an understanding of: The formula used to calculate: Areas Volumes Ratios.
Areas and Volumes Introduction Faculty of Applied Engineering and Urban Planning Civil Engineering Department 2 nd Semester 2008/2009 Surveying.
Wes Marshall, P.E. University of Connecticut March 2007
Lecture 2 Introduction to Earthmoving
Planning for Earthwork Construction
Team Assignments C D A B Clayten Greenwell Ryan Franklin Elliot Magoto
Centroids and Centers of Gravity
Soil and Earth Works Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lecture 3 - Week 2 2 nd Semester 2008/2009 UP Copyrights.
Road Construction Technology
Highway Subgrade (1) Introduction
9.6 Fluid Pressure According to Pascal’s law, a fluid at rest creates a pressure ρ at a point that is the same in all directions Magnitude of ρ measured.
GEO-MECHANICS (CE2204) Engineering Properties of Soils
ESTIMATING EARTHWORK DR. Nabil Dmaidi.
Earthwork & Volumes Spec Requirements End Areas End-area Volumes
Soil and Rock Soil and rock are the principle components of many construction projects. Knowledge of their properties, characteristics, and behavior is.
Soil And Rock General Soil Characteristics Trafficability – ability of soil to support weight of vehicles under repeated traffic –Controls traffic on unimproved.
4. Properties of Materials Sediment (size) Physical States of Soil Concepts of Stress and Strain Normal and Shear Stress Additional Resistance Components.
Mass Diagrams Balance Cuts and Fills Shrink/swell Mass Diagram Cost Analysis.
© Awad S. Hanna, PhD, P.E.1 Estimating and Scheduling CEE 492 Lecture 5 ESTIMATING EARTHWORK.
PILE FOUNDATIONS UNIT IV.
SOIL MECHANICS AND CLASSIFICATION. FACTORS WHICH HOLD SOIL TOGETHER o Cohesion  Internal Friction.
Soil Classification Prof. Basuony El-Garhy
Sanitary Engineering Lecture 10 Revision
Highway Engineering CE 431
Site Grading of Terrace
Calculating Cut and Fill
5. WEIGHT VOLUME RELATIONSHIPS
CONSTRUCTION METHODS & TECHNOLOGY
Distributed Forces: Centroids and Centers of Gravity
Distributed Forces: Centroids and Centers of Gravity
FBE05 – Mathematics and Statistics
Pavement materials: Soil
ESTIMATING EARTHWORK Prof Awad S. Hanna.
Introduction Persons engaged in surveying are often called to determine volumes of various types of material. The most common unit of volume is cubic having.
BET403 Cost Engineering Individual Assignment & Group Report
ESTIMATING EARTHWORK Prof Awad S. Hanna.
Presentation transcript:

Lecture 3 Earthmoving Materials Construction Methods Lecture 3 Earthmoving Materials Lecture3

General Soil Characteristics Trafficability Trafficability is the ability of a soil to support the weight of vehicles under repeated traffic. In construction, trafficability controls the amount and type of traffic that can use unimproved access road. Usually expressed qualitatively Primarily a function of soil type and moisture conditions. Loadability It is a measure of the difficulty in excavating and loading a soil Loose granular soils are highly loadable, whereas compacted cohesive soils and rock have low loadability. Lecture 3

General Soil Characteristics Soil unit weight Unit soil weight is normally expressed in ton per cubic meter and it depends on soil type, moisture content and degree of compaction. Moisture content The moisture content of a soil is expressed as a percentage that represents the weight of water in the soil divided by the dry weight of the soil: Example A soil sample weighted 54.4 kg in the nature state and 45.3 kg after drying The moisture content would be: Moist weight – Dry weight Dry weight  100 Moisture content % = 54.4 – 45.3 45.3  100 = 20% Moisture content % = Lecture 3

Soil Identification and Classification Soil types: Gravel: particles about 6mm to 76mm in diameter Sand: particles about 0.7mm to 6mm in diameter Silt: particles about 0.002mm to 0.7mm in diameter Clay: particles less than 0.002 Organic material: soil contain partially decomposed vegetable matter Soil classification systems Unified System AASHTO System Lecture 3

Soil Identification and Classification Unified System Lecture 3

Soil Identification and Classification AASHTO System Lecture 3

Soil Identification and Classification Construction Characteristics of Soil Lecture 3

Soil Volume Change Characteristics Soil Condition Bank: material in its natural state before disturbance Loose: material that has been excavated or loaded Compacted: material after compaction Swell The unit volume of soil in the bank condition will occupy more than one unit volume after excavation. Weight of bank volume Swell% = -1  100 Weight of loose volume Lecture 3

Soil Volume Change Characteristics Example Find the swell of a soil that weight 1661 kg/m3 in its natural state and 1186 kg/m3 after excavation. Swell% Lecture 3

Soil Volume Change Characteristics Shrinkage The soil will occupy less volume than it did under either the bank or loose conditions. Example Find the shrinkage of a soil that weight 1661 kg/m3 in its natural state and 2077 kg/m3 after compaction Hence 1 bank cubic meter of material will shrink to 0.8 compacted cubic meter as a result of compaction. Lecture 3

Soil Volume Change Characteristics Load and Shrinkage Factors A factor used for the conversion of loose volume to bank volume is referred to as load factor. A factor used for the conversion of bank volume to compacted volume is referred to as shrinkage factor. Lecture 3

Soil Volume Change Characteristics Example A soil weighs 1163 kg/LCM, 1661 kg/BCM), and 2077 kg/CC (a) Find the load factor and shrinkage factor for the soil. (b) How many bank cubic meters (BCM) and compacted cubic meters (CCM) are contained in 1 million loose cubic meters of this soil? Solution (a) (b) Lecture 3

Soil Volume Change Characteristics Typical values of unit weight, swell, shrinkage, load factor, and shrinkage factor for some common earthmoving materials Lecture 3

Spoil Banks Spoil Banks Spoil banks are characterized by a triangular cross section. If the material is dumped from a fixed position, a spoil pile is created which has a conical shape. To determine the dimensions of spoil banks or piles, it is first necessary to convert the volume of excavation from in-place conditions (BCM) to loose conditions (LCM). A soil's angle of repose is the angle that the sides of a spoil bank or pile naturally form with the horizontal when the excavated soil is dumped on to the pile. The angle of repose varies with the soil's physical characteristics and its moisture content. Lecture 3

Spoil Banks Typical values of angle of repose for common soils Triangular Spoil Bank Lecture 3

Spoil Banks Conical Spoil Pile Lecture 3

Spoil Banks Example Solution Find the base width and height of a triangular spoil bank containing 76.5 BCM if the pile length is 9.14 m, the soil's angle of repose is 37°, and its swell is 25%. Solution Lecture 3

Spoil Banks Example Solution Find the base diameter and height of a conical spoil pile that will contain 76.5BCM of excavation if the soil's angle of repose is 32° and its swell is 12%. Solution Lecture 3

Estimating Earthwork Volume The procedures to estimating an earthmoving can be divided into three principal categories: (1) pit excavations (small, relatively deep excavations such as those required for basements and foundations), (2) trench excavation for utility lines, and (3) excavating or grading relatively large areas. Pit Excavations Volume = Horizontal area  Average depth first divide the horizontal area into a convenient set of rectangles, triangles, or circular segments. the total area is found as the sum of the segment areas. The average depth is then calculated. Lecture 3

Estimating Earthwork Volume Example Estimate the volume of excavation required (bank measure) for the basement shown. Values shown at each comer are depths of excavation. All values are in meter. Solution Lecture 3

Estimating Earthwork Volume Trench Excavations Volume = Cross-sectional area  Length Example Find the volume (bank measure) of excavation required for a trench 0.92 m wide, 1.83 m deep, and 152 m long. Assume that the trench sides will be approximately vertical. Solution Lecture 3

Estimating Earthwork Volume Large Areas Divide the area into a grid indicating the depth of excavation Assign the depth at each comer or segment intersection a weight according to its location Interior points (intersection of four segments) are assigned a weight of four, exterior points at the intersection of two segments are assigned a weight of two, and comer points are assigned a weight of one. Lecture 3

Estimating Earthwork Volume Example Find the volume of excavation required for the area shown. The figure at each grid intersection represents the depth of cut at that location. Lecture 3

Estimating Earthwork Volume Solution Lecture 3

Estimating Earthwork Volume Construction use of the mass diagram A mass diagram is a continuous curve representing the accumulated volume of earthwork plotted against the linear profile of a roadway or airfield Lecture 3

Estimating Earthwork Volume Characteristics of a Mass Diagram The vertical coordinate of the mass diagram corresponding to any location on the roadway profile represents the cumulative earthwork volume from the origin to that point. Within a cut, the curve rises from left to right. Within a fill, the curve falls from left to right. A peak on the curve represents a point where the earthwork changes from cut to fill. A valley (low point) on the curve represents a point where the earthwork changes from fill to cut. When a horizontal line intersects the curve at two or more points, the accumulated volumes at these points are equal. Thus, such a line represents a balance line on the diagram. Lecture 3

Estimating Earthwork Volume Lecture 3

Estimating Earthwork Volume Using the Mass Diagram The length and direction of haul within a balanced section. The average length of haul for a balanced section. The location and amount of borrow (material hauled in from a borrow pit) and waste (material hauled away to a waste area) for the project. Type of equipment that should be considered for accomplishing the work. Lecture 3

Estimating Earthwork Volume Example: Find the following values. The total volume of cut, fill, waste and borrow The average length of haul Lecture 3