3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine.
Lecture 4 Excavating and Lifting
Draglines and Clamshells
Eng. Malek Abuwarda Lecture 8 P1P1 Construction Methods Lecture 8 Loading and Hauling.
Loading and Hauling Part 3
Lecture 7 Loading and Hauling
Front End Loader Costs ©Dr. B. C. Paul 2000 Start Detailed Economic Comparison of 3 machines l Strategy Go Through Each Machine and Figure the Cost Compare.
Front shovel, back hoe and loader. Group member: Lam Wai Kei Hui Tan La
Chapter 3 Measuring Excavation and Sitework
Excavating and Lifting Hmwk Ch 2 # 1,2,5,8 Ch 3 #2,4,6,10.
Earthmoving Materials and Operations
TRUCKS THE MOST COMMON HAULING EQUIPMENT USED FOR MILITARY CONSTRUCTION SITE ARE 2 1/2, 5, AND 20 TON DUMP TRUCKS. THE HAUL CAPACITY CAN BE EXPRESSED.
Earthwork QTO Stage 1 Preconstruction Stage 2: Procurement
Matching An Excavator to Our Trucks ©2009 Dr. B. C. Paul Note – These Slides contain tables and information found in the Caterpillar Performance Handbook.
ESTIMATING EARTHWORK Prof Awad S. Hanna.
Eng. Malek Abuwarda Lecture 5 P1P1 Construction Methods Lecture 5 Excavating and Lifting.
1 Cranes Module 13. 2Objectives After this module you should be able to – identify the most common crane hazards – take the necessary steps to avoid those.
Excavating and Lifting Part 3
Lecture 3 Earthmoving Materials
CTC-375 Construction Methods
CE 453 Lesson 24 Earthwork and Mass Diagrams
Loading and Hauling Part 1
Estimating Ahmed Elyamany, PhD, AVS. EARTHWORK AND EXCAVATION bank  Earth that is to be excavated is called bank measure. loose  Earth that is to be.
Excavating and Lifting Part 1
Loading and Hauling Part 2
Lecture 6 Loading and Hauling
CONSTRUCTION TECHNOLOGY & maintenance
TYPES OF CONSTRUCTION MACHINERY. FOLLOWING ARE THE MAJOR TYPES OF EQUIPMENTS THAT IS BEING USED IN THE CONSTRUCTION INDUSTRY.
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display. Chapter 6 Machine Equipment Power Requirements.
Compaction and Stabilization Equipment
Wes Marshall, P.E. University of Connecticut March 2007
Lecture 2 Introduction to Earthmoving
Planning for Earthwork Construction
SHOVELS.
Horticulture CD Unit C 6-3: Nursery, Landscaping, and Gardening.
Session 15 – 16 SHEET PILE STRUCTURES
Matching Shovels ©Dr. B. C. Paul 2000 revised 2008 Note – Matching procedures depicted in these slides are widely understood among those schooled in the.
Soil Compaction Topic I Topic I.
Step #1 Matching ©Dr. B. C. Paul 2000 revised 2008 Note many of the ideas expressed in these slides can be found in Surface Mining Manuals, the Book Surface.
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display. Chapter 7 Dozers.
ESTIMATING EARTHWORK DR. Nabil Dmaidi.
نظام المحاضرات الالكترونينظام المحاضرات الالكتروني Construction Methods By Ruqaya ALZubaidi.
Soil And Rock General Soil Characteristics Trafficability – ability of soil to support weight of vehicles under repeated traffic –Controls traffic on unimproved.
Chapter 4 Loading and Hauling Part 3 1CE 417 King Saud University.
Simple Machines WHEEL AND AXLE PULLEYS. The Wheel and Axle The wheel and axle is another type of simple machine that moves objects across distances. Wheels.
C.K. PITHAWALA COLLEGE OF ENGINEERING & TECHNOLOGY
SITE INVESTIGATION ARUN MUCHHALA ENGINEERING COLLEGE-DHARI
Excavation and lifting Excavator: Power driven digging machine Types 1. Hydraulic excavator 2. Cable operated excavator 3. Shovel 4. Draglines 5. Hoes.
Interpreting a contour map
EXAMPLE A 400 m2 (40 x 10 m) area is to be excavated, 1 m deep, with side slopes 2:1. As the width (10 m) is less than 30 times the depth (30 x 1 m), the.
Site Grading Site Grading Civil Engineering and Architecture
CONSTRUCTION METHODS & TECHNOLOGY
CONSTRUCTION METHODS & TECHNOLOGY
SAB 3122 CONSTRUCTION TECHNOLOGY AND ESTIMATING Excavation
Flexible pavement design
Lecture 7 Excavators TSP-308 MPK Ferdinand Fassa.
Lecture 6 scrapers TSP-308 MPK Ferdinand Fassa.
CONSTRUCTION EQUIPMENT MANAGEMENT
Lecture 5 Dozer TSP-308 MPK Ferdinand Fassa.
MUHAMMAD WAJAHAT AMIN (INTERNEE, MINE PLANNING) OPEN PIT MINING TOPICS.
ESTIMATING EARTHWORK Prof Awad S. Hanna.
ESTIMATING EARTHWORK Prof Awad S. Hanna.
Presentation transcript:

Excavating and Lifting Part 2 Chapter 3 Excavating and Lifting Part 2

3-4 DRAGLINES Operation and Employment Production Estimating Job Management

Operation and Employment The dragline : It is a very versatile machine that has the longest reach for digging and dumping of any member of the crane-shovel family. It can dig from above machine level to significant depths in soft to medium-hard material. The components of a dragline are shown in Figure 3-10.

FIGURE 3-10: Components of a dragline.

3-4 DRAGLINES Bucket teeth and weight produce digging action as the drag cable pulls the bucket across the ground surface. Digging is also controlled by the position at which the drag chain is attached to the bucket (Figure 3-11).

FIGURE 3-11: Dragline bucket.

3-4 DRAGLINES It is a very versatile excavator, it does not have the positive digging action or lateral control of the shovel. Because of that: the bucket may bounce or move sideways during hard digging. More spillage must be expected in loading than would occur with a shovel.

3-4 DRAGLINES The maximum bucket size to be used on a dragline depends on machine power, boom length, and material weight. Therefore, use the dragline capacity chart provided by the manufacturer instead of the machine's lifting capacity chart to determine maximum allowable bucket size.

3-4 DRAGLINES To estimate dragline production using the tables, determine the ideal output of the dragline for the machine size and material (Table 3-7), then adjust this figure by multiplying it by a swing-depth factor (Table 3-9) and a job efficiency factor, as shown in Equation 3-3. Expected production = Ideal output × Swing-depth factor × Efficiency (3-3) Notice the conditions applicable to Table 3-7 given in the footnote..

3-4 DRAGLINES To use Table 3-9, it is first necessary to determine the optimum depth of cut for the machine and material involved from Table 3-8. Next, divide the actual depth of cut by the optimum depth and express the result as a percentage.

3-4 DRAGLINES The appropriate swing-depth factor is then obtained from Table 3-9, interpolating as necessary. The method of calculating expected hourly production is illustrated in Example 3-4.

EXAMPLE 3-4 Determine the expected dragline production in loose cubic yards (LCM) per hour based on the following information. Dragline size = 2 cu yd (1.53 m3) Swing angle = 120o Average depth of cut = 7.9 ft (2.4 m) Material = common earth Job efficiency = 50 min/h Soil swell = 25%

EXAMPLE 3-4 Solution Ideal output =230 BCY/h (176 BCM/h) (Table 3-7) Optimum depth of cut = 9.9 ft (3.0 m) (Table 3-8) Actual depth/optimum depth = 7.9/9.9 × 100 = 80% [= 2.4/3.0 × 100 = 80%]

EXAMPLE 3-4 Swing-depth factor=0.90 (Table 3-9) Efficiency factor =50/60 = 0.833 Volume change factor = 1 + 0.25 = 1.25 Estimated production = 230 × 0.90 × 0.833 ×1.25 = 216 LCY/h [= 176 × 0.90 × 0.833 ×1.25 = 165 LCM/h]

Job Management Trial operations may be necessary to select: the boom length, boom angle, bucket size and weight, and the attachment position of the drag chain that yield maximum production. As in shovel operation, maximum production is obtained with a minimum swing angle.

Job Management Special bucket hitches are available which shorten the drag distance necessary to obtain a full bucket load. Deep cuts should be excavated in layers whose thickness is as close to the optimum depth of cut as possible.

3-5 CLAMSHELLS Operation and Employment Production Estimating Job Management

3-5 CLAMSHELLS Operation and Employment When the crane-shovel is equipped with a crane boom and clamshell bucket, it becomes an excavator known as a clamshell. The clamshell is capable of excavating to great depths. The shovel and backhoe is better than clamshell because of : lacks the positive digging action and precise lateral control.

FIGURE 3-13: Components of a Clamshell

3-5 CLAMSHELLS Clamshells are commonly used for: excavating vertical shafts and footings, unloading bulk materials from rail cars and ships, and moving bulk material from stockpiles to bins, hoppers, or haul units.

FIGURE 3-14: Clamshell bucket

3-5 CLAMSHELLS Bucket penetration depends on bucket weight assisted by the bucket teeth. Therefore, buckets are available in light, medium, and heavy weights, with and without teeth. Heavy buckets: are suitable for digging medium soils. Medium buckets: are used for general-purpose work, including the excavation of loose soils. Light buckets: are used for handling bulk materials such as sand and gravel.

3-5 CLAMSHELLS The orange peel bucket illustrated in Figure 3-15 is principally utilized for underwater excavation and for rock placement. Because of its circular shape, it is also well suited to excavating piers and shafts. It operates on the same principle as does the clamshell.

FIGURE 3-15: Orange peel bucket. (Courtesy of ESCO Corporation)

3-5 CLAMSHELLS Production Estimating No standard production tables are available for the clamshell. Thus production estimation should be based on the use of Equation 2-1. The procedure is illustrated in Example 3-5.

EXAMPLE 3-5 Estimate the production in loose cubic yards per hour for a medium-weight clamshell excavating loose earth. Heaped bucket capacity is 1 cu yd (0.75 m3). The soil is common earth with a bucket fill factor of 0.95. Estimated cycle time is 40 s. Job efficiency is estimated at 50 min/h.

EXAMPLE 3-5 Solution Production = 3600/40 × 1 × 0.95 × 60/50 = 71 LCY/h B = 3600/40 × 0.75 × 0.95 × 60/50 = 53 LCM/h

Job Management The maximum allowable load (bucket weight plus soil weight) on a clamshell should be obtained from the manufacturer's clamshell loading chart for continuous operation.

Job Management limit the load to 80% of the safe lifting capacity given by the crane capacity chart for rubber- tired equipment or 90% for crawler-mounted equipment. use of the lightest bucket capable of digging the material will enable a larger bucket to be used and will usually increase production.

Job Management Cycle time is reduced by organizing the job so that the dumping radius is the same as the digging radius. Keep the machine level to avoid swinging uphill or downhill. Nonlevel swinging is hard on the machine and usually increases cycle time.